We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 62 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1041m3 completed out of 1300m3, PCC for pilecap – 88.6m3 completed out of 255m3, RCC for pile cap – 148.1m3 completed out of 325m3, RCC for plinth beam and raft slab – 131m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 58 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 836m3 completed out of 1300m3, PCC for pilecap – 66.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 109m3 completed out of 381m3, RCC retaining wall 14m3 completed out of 125m3, column RCC – 7m3 completed out of 800m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 54 nos completed out of 111 Nos:, Excavation of pile cap foundation – 633m3 completed out of 1300m3, PCC for pilecap – 45.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 60m3 completed out of 381m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 36 nos completed out of 111 Nos:, Excavation of pile cap foundation – 401m3 completed out of 1300m3, PCC for pilecap – 18.7m3 completed out of 255m3, RCC for pile cap – 62m3 completed out of 325m3, RCC for plinth beam and raft slab – 7m3 completed out of 381m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile chipping 22 nos completed out of 111 Nos:, Excavation of pile cap foundation – 335m3 completed out of 1300m3, PCC for pilecap – 6.8m3 completed out of 255m3, RCC for pile cap – 43.3m3 completed out of 325m3, RCC for plinth beam and raft slab – 2m3 completed out of 381m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile cap 5 Nos completed out of 57 Nos:, pile chipping 11 nos completed out of 111 Nos: