}

Project Description

Experience the epitome of contemporary luxury at Artech Marvel, where timeless elegance meets modern sophistication in the heart of Pattom, Trivandrum. Our latest project showcases a collection of 2 and 3-BHK apartments that exude architectural excellence and impeccable craftsmanship. From stunning cityscape views to the seamless blend of modern and classic elements, Artech Marvel is a world of opulence and leisure. Each apartment has been thoughtfully designed with high-end finishes and ample natural light, striking the perfect balance between style and functionality.

Come and discover a new standard of living at Artech Marvel – an exquisite display of luxury living at its best.

QUICK
ENQUIRE

Take your first few steps towards finding the ultimate happiness of the Perfect Home.
  • Air-conditioned Multi-Purpose Hall for association and other activities.
  • Air Conditioned Unisex Gym
  • Air Conditioned state of the art AV Room
  • Guest Suite
  • Indoor Games Room
  • Rooftop Party Area
  • Children’s Play Area
  • Video door phone with intercom facility
  • Common toilet for supporting staff
  • Reticulated LPG supply
  • Gas leakage detector
  • Boom barrier
  • Access control system
  • Surveillance camera system
  • Common Electric car charging point
  • Efficient waste disposable system
  • Fire Suppression system
  • Car wash facility
  • Drivers Dormitory

Are you on the lookout for a home loan? We can help you. We have tie-ups with prominent banks for this project. It will help you make the loan application process easier.

  • AXIS
  • SOUTH INDIAN BANK
  • BANK OF BARODA
  • HDFC
  • FEDERAL BANK
  • ICICI
  • UCO

Work status as on 09-07-2024, we have completed the following.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 89 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1665m3 completed out of 1800m3, PCC for pilecap – 221m3 completed out of 255m3, RCC for pile cap – 305m3 completed out of 325m3, RCC for plinth beam and raft slab – 349m3 completed out of 381m3, RCC retaining wall 83m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2024.

  • Sub Structural Works – Earth back filling – 60m3 to be completed, pile chipping – 11 more nos: to be completed, pilecap RCC – 1m3 to be completed, Column and shear wall RCC 20m3 to be completed, retaining wall RCC – 20m3 to be completed, Basement floor Roof slab RCC – 85m3 to be completed, GF roof slab 75m3 to be completed

Work status as on 11-06-2024, we have completed the following.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 89 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1516m3 completed out of 1800m3, PCC for pilecap – 108m3 completed out of 255m3, RCC for pile cap – 183m3 completed out of 325m3, RCC for plinth beam and raft slab – 135m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.

  • Sub Structural Works – Earth work – 250m3 to be completed, pile chipping – 11 more nos: to be completed, PCC work – 35m3 to be completed, pilecap RCC – 25m3 to be completed, plinth beam and raft slab – 30m3 to be completed, Column RCC – 25m3 to be completed, retaining wall RCC – 5m3 to be completed, Roof slab RCC – 90m3 to be completed

Work status as on 09-05-2024, we have completed the following.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 76 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1386m3 completed out of 1800m3, PCC for pilecap – 105.4m3 completed out of 255m3, RCC for pile cap – 158.7m3 completed out of 325m3, RCC for plinth beam and raft slab – 135m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.

  • Sub Structural Works – Earth work – 245m3 to be completed, pile chipping – 14 more nos: to be completed, PCC work – 25m3 to be completed, pilecap RCC – 42m3 to be completed, plinth beam and raft slab – 70m3 to be completed, Column RCC – 10m3 to be completed, retaining wall RCC – 8m3 to be completed, Boundary wall RCC – 22m3 to be completed, Roof slab RCC – 95m3 to be completed

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 62 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1041m3 completed out of 1300m3, PCC for pilecap – 88.6m3 completed out of 255m3, RCC for pile cap – 148.1m3 completed out of 325m3, RCC for plinth beam and raft slab – 131m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 58 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 836m3 completed out of 1300m3, PCC for pilecap – 66.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 109m3 completed out of 381m3, RCC retaining wall 14m3 completed out of 125m3, column RCC – 7m3 completed out of 800m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 54 nos completed out of 111 Nos:, Excavation of pile cap foundation – 633m3 completed out of 1300m3, PCC for pilecap – 45.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 60m3 completed out of 381m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 36 nos completed out of 111 Nos:, Excavation of pile cap foundation – 401m3 completed out of 1300m3, PCC for pilecap – 18.7m3 completed out of 255m3, RCC for pile cap – 62m3 completed out of 325m3, RCC for plinth beam and raft slab – 7m3 completed out of 381m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile chipping 22 nos completed out of 111 Nos:, Excavation of pile cap foundation – 335m3 completed out of 1300m3, PCC for pilecap – 6.8m3 completed out of 255m3, RCC for pile cap – 43.3m3 completed out of 325m3, RCC for plinth beam and raft slab – 2m3 completed out of 381m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile cap 5 Nos completed out of 57 Nos:, pile chipping 11 nos completed out of 111 Nos:

  • Air-conditioned Multi-Purpose Hall for association and other activities.
  • Air Conditioned Unisex Gym
  • Air Conditioned state of the art AV Room
  • Guest Suite
  • Indoor Games Room
  • Rooftop Party Area
  • Children’s Play Area

  • Video door phone with intercom facility
  • Common toilet for supporting staff
  • Reticulated LPG supply
  • Gas leakage detector
  • Boom barrier
  • Access control system
  • Surveillance camera system
  • Common Electric car charging point
  • Efficient waste disposable system
  • Fire Suppression system
  • Car wash facility
  • Drivers Dormitory

Are you on the lookout for a home loan? We can help you. We have tie-ups with prominent banks for this project. It will help you make the loan application process easier.

