- Internal Finishes – Flooring – BF 1, BF 2, GF 100% to be completed, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor, 12th floor 100% to be completed, Wall Tile work – 5th floor , 6th floor , 7th,8th,9th,10th,11th,12th floor, 13th floor, 14th floor, 15th floor, 16th floor – 100% to be completed, Ramp tiling – 90% to be completed, Terrace 100% to be completed, Handrail – Mainstair handrail – 100% to be completed, Painting – 1st and 2nd coat emulsion 10 flats to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – BF-1, BF-2 floor to be completed, Centralised gas piping work – 100% to be completed
- Final Finishes – Final painting – 10 flats to be completed for the month of August 24 Plumbing and Sanitary wares – 10 flats to be completed, Electrical final fixtures – 10 more flats to be completed
- External Finishes- Windows and sliding doors -30% more to be completed, External painting – 2nd coat painting – 100% to be completed
Work status as on 09-07-2024, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
- Internal Finishes- Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, BF 1 floor – 90% completed, BF-2 Floor – 60% completed, GF – 90% completed, 1st floor – completed, 2nd floor – 95% completed, 3rd floor – 95% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 90% completed, 13th floor – 90% completed, 14th floor – 90% completed, 15th floor – 90% completed, 16th floor – 90% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 90% completed, 13th floor – 90% completed , 14th floor – 90% completed, 15th floor – 90% completed, 16th floor – 95% completed, Passage tiling – BF -2 to terrace floor completed, Ramp tiling – 80% completed, terrace – 90% completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, 1st and 2nd coat emulsion – 11 flats completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 90% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 16th floor completed, flush tank fixing 1st to 16th floor completed, Centralised gas piping work – 95% completed, fire fighting final fixtures completed
- Final Finishes – Door shutters & ironmongery – 27 flats Completed, Final painting – 11 flats completed, Plumbing and Sanitary wares – 11 flats completed, Electrical final fixtures – 23 flats completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – 1st coat painting completed, 2nd coat painting – 65% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2024.
ARTECH METROPOLIS (TOWER-2)
-
- Internal Finishes – Flooring – BF 1, BF 2, GF 100% to be completed, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor, 12th floor 100% to be completed, Wall Tile work – 5th floor , 6th floor , 7th,8th,9th,10th,11th,12th floor, 13th floor, 14th floor, 15th floor, 16th floor – 100% to be completed, ramp tiling – 90% to be completed, terrace 100% to be completed, Handrail – Mainstair handrail – 100% to be completed, painting – 1st and 2nd coat emulsion 10 flats to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – BF-1, BF-2 floor to be completed, Centralised gas piping work – 100% to be completed
- Final Finishes – Door shutters & ironmongery – 10 more flats to be completed, Final painting – 10 more flats to be completed, Plumbing and Sanitary wares – 8 more flats to be completed, Electrical final fixtures – 5 more flats to be completed
- External Finishes- Windows and sliding doors -30% more to be completed, External painting – 2nd coat painting – 100% to be completed
Work status as on 11-06-2024, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
- Internal Finishes- Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, BF 1 floor – 90% completed, BF-2 Floor – 60% completed, GF – 90% completed, 1st floor – completed, 2nd floor – 95% completed, 3rd floor – 95% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 90% completed, 13th floor – 90% completed, 14th floor – 90% completed, 15th floor – 90% completed, 16th floor – 90% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 90% completed, 13th floor – 90% completed , 14th floor – 90% completed, 15th floor – 90% completed, 16th floor – 95% completed, Passage tiling – BF -2 to terrace floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 90% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 16th floor completed, flush tank fixing 1st to 16th floor completed, Centralised gas piping work – 85% completed, fire fighting final fixtures completed
- Final Finishes – Door shutters & ironmongery – 20 flats Completed, Final painting – 10 flats completed, Plumbing and Sanitary wares – 9 flats completed, Electrical final fixtures – 13 flats completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – 1st coat painting completed, 2nd coat painting – 65% completed
- Mockup- Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
ARTECH METROPOLIS (TOWER-2)
-
- Internal Finishes – Flooring – BF 1, BF 2, GF 100% to be completed, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor, 12th floor 100% to be completed, Wall Tile work – 5th floor , 6th floor , 7th,8th,9th,10th,11th,12th floor, 13th floor, 14th floor, 15th floor, 16th floor – 100% to be completed, Handrail – Mainstair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – BF-1, BF-2 floor to be completed, Centralised gas piping work – 15% more to be completed
- Final Finishes – Final painting – 5 more flats to be completed, Plumbing and Sanitary wares – 4 more flats to be completed, Electrical final fixtures – 5 more flats to be completed
- External Finishes- Windows and sliding doors -30% more to be completed, External painting – 2nd coat painting – 100% to be completed
Work status as on 09-05-2024, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Civil Works- Ceiling plaster completed, wall plastering upto 16th floor completed, Machine room plastering completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes- Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, BF 1 floor – 90% completed, BF-2 Floor – 60% completed, GF – 90% completed, 1st floor – completed, 2nd floor – 95% completed, 3rd floor – 95% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 90% completed, 13th floor – 90% completed, 14th floor – 90% completed, 15th floor – 90% completed, 16th floor – 90% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 85% completed, 13th floor – 90% completed , 14th floor – 85% completed, 15th floor – 80% completed, 16th floor – 95% completed, Passage tiling – BF -2 to 16th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 90% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 16th floor completed, flush tank fixing 1st to 16th floor completed, Centralised gas piping work – 85% completed
- Final Finishes – Door shutters & ironmongery – 20 flats Completed, Final painting – 9 flats completed, Plumbing and Sanitary wares – 7 flats completed, Electrical final fixtures – 11 flats completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – 1st coat painting completed, 2nd coat painting – 60% completed
- Mockup- Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – BF 1, BF 2, GF 100% to be completed, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor, 12th floor 100% to be completed, Wall Tile work – 5th floor , 6th floor , 7th,8th,9th,10th,11th,12th floor, 13th floor, 14th floor, 15th floor, 16th floor – 100% to be completed, Handrail – Mainstair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works -Concealed plumbing works – BF-1, BF-2 floor to be completed, Centralised gas piping work – 15% more to be completed
- Final Finishes -Final painting – 5 more flats to be completed, Plumbing and Sanitary wares – 4 more flats to be completed, Electrical final fixtures – 5 more flats to be completed
- External Finishes- Windows and sliding doors -30% more to be completed, External painting – 2nd coat painting – 100% to be completed
Work status as on 09-04-2024, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, BF 1 floor – 90% completed, BF-2 Floor – 60% completed, GF – 90% completed, 1st floor – completed, 2nd floor – 95% completed, 3rd floor – 75% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 70% completed, 13th floor – 90% completed, 14th floor – 80% completed, 15th floor – 60% completed, 16th floor – 90% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 85% completed, 13th floor – 90% completed , 14th floor – 75% completed, 15th floor – 50% completed, 16th floor – 85% completed, Passage tiling – BF -2 to 13th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 90% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 16th floor completed, flush tank fixing 1st to 16th floor completed, Centralised gas piping work – 80% completed
- Final Finishes – Door shutters & ironmongery – 15 flats Completed, Final painting – 8 flats completed, Plumbing and Sanitary wares – 6 flats completed, Electrical final fixtures – 9 flats completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – 1st coat painting completed, 2nd coat painting – 50% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2024.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes Flooring – BF 1, BF 2, GF 100% to be completed, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor, 12th floor 100% to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th,8th,9th,10th,11th,12th floor – 100% to be completed, 13th floor 100% will be completed, 14th floor 25% more to be completed, 15th floor – 30% more to be completed, 16th floor – 100% to be completed, Passage tiling – 14th, 15th floor to be completed, Handrail – Mainstair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – BF-1, BF-2 floor to be completed, Centralised gas piping work – 20% more to be completed
- Final Finishes Final painting – 5 more flats to be completed, Plumbing and Sanitary wares – 4 more flats to be completed, Electrical final fixtures – 5 more flats to be completed
- External Finishes Windows and sliding doors -30% more to be completed, External painting – 2nd coat painting – 70% to be completed
Work status as on 09-03-2024, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, BF 1 floor – 90% completed, BF-2 Floor – 60% completed, GF – 90% completed, 1st floor – completed, 2nd floor – 95% completed, 3rd floor – 75% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 70% completed, 13th floor – 90% completed, 14th floor – 70% completed, 15th floor – 50% completed, 16th floor – 70% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 75% completed, 13th floor – 90% completed , 14th floor – 75% completed, 15th floor – 50% completed, 16th floor – 50% completed, Passage tiling – BF -2 to 13th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 70% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 16th floor completed, flush tank fixing 1st to 16th floor completed, Centralised gas piping work – 70% completed
