Work status as on 13-09-2023, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting completed , pile chipping 60% completed (190 nos: completed out of 310 nos:), pile load test completed , pile integrity test completed
- Building Area :- PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – completed, Lower Basement column RCC 47 Nos: completed out of 51 Nos:, Lower basement floor slab and beam – 900 m2 completed out of 2016 m2, Upper basement slab concrete – 800m2 completed out of 2400m2, RCC column upper basement – 47 Nos: completed out of 51 Nos: , Ground floor slab RCC – 725 m2 completed out of 2000 m2
- Podium Area:- PCC pile cap – 28 Nos: completed out of 58 Nos:, RCC pile cap – 22 Nos: completed out of 58 Nos:, RCC pile cap (STP) – completed, Lower basement column RCC – 18 Nos: completed out of 70 Nos:, Upper basement column RCC – 10 Nos: completed out of 52 Nos:, STP slab concrete – 46m2 completed
- Boundary wall :- PCC pile cap – 5 Nos: completed out of 45 Nos:, RCC pile cap – 5 Nos: completed out of 45 Nos:, RCC wall – 40 Rm completed out of 250RM
Work status as on 12-08-2023, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting completed , pile chipping 58% completed (181 nos: completed out of 310 nos:), pile load test completed , pile integrity test completed.
- Building Area :- PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – 450m2 completed out of 500m2, Lower Basement column RCC 47 Nos: completed out of 51 Nos:, Upper basement slab concrete – 445m2 completed out of 2400m2, RCC column upper basement – 16 Nos: completed out of 51 Nos:
- Podium Area:- PCC pile cap – 25 Nos: completed out of 58 Nos:, RCC pile cap – 21 Nos: completed out of 58 Nos:, RCC pile cap (STP) – completed, Lower basement column RCC – 12 Nos: completed out of 70 Nos:, STP slab concrete – 46m2 completed.
- Boundary wall :- PCC pile cap – 5 Nos: completed out of 45 Nos:, RCC pile cap – 5 Nos: completed out of 45 Nos:, RCC wall – 33 Rm completed out of 250RM.
Work status as on 12-07-2023, we have completed the following.
- Sub Structural Works – Sub structural works – PBuilding Area :- PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – 450m2 completed out of 500m2, Lower Basement column RCC 47 Nos: completed out of 51 Nos:, Upper basement slab concrete – 445m2 completed out of 2400m2, RCC column upper basement – 16 Nos: completed out of 51 Nos:
Work status as on 06-06-2023, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 100% completed (310 nos: completed out of 310 nos:), pile chipping 58% completed (180 nos: completed out of 310 nos:), pile load test completed (P179 – 100cm pile), pile integrity test first stage completed (48 nos: completed out of 48 nos:), excavation for pile cap foundation is progressing, PCC for pile cap 36% completed (47 nos: completed out of 128 nos:), pile cap concreting 36% completed (47 nos: completed out of 128 nos:)
Work status as on 05-05-2023, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 100% completed (310 nos: completed out of 310 nos:), pile chipping 48% completed (150 nos: completed out of 310 nos:), excavation for pile cap foundation is progressing, PCC for pile cap 34% completed (44 nos: completed out of 128 nos:), pile cap concreting 27% completed (35 nos: completed out of 128 nos:), pile load test completed (P179 – 100cm pile), pile integrity test first stage completed (48 nos: completed out of 48 nos:)