Work status as on 14-10-2024, we have completed the following..
- Civil Works -Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 90% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door -100% completed Wall tiling 80% completed Flooring 90% completed Passage floor tiling BF to 19th floor -100% completed, Lift cladding – p3 lift completed GF Interlock – 70% completed, Putty works & Painting Putty – 98% completed ,1st to 19th floor -2 coat putty & 2 coat primer completed,Ground Floor -95% 2 coat putty and primer completed ,Painting 1st coat -80% completed (70 flats),Water proofing – 100% completed ,Door frame – 100% completed Stair Handrails -100% completed (firestair handrail completed) Main stair -100% completed, Balcony handrail- 97% completed
- Electrical, Plumbing & Firefighting works- Concealed plumbing works – 95% completed (till 19th floor completed CP Sanitary – 10 flats completed,Corecutting – till 19th floor – 95% completed Centralised Gas piping system- 70% completed Firefighting final fixtures – Horizontal pipe line till GF -19th floor completed, Vertical pipe line work – 98% completed Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed, 13 30% completed 14 ,15 -in progress Switch fixing – 27 flats completed
- External Finishes- Windows & Sliding doors – 65 %completed,External Plastering – 98% completed External Painting – 95% completed External Infrastructure and MEP services – 25% completed
- Final Finishes -Door shutters & ironmongery – 50% Completed, Final painting 13% completed, Plumbing and Sanitary wares – 30% completed, Electrical final fixtures – 30% completed, Firefighting final fixtures -55% completed
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2024.
- Internal Finishes- Balcony handrail -100% to be completed
- Electrical, Plumbing & Firefighting works- Concealed plumbing work – 100% ,plumbing duct work100% to be completed
- External Finishes- Windows & Sliding doors – 100% to be completed, External Plastering – 100% to be completed, External Painting – 100% to be completed
- Final Finishes – Door shutter fixing 70%,Eletrical wire pulling 70% to be completed
Work status as on 12-09-2024, we have completed the following.
- Structural Works -Pile cap – completed, slab – completed, retaining wall – completed, compound wall – completed (110m)
- Civil Works -Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 90% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door -100% completed Wall tiling 80% completed Flooring 90% completed Passage floor tiling BF to 19th floor -100% completed, Lift cladding – p3 lift completed GF Interlock – 70% completed, Putty works & Painting Putty – 95% completed ,1st to 19th floor -2 coat putty & 2 coat primer completed,Ground Floor -95% 2 coat putty and primer completed ,Painting 1st coat -80% completed (70 flats),Water proofing – 80% completed ,Door frame – 100% completed Stair Handrails -100% completed (firestair handrail completed) Main stair -100% completed, Balcony handrail- 80% completed (3rd – 12th floor – completed)
- Electrical, Plumbing & Firefighting works