- Final Finishes – Door shutters & ironmongery – 15 flats Completed, Final painting – 5 flats completed, Plumbing and Sanitary wares – 4 flats completed, Electrical final fixtures – 7 flats completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – 1st coat painting completed, 2nd coat painting – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2024.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – BF 1, BF 2, GF 100% to be completed, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor,12th floor 100% to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th,8th,9th,10th,11th,12th floor – 100% to be completed, 13th floor 80% will be completed, 14th floor 25% more to be completed, 15th floor – 30% more to be completed, 16th floor – 25% more to be completed, Passage tiling – 14th, 15th floor to be completed, Handrail – Mainstair handrail – 30% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – BF-1, BF-2 floor to be completed, Centralised gas piping work – 20% more to be completed
- Final Finishes – Final painting – 10 more flats to be completed, Plumbing and Sanitary wares – 4 more flats to be completed, Electrical final fixtures – 10 more flats to be completed
- External Finishes – Windows and sliding doors -30% more to be completed, External painting – 2nd coat painting – 70% to be completed
Work status as on 10-02-2024, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, Machine room plastering completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, BF 1 floor – 90% completed, BF-2 Floor – 60% completed, GF – 90% completed, 1st floor -completed, 2nd floor – 95% completed, 3rd floor – 75% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 70% completed, 13th floor – 90% completed, 14th floor – 50% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 12th floor – 75% completed, 13th floor – 90% completed , 14th floor – 50% completed, 15th floor – 25% completed, Passage tiling – BF -2 to 13th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 16th floor completed, flush tank fixing 1st to 16th floor completed, corridor fire stair handrail works – B/F-1 to Terrace floor completed, main stair 70% completed, Centralised gas piping work – 60% completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – 1st coat painting completed, 2nd coat painting – 50% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2024.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – BF 1, BF 2, GF 100% to be completed, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor,12th floor 100% to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th,8th,9th,10th,11th,12th floor – 100% to be completed, 13th floor 80% will be completed, 14th floor 50% more to be completed, 15th floor – 30% more to be completed, 16th floor – 25% to be completed, Passage tiling – 14th, 15th floor to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – BF-1, BF-2 floor to be completed, Main stair Handrail work – 90% will be completed, Centralised gas piping work – 20% more to be completed
- External Finishes – Windows and sliding doors -30% more to be completed, External painting – 2nd coat painting – 70% to be completed
Work status as on 08-12-2023, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works Ceiling plaster completed, wall plastering upto 16th floor completed, Machine room plastering completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor -completed, 2nd floor – 90% completed, 3rd floor – 75% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed,13th floor – 90% completed, 14th floor – 50% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed, 13th floor – 40% completed , Passage tiling – BF -2 to 13th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works Concealed plumbing works – sunken filling up to 15th floor completed, flush tank fixing 1st to 15th floor completed, corridor fire stair handrail works – B/F-3 to Terrace floor completed, main stair 50% completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor 100% to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th,8th,9th,10th,11th floor – 100% to be completed, 13th floor 80% will be completed, 14th floor 50% will be completed, Passage tiling – 14th, 15th floor to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 16th floor to be completed, flush tank – 16th floor to be completed.Main stair Handrail work – 40% will be completed
- External Finishes Windows and sliding doors -30% more to be completed
Work status as on 10-11-2023, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, Machine room plastering completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 90% completed, 2nd floor – 90% completed, 3rd floor – 75% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 95% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 75% completed,12th floor 10% completed,13th floor – 50% completed, 14th floor – 50% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 90% completed, 11th floor – 90% completed,12th floor 10% completed,13th floor – 40% completed , Passage tiling – BF -2 to 13th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 15th floor completed, flush tank fixing 1st to 15th floor completed.orridor fire stair handrail works – B/F-3 to Terrace floor completed , main stair 50% completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2023.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor 100% to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th,8th,9th,10th,11th floor – 100% to be completed, 12th floor 80% will be completed, 13th floor 80% will be completed, 14th floor 50% will be completed ,Passage tiling – 14th, 15th floor to be completed, Handrail – Mainstair handrail – 40% more to be completed.
