Work status as on 13-08-2024, we have completed the following.
- Sub Structural Works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 80m3 completed,Column 10 nos completed(part 2) sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
Work status as on 09-07-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 460 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 30m3 completed, Plinth beam RCC – 5m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
Work status as on 11-06-2024, we have completed the following.
- Sub Structural Works – S Sub structural works – Pile concreting 459 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
- Sub Structural Works- pile concreting 95% to be completed
Work status as on 09-05-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 459 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
-
- Sub Structural Works-pile concreting 95% to be completed
Work status as on 09-04-2024, we have completed the following.
-
-
- Sub Structural Works Sub structural works – Pile concreting 435 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed
Work status as on 09-03-2024, we have completed the following.
-
-
- Sub Structural Works Sub structural works – Pile concreting 367 nos: completed out of 495 nos:, Pile chipping – 19nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 30m3 completed, sump tank base slab RCC completed
Work status as on 10-02-2024, we have completed the following.
-
-
- Sub structural works – Pile concreting 300 nos: completed out of 495 nos:, Pile chipping started, excavation for pilecap (10 Nos:) completed
Work status as on 13-01-2024, we have completed the following.
-
-
- Sub Structural Works – Sub structural works – Pile concreting 221 nos: completed out of 495 nos:
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2024.
-
-
- Sub Structural Works – 70 more nos: of pile concreting to be completed, retaining wall 75% to be completed
Work status as on 08-12-2023, we have completed the following.
-
-
- Sub Structural Works – Sub structural works – Pile concreting 162 nos: completed out of 495 nos:
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
-
-
- Sub Structural Works – 75 more nos: of pile concreting to be completed, retaining wall 75% to be completed
We are pleased to inform you the current work progress at our site Artech “L’Attitude”, Sreekaryam, Few snaps of the work progress is attached for your reference.