  • AXIS
  • SOUTH INDIAN BANK
  • BANK OF BARODA
  • HDFC
  • FEDERAL BANK
  • ICICI
  • UCO

Work status as on 09-07-2024, we have completed the following.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 89 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1665m3 completed out of 1800m3, PCC for pilecap – 221m3 completed out of 255m3, RCC for pile cap – 305m3 completed out of 325m3, RCC for plinth beam and raft slab – 349m3 completed out of 381m3, RCC retaining wall 83m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2024.

  • Sub Structural Works – Earth back filling – 60m3 to be completed, pile chipping – 11 more nos: to be completed, pilecap RCC – 1m3 to be completed, Column and shear wall RCC 20m3 to be completed, retaining wall RCC – 20m3 to be completed, Basement floor Roof slab RCC – 85m3 to be completed, GF roof slab 75m3 to be completed

Work status as on 11-06-2024, we have completed the following.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 89 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1516m3 completed out of 1800m3, PCC for pilecap – 108m3 completed out of 255m3, RCC for pile cap – 183m3 completed out of 325m3, RCC for plinth beam and raft slab – 135m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.

  • Sub Structural Works – Earth work – 250m3 to be completed, pile chipping – 11 more nos: to be completed, PCC work – 35m3 to be completed, pilecap RCC – 25m3 to be completed, plinth beam and raft slab – 30m3 to be completed, Column RCC – 25m3 to be completed, retaining wall RCC – 5m3 to be completed, Roof slab RCC – 90m3 to be completed

Work status as on 09-05-2024, we have completed the following.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 76 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1386m3 completed out of 1800m3, PCC for pilecap – 105.4m3 completed out of 255m3, RCC for pile cap – 158.7m3 completed out of 325m3, RCC for plinth beam and raft slab – 135m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.

  • Sub Structural Works – Earth work – 245m3 to be completed, pile chipping – 14 more nos: to be completed, PCC work – 25m3 to be completed, pilecap RCC – 42m3 to be completed, plinth beam and raft slab – 70m3 to be completed, Column RCC – 10m3 to be completed, retaining wall RCC – 8m3 to be completed, Boundary wall RCC – 22m3 to be completed, Roof slab RCC – 95m3 to be completed

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 62 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1041m3 completed out of 1300m3, PCC for pilecap – 88.6m3 completed out of 255m3, RCC for pile cap – 148.1m3 completed out of 325m3, RCC for plinth beam and raft slab – 131m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 58 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 836m3 completed out of 1300m3, PCC for pilecap – 66.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 109m3 completed out of 381m3, RCC retaining wall 14m3 completed out of 125m3, column RCC – 7m3 completed out of 800m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 54 nos completed out of 111 Nos:, Excavation of pile cap foundation – 633m3 completed out of 1300m3, PCC for pilecap – 45.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 60m3 completed out of 381m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 36 nos completed out of 111 Nos:, Excavation of pile cap foundation – 401m3 completed out of 1300m3, PCC for pilecap – 18.7m3 completed out of 255m3, RCC for pile cap – 62m3 completed out of 325m3, RCC for plinth beam and raft slab – 7m3 completed out of 381m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile chipping 22 nos completed out of 111 Nos:, Excavation of pile cap foundation – 335m3 completed out of 1300m3, PCC for pilecap – 6.8m3 completed out of 255m3, RCC for pile cap – 43.3m3 completed out of 325m3, RCC for plinth beam and raft slab – 2m3 completed out of 381m3

We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.

  • Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile cap 5 Nos completed out of 57 Nos:, pile chipping 11 nos completed out of 111 Nos:

Luxury Apartments in Pattom, Trivandrum

Trivandrum city is like no other when it comes to buying a home and setting up roots. Here, you will find that there is no paucity of natural tourism spots, cultural grandeur, premier educational institutes, medical tourism or well-developed infrastructure. And for those looking to buy luxury flats in Trivandrum, one of the best neighborhoods to invest in is Pattom. As this locality offers well-maintained roads and easily accessible essential services to enhance the livability factor of this area, the demand for flats in Pattom is understandably very high too.

Some of the best builders have premium apartments for sale in Pattom, including Artech Realtors. And ‘Artech Marvel’ is their ode to luxury contemporary apartment living in the city, where timeless elegance meets modern sophistication in the heart of Pattom. Each apartment is designed with impeccable finishing, a seamless blend of modern and classic elements and ample lighting, thus creating the perfect balance between style and functionality.

Along with the value-added facilities and lifestyle-enhancing amenities, what you get with Artech Marvel are some of the best luxury apartments in Pattom. What’s more, these apartments come in convenient sizes to suit every family’s space needs. With Artech Marvel featuring thoughtfully-designed 2 and 3 BHK apartments in Pattom that exude architectural excellence and spacious designs, you won’t ever have to worry again about finding premium homes crafted by renowned builders!
Come, discover Artech Marvel, where every apartment sets a new standard in living and an exquisite display of luxury living at its best

RELATED PROJECTS

DISCLAIMER

The information provided on this website is meant for general guidance. Though we have taken utmost care on the accuracy of the contents, the customer should make an autonomous assessment of the contents. However, the prospective buyers should rely upon the terms and conditions of the sale and construction agreement between the Builder and the Client.

The visuals of the projects symbolize artistic impression only. The information contained herein including the fittings, finishes, features, floor size and color etc. in the visuals are subject to change. However, the plans & specifications indicated in the Builder and Client agreements are final and we have not authorized anyone to make any oral commitments or promises on our behalf in regard to the plans and specifications of the apartments/projects.

For any clarification please feel free to call +91 9847 600 600 or walk into our offices. Our representatives will always be at your service.