- Concealed plumbing works – 16th floor to be completed, flush tank – 16th floor to be completed.Main stair Handrail work – 40% will be completed.
- External Finishes – Windows and sliding doors -30% more to be completed
Work status as on 10-10-2023, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, Machine room plastering completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 90% completed, 2nd floor – 90% completed, 3rd floor – 75% completed, 4th floor – 95% completed, 5th floor – 90% completed, 6th floor – 85% completed, 7th floor – 70% completed, 8th floor – 75% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 75% completed,12th floor 10% completed,13th floor 40% completed wall tiling – 1st floor – 95% completed, 2nd floor – 90% completed, 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor – 95% completed, 6th floor – 90% completed, 7th floor – 90% completed, 8th floor – 90% completed, 9th floor – 90% completed, 10th floor – 75% completed, 11th floor – 90% completed,12th floor 10% completed,13th floor 40% completed , Passage tiling – BF -2 to 13th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 15th floor completed, flush tank fixing 1st to 15th floor completed.orridor fire stair handrail works – B/F-3 to Terrace floor completed , main stair 50% completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2023.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor 100% to be completed, 7th floor,8th floor,9th floor,10th floor,11th floor – 100% more to be completed, 12th floor 30% will be completed,13th floor 40% will be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th,8th,9th,10th,11th floor – 100% to be completed, 12th floor 80% will be completed,13th floor 80% will be completed, 14th floor 50% will be completed ,Passage tiling – 14th, 15th floor to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 16th floor to be completed, flush tank – 16th floor to be completed.Main stair Handrail work – 40% will be completed
- External Finishes – Windows and sliding doors -30% more to be completed
Work status as on 13-09-2023, we have completed the following.
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, Machine room plastering completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 90% completed, 2nd floor – 90% completed, 3rd floor – 75% completed, 4th floor – 85% completed, 5th floor – 80% completed, 6th floor – 75% completed, 7th floor – 70% completed, 8th floor – 75% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 75% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 75% completed, 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor – 85% completed, 6th floor – 80% completed, 7th floor – 50% completed, 8th floor – 90% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 75% completed, Passage tiling – BF -2 to 12th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 14th floor completed, flush tank fixing 1st to 14th floor completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor 100% to be completed, 7th floor – 30% more to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th floor – 100% to be completed, Passage tiling – 13th, 14th floor to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works -15th to 16th floor to be completed, flush tank – 15th floor to be completed
- External Finishes – Windows and sliding doors -30% more to be completed
Work status as on 12-08-2023, we have completed the following.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Civil works – completed
- Internal Finishes – Main door – completed, Waterproofing- completed, Wall tiling – BF -1, BF -2, G/F to 17th floor completed, Flooring – BF – 1, BF – 2, completed, BF – 3, 95% completed, G/F to 17th floor completed (99% completed), Terrace completed, putty works & Painting- GF to 17th Floor Flat inside 1st and 2nd coat putty and one coat primer completed, BF- 3 to Terrace 2 coat putty and primer completed, BF – 3 Floor to 17th Floor stair and passage 2nd coat putty and one coat primer completed, BF-3 to terrace passage 1st coat and 2nd coat painting completed, Door frame fixtures – BF 2 to 4th Floor completed, Handrails- completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – G/F to Terrace completed, BF – 1 Completed, BF -2 Completed, Corridor handrail works – completed, Wall and floor services, Risers, – completed, Centralised Gas piping system – 90% completed (GF to 17th floor)
- Final Finishes – Door shutters & ironmongery, – 75 flats completed, Final Painting – Two coat painting 75 flats completed, Plumbing & Sanitaryware – 70 flats completed, Electrical final fixtures – 75 flats completed, Firefighting final fixtures – 73 flats completed
- External Finishes – Windows & Sliding doors – 90% completed, External Plastering- completed, External Painting – 1st coat painting completed, 2nd coat painting – 98% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – 100% completed
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, Machine room plastering completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 90% completed, 2nd floor – 90% completed, 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor – 70% completed, 6th floor – 70% completed, 7th floor – 55% completed, 8th floor – 75% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 75% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 75% completed, 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor – 85% completed, 6th floor – 80% completed, 7th floor – 50% completed, 8th floor – 90% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 50% completed, Passage tiling – BF -2 to 10th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 14th floor completed, flush tank fixing 1st to 14th floor completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Internal Finishes – Flooring – BF – 3, 100% to be completed
- Electrical, Plumbing & Firefighting works – gas work 100% to be completed.
- Final Finishes – Door shutter fixing – 1 more flats to be completed, painting- two coat painting – 1 more flats to be completed, plumbing & sanitary – 6 more flats to be completed, Eletrical final fittings – 1 more flats to be completed, Fire fighting final fitting – 3 more flats to be completed
- External Finishes- Windows and sliding doors – 100% to be completed, External painting – 2nd coat painting 100% to be completed.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor 100% to be completed, 7th floor – 30% more to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th floor – 100% to be completed, Passage tiling – 11th, 12th floor to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works -15th to 16th floor to be completed, flush tank – 15th floor to be completed
- External Finishes – Windows and sliding doors -30% more to be completed
Work status as on 12-07-2023, we have completed the following.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil works – completed
- Internal Finishes – Main door – completed, Waterproofing- completed, Wall tiling – BF -1, BF -2, G/F to 17th floor completed, Flooring – BF – 1, BF – 2, completed, BF – 3, 95% completed, G/F to 17th floor completed (99% completed), Terrace completed, putty works & Painting- GF to 17th Floor Flat inside 1st and 2nd coat putty and one coat primer completed, BF- 3 to Terrace 2 coat putty and primer completed, BF – 3 Floor to 17th Floor stair and passage 2nd coat putty and one coat primer completed, BF-3 to terrace 1st coat and 2nd coat painting completed, Door frame fixtures – BF 2 to 4th Floor completed, Handrails- completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – G/F to Terrace completed, BF – 1 Completed, BF -2 Completed, Corridor handrail works – completed, Wall and floor services, Risers, – completed, Centralised Gas piping system – 90% completed (GF to 17th floor)
- Final Finishes – Door shutters & ironmongery, – 75 flats completed, Final Painting – Two coat painting 73 flats completed, Plumbing & Sanitaryware – 67 flats completed, Electrical final fixtures – 75 flats completed, Firefighting final fixtures – 73 flats completed
- External Finishes – Windows & Sliding doors – 90% completed, External Plastering- completed, External Painting – 1st coat painting completed, 2nd coat painting – 98% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – 100% completed
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 90% completed, 2nd floor – 90% completed, 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor – 70% completed, 6th floor – 70% completed, 7th floor – 55% completed, 8th floor – 75% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 50% completed, wall tiling – 1st floor – 95% completed, 2nd floor – 75% completed, 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor – 75% completed, 6th floor – 70% completed, 7th floor – 50% completed, 8th floor – 80% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 50% completed, Passage tiling – BF -2 to 10th floor completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 14th floor completed, flush tank fixing 1st to 13th floor completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Internal Finishes – Flooring – BF – 3, 100% to be completed
- Electrical, Plumbing & Firefighting works – gas work 100% to be completed.
- Final Finishes – Door shutter fixing – 1 more flats to be completed, painting- two coat painting – 3 more flats to be completed, plumbing & sanitary – 9 more flats to be completed, Eletrical final fittings – 1 more flats to be completed, Fire fighting final fitting – 3 more flats to be completed
- External Finishes – Windows and sliding doors – 100% to be completed, External painting – 2nd coat painting 100% to be completed.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor, 2nd floor, 4th floor, 5th Floor, 6th floor, 8th floor, 9th floor, 10th floor, 11th floor 100% to be completed, 7th floor – 30% more to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 100% to be completed, 7th floor – 100% to be completed, Passage tiling – 11th, 12th floor to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works -15th to 16th floor to be completed, flush tank – 14th,15th floor to be completed
- External Finishes – Windows and sliding doors -30% more to be completed
Work status as on 06-06-2023, we have completed the following.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil works – completed
- Internal Finishes – Main door – completed, Waterproofing- completed, Wall tiling – BF -1, BF -2, G/F to 17th floor completed, Flooring – BF – 1, BF – 2, completed, BF – 3, 95% completed, G/F to 17th floor completed (99% completed), Terrace completed, putty works & Painting- 1st Floor to 17th Floor Flat inside 1st and 2nd coat putty and one coat primer completed, BF- 3 to Terrace 2 coat putty and primer completed, BF – 3 Floor to 17th Floor stair and passage 2nd coat putty and one coat primer completed, BF-3 to terrace 1st coat and 2nd coat painting completed, Door frame fixtures – BF 2 to 4th Floor completed, Handrails- completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – G/F to Terrace completed, BF – 1 Completed, BF -2 Completed, Corridor handrail works – completed, Wall and floor services, Risers, – completed, Centralised Gas piping system – 90% completed (GF to 17th floor)
- Final Finishes – Door shutters & ironmongery, – 75 flats completed, Final Painting – Two coat painting 73 flats completed, Plumbing & Sanitaryware – 65 flats completed, Electrical final fixtures – 73 flats completed, Firefighting final fixtures – 73 flats completed
- External Finishes – Windows & Sliding doors – 90% completed, External Plastering- completed, External Painting – 1st coat painting completed, 2nd coat painting – 98% completed
- Mockup – Blockwork, Internal plaster – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – 100% completed
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, machine room plastering – completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 70% completed, 2nd floor – 70% completed, 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor – 70% completed, 6th floor – 70% completed, 7th floor – 55% completed, 8th floor – 75% completed, 9th floor – 75% completed, 10th floor – 75% completed, 11th floor – 50% completed, wall tiling – 1st floor – 80% completed, 2nd floor – 75% completed, 3rd floor – 75% completed, 4th floor – 25% completed, 5th floor – 50% completed, 6th floor – 70% completed, 8th floor – 25% completed, 9th floor – 50% completed, 10th floor – 50% completed, putty works & Painting- 1st to 16th floor 2 coat putty and 2 coat primer completed Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 14th floor completed, flush tank fixing 1st to 13th floor completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Internal Finishes – Flooring – BF – 3, 100% to be completed
- Electrical, Plumbing & Firefighting works – gas work 100% to be completed.
- Final Finishes – Door shutter fixing – 1 more flats to be completed, painting- two coat painting – 3 more flats to be completed, plumbing & sanitary – 11 more flats to be completed, Eletrical final fittings – 3 more flats to be completed, Fire fighting final fitting – 3 more flats to be completed
- External Finishes – Windows and sliding doors – 100% to be completed, External painting – 2nd coat painting 100% to be completed.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor 20% more to be completed, 2nd floor – 25% more to be completed, 4th floor – 20% more to be completed, 5th Floor – 20% more to be completed and 6th floor – 25% more to be completed, 7th floor – 30% more to be completed, 8th floor – 25% more to be completed, 9th floor – 20% more to be completed, 10th floor – 20% more to be completed, 11th floor – 50% more to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 20% to be completed, 7th floor – 50% to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works -15th to 16th floor to be completed, flush tank – 14th,15th floor to be completed
- External Finishes – Windows and sliding doors -30% more to be completed
Work status as on 05-05-2023, we have completed the following.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil works – completed
- Internal Finishes – Main door – completed, Waterproofing- completed, Wall tiling – BF -1, G/F to 17th floor completed, BF -2, completed, Flooring – BF – 1 completed, G/F to 17th floor completed (99% completed), BF – 2, completed, BF – 3, 95% completed, Terrace completed, putty works & Painting- 1st Floor to 17th Floor Flat inside 1st and 2nd coat putty and one coat primer completed, BF- 3 to Terrace 2 coat putty and primer completed, BF – 3 Floor to 17th Floor stair and passage 2nd coat putty and one coat primer completed, BF-3 to terrace 1st coat and 2nd coat painting completed, Door frame fixtures – BF 2 to 4th Floor completed, Handrails- completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – G/F to Terrace completed, BF – 1 Completed, BF -2 Completed, Corridor handrail works – completed, Wall and floor services, Risers, – completed, Centralised Gas piping system – 90% completed (GF to 17th floor)
- Final Finishes – Door shutters & ironmongery, – 75 flats completed, Final Painting – Two coat painting 68 flats completed, Plumbing & Sanitaryware – 63 flats completed, Electrical final fixtures – 72 flats completed, Firefighting final fixtures – 73 flats completed
- External Finishes – Windows & Sliding doors – 90% completed, External Plastering- completed, External Painting – 1st coat painting completed, 2nd coat painting – 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – 100% completed
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, machine room plastering – completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 70% completed, 2nd floor – 70% completed, 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor – 70% completed, 6th floor – 70% completed, 7th floor – 55% completed, 8th floor – 25% completed, 9th floor – 75% completed, 10th floor – 75% completed, wall tiling – 1st floor – 80% completed, 2nd floor – 75% completed, 3rd floor – 75% completed, 4th floor – 25% completed, 5th floor – 50% completed, 6th floor – 70% completed, 8th floor – 25% completed, 9th floor – 25% completed, putty works & Painting- 1st to 14th floor 2 coat putty and 2 coat primer completed, 13th to 16th floor 1st coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – sunken filling up to 13th floor completed, flush tank fixing 1st to 13th floor completed
- External Finishes – Windows and sliding doors -70% completed, External Plastering : west side completed, South side – completed, North side – completed, East side – completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Internal Finishes – Flooring – BF – 3, 100% to be completed
- Electrical, Plumbing & Firefighting works – gas work 100% to be completed.
- Final Finishes – Door shutter fixing – 1 more flats to be completed, painting- two coat painting – 8 more flats to be completed, plumbing & sanitary – 13 more flats to be completed, Eletrical final fittings – 4 more flats to be completed, Fire fighting final fitting – 3 more flats to be completed
- External Finishes – Windows and sliding doors – 100% to be completed, External painting – 2nd coat painting 100% to be completed.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor 20% more to be completed, 2nd floor – 25% more to be completed, 4th floor – 20% more to be completed, 5th Floor – 20% more to be completed and 6th floor – 25% more to be completed, 7th floor – 30% more to be completed, 8th floor – 50% to be completed, 9th floor – 20% more to be completed, 10th floor – 20% more to be completed, 11th floor – 50% to be completed, Wall Tile work – 5th floor 100% to be completed, 6th floor – 20% to be completed, 7th floor – 50% to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works -14th to 16th floor to be completed, flush tank – 14th,15th floor to be completed
