Work status as on 10-03-2025, we have completed the following.
ARTECH L’ATTITUDE (TOWER A)
- Sub Structural Works – Footing RCC- 76 cum, Lift Pit with Combined Footing- 51.3 cum, Excavation-112 cum, Backfilling-180 cum, PCC- 17 cum, Raft Slab RCC- 48.2 cum, Column RCC- 13.14 cum, GF Slab RCC- 82 cum, Retaining Wall RCC- 15.7 cum
ARTECH L’ATTITUDE (TOWER B)
- Sub Structural Works – Pile cap RCC- 81.94 cum, Column RCC- 16.718 cum, Retaining Wall RCC- 5.1 cum, Raft Slab RCC- 72 cum, PCC- 34 cum, Backfilling- 94 cum, Excavation-115 cum, Lift Pit shear walls and columns- 14cum
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2025.
ARTECH L’ATTITUDE (TOWER A)
- Sub Structural Works – Footing RCC- 47cum, Column RCC-34cum, Raft Slab RCC- 140 cum, Excavation-112 cum, Backfilling-180 cum, PCC- 29 cum, GF Slab RCC- 195 cum, LGF1,LGF2 Slab RCC- 370 cum, Staircase RCC-22 cum, Retaining Wall RCC- 14 cum, Lift Wall RCC- 21cum, Backfilling-85 cum, Excavation-125 cum
ARTECH L’ATTITUDE (TOWER B)
- Sub Structural Works – Pile cap RCC- 98 cum, LGF1,LGF2 Slab RCC-250 cum, GF Slab RCC- 145 cum,Staircase RCC-12 cum, Lift Wall RCC- 8cum, , Retaining Wall RCC- 5.1 cum, Raft Slab RCC- 196cum, PCC- 22cum
Work status as on 13-02-2025, we have completed the following.
- Sub Structural Works – EXCAVATION-187.65CUM,PCC-14.7CUM, BASE SLAB RCC-44.07CUM, EARTH FILLING-88.2CUM, COLUMN RCC-23CUM, SHEAR WALL RCC-28.8CUM, PLINTH BEAM RCC-5.4CUM, RAFT SLAB RCC-55.5CUM, GF SLAB RCC-110CUM, COLUMN RCC-32.77CUM, PILE CAP RCC-66.3CUM, GF SLAB RCC-134CUM, EXCAVATION -410CUM, BACKFILLING-322CUM, BACKFILLING-322CUM, LIFT WALL RCC -4.6CUM
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2025.
- Sub Structural Works – FOOTINGRCC-82.175,LIFT PIT WITH COMBINED FOOTING-50.37,EXCAVATION-156.32,BACK FILLING-261,PCC-33.2,BASE SLAB RCC-6.4,COLUMN RCC-23.1,RETAINING WALL-21.63,GROUND FLOOR RCC-85.2,LGF1 SLAB RCC-94.37,LGF2 SLAB RCC-126,PILECAP RCC-52.3,EXCAVATION-166,PLINTH BEAM-8.2,PCC-35RAFT SLAB -147,LGF1 SLAB RCC-122,BASEMENT COLUMN RCC-19.99
Work status as on 12-12-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 15m3 completed,Column 10 nos completed(part 2) Sump tank base slab RCC completed, Sump tank wall upto 2.3m RCC completed, Retaining wall rear side 60% completed, sheet piling completed ,LGF2 FLOORSLAB AND RAMP- 130m3 ,Grade Slab work -130 m3 completed ,Earth Work Excavation 1278 cum, Base Slab RCC-227 cum , Pile cap-88.5cum, Plinth Beam RCC-9cum, Basement Slab RCC -93cum, PCC-96.5cum, Base Slab RCC-436 cum, Column RCC-63 cum, LGF 2 Slab RCC -118cum, GF Slab- 248cum,LGF 1 Slab RCC Block 2 -116cum,STP Wall RCC-117 cum, Retaining Wall RCC- 37cum, Footing-63cum
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2024.