Work status as on 08-04-2023, we have completed the following.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Structural Works – All sub-structural and structural works – completed
- Civil Works Civil works – completed
- Internal Finishes – Main door – completed, Waterproofing- completed, Wall tiling – BF -1, G/F to 17th floor completed, BF -2, completed, Flooring – BF – 1 completed, G/F to 17th floor completed (99% completed), BF – 2, completed, BF – 3, 95% completed, Terrace completed, putty works & Painting- 1st Floor to 17th Floor Flat inside 1st and 2nd coat putty and one coat primer completed, BF- 3 to Terrace 2 coat putty and primer completed, BF – 3 Floor to 17th Floor stair and passage 2nd coat putty and one coat primer completed, Door frame fixtures – BF 2 to 4th Floor completed, Handrails- completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – G/F to Terrace completed, BF – 1 Completed, BF -2 Completed, Corridor handrail works – completed, Wall and floor services, Risers, – completed, Centralised Gas piping system – 90% completed (GF to 17th floor)
- Final Finishes – Door shutters & ironmongery, – 74 flats completed, Final Painting – Two coat painting 66 flats completed, Plumbing & Sanitaryware – 58 flats completed, Electrical final fixtures – 70 flats completed, Firefighting final fixtures – 72 flats completed
- External Finishes – Windows & Sliding doors – 90% completed, External Plastering- completed, External Painting – 1st coat painting completed, 2nd coat painting – 85% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – 100% completed
ARTECH METROPOLIS (TOWER-2)
-
-
- Structural Works – Pile cap – completed , slab completed – upto terrace Floor completed, All pergola completed, terrace Parapet completed, Lift machine room base and cover slab completed, stair case head room completed, OH tank base, wall and cover slab completed
- Civil Works – Ceiling plaster completed, wall plastering upto 16th floor completed, machine room plastering – completed, Masonry – Block/ brick completed, BF – 16th floor completed.
- Internal Finishes – Waterproofing – 1st to 17th floor completed, Flooring – sample flat completed, 1st floor – 70% completed, 2nd floor – 70% completed, 3rd floor – 75% completed, 4th floor – 25% completed, 5th floor – 70% completed, 6th floor – 70% completed, 7th floor – 25% completed, 8th floor – 25% completed, 9th floor – 25% completed, 10th floor – 50% completed, wall tiling – 1st floor – 80% completed, 2nd floor – 75% completed, 3rd floor – 25% completed, 5th floor – 50% completed, putty works & Painting- 1st to 14th floor 2 coat putty and 2 coat primer completed, 13th to 16th floor 1st coat primer completed, Door frame fixtures – Main door frame – BF – 3 to 16th floor completed, Handrails – 1st to 16th floor completed, Fire stair – BF -1 to terrace completed, Mainstair – 50% completed.
- Electrical, Plumbing & Firefighting works Concealed plumbing works – sunken filling up to 13th floor completed, flush tank fixing 1st to 10th floor completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – sunken filling up to 13th floor completed, flush tank fixing 1st to 10th floor completed
- External Finishes Windows and sliding doors -70% completed, External Plastering : west side completed, South side – completed, North side – completed, East side – completed, External painting – west side painting completed, North side painting completed, east side – completed
- Mockup Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
ARTECH METROPOLIS ( TOWER -1 )
-
-
- Internal Finishes – Flooring – BF – 3, 100% to be completed
- Electrical, Plumbing & Firefighting works – gas work 100% to be completed.
- Final Finishes – Door shutter fixing – 2 more flats to be completed, painting- two coat painting – 10 more flats to be completed, plumbing & sanitary – 18 more flats to be completed, Eletrical final fittings – 6 more flats to be completed, Fire fighting final fitting – 4 more flats to be completed
- External Finishes – Windows and sliding doors – 100% to be completed, External painting – 2nd coat painting 100% to be completed.
ARTECH METROPOLIS (TOWER-2)
-
-
- Internal Finishes – Flooring – 1st floor 30% more to be completed, 2nd floor – 30% more to be completed, 4th floor – 50% to be completed, 5th Floor – 30% more to be completed and 6th floor – 75% to be completed, 7th floor – 50% to be completed, 8th floor – 50% to be completed, 9th floor – 25% more to be completed, 10th floor – 30% more to be completed, Wall Tile work – 5th floor 100% to be completed, Handrail – Mainstair handrail – 40% more to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works -14th to 16th floor to be completed
- External Finishes – Windows and sliding doors -30% more to be completed
Click here to see the previous work progress updates.