- Sub Structural Works – Earth work excavation-996 cum,Footing- 58cum, Pile cap-134cum, Plinth Beam-7.8cum, PCC-111cum, Base Slab RCC-436 cum, Column RCC-143 cum,LGF 1 Slab RCC STP Area -64cum, GF Slab- 29cum,LGF 1 Slab RCC Block 2 -116cum,STP Tank Wall RCC-14.5cum, Retaining Wall RCC- 25cum
Work status as on 08-11-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 15m3 completed,Column 10 nos completed(part 2) Sump tank base slab RCC completed, Sump tank wall upto 2.3m RCC completed, Retaining wall rear side 60% completed, sheet piling completed ,LGF2 FLOORSLAB AND RAMP- 130m3 ,Grade Slab work -130 m3 completed Tower1: Excavation-200cum,excavation- 200cum pcc-40 cum,pilecap-120 cum,plinth beam&grade slab-80cum,Basement columns-70 cum,LGF2 floor slab-125 cum,LGF2 Columns-100 cum,LGF1 floor slab-220 cum,STP WALL CONCRETE=40 CUM,LIFT PILE CAP& FOOTINGS=30 CUM,PCC= 6 CUM,ROCK BREAKING = 25 CUM,COLUMN CONCRETE =18cum
Tower 02 Excavation- 500cum,PCC-40 cum,Pilecap-170 cum,Plinth beam&grade slab-80cum,GRADE SLAB =50 CUM,PCC = 10 CUM,PILE CAP =30 CUM,PILE CHIPPING = 38 RM,COLUMN CONCRETE= 7 CUM
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2024.
- Sub Structural Works – L1 slab,L2 Slab and Column to be completed,STP wall casting, Part 2 lift wall casting,Part 4,1 lift area waterproofing
Work status as on 14-10-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 15m3 completed,Column 10 nos completed(part 2) Sump tank base slab RCC completed, Sump tank wall upto 2.3m RCC completed, Retaining wall rear side 60% completed, sheet piling completed ,LGF2 FLOORSLAB AND RAMP- 130m3 ,Grade Slab work -130 m3 completed Tower1: Excavation-200cum,excavation- 200cum pcc-40 cum,pilecap-120 cum,plinth beam&grade slab-80cum,Basement columns-70 cum,LGF2 floor slab-125 CUM,LGF2 Columns-100 cum, Tower 02 Excavation- 500cum,PCC-40 cum,Pilecap-170 cum,Plinth beam&grade slab-80cum
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2024.
- L1 slab,L2 Slab and Column to be completed,STP wall casting, Part 2 lift wall casting,Part 4,1 lift area waterproofing
Work status as on 12-09-2024, we have completed the following.
- Sub Structural Works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 15m3 completed,Column 10 nos completed(part 2) Sump tank base slab RCC completed, Sump tank wall upto 2.3m RCC completed, Retaining wall rear side 60% completed, sheet piling completed ,LGF2 FLOORSLAB AND RAMP- 130m3 ,Grade Slab work -130 m3 completed
Work status as on 13-08-2024, we have completed the following.
- Sub Structural Works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 80m3 completed,Column 10 nos completed(part 2) sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
Work status as on 09-07-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 460 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 30m3 completed, Plinth beam RCC – 5m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
Work status as on 11-06-2024, we have completed the following.
- Sub Structural Works – S Sub structural works – Pile concreting 459 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
- Sub Structural Works- pile concreting 95% to be completed
Work status as on 09-05-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 459 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
-
- Sub Structural Works-pile concreting 95% to be completed
Work status as on 09-04-2024, we have completed the following.
-
-
- Sub Structural Works Sub structural works – Pile concreting 435 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed
Work status as on 09-03-2024, we have completed the following.
-
-
- Sub Structural Works Sub structural works – Pile concreting 367 nos: completed out of 495 nos:, Pile chipping – 19nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 30m3 completed, sump tank base slab RCC completed
Work status as on 10-02-2024, we have completed the following.
-
-
- Sub structural works – Pile concreting 300 nos: completed out of 495 nos:, Pile chipping started, excavation for pilecap (10 Nos:) completed
Work status as on 13-01-2024, we have completed the following.
-
-
- Sub Structural Works – Sub structural works – Pile concreting 221 nos: completed out of 495 nos:
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2024.
-
-
- Sub Structural Works – 70 more nos: of pile concreting to be completed, retaining wall 75% to be completed
Work status as on 08-12-2023, we have completed the following.
-
-
- Sub Structural Works – Sub structural works – Pile concreting 162 nos: completed out of 495 nos:
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
-
-
- Sub Structural Works – 75 more nos: of pile concreting to be completed, retaining wall 75% to be completed
We are pleased to inform you the current work progress at our site Artech “L’Attitude”, Sreekaryam, Few snaps of the work progress is attached for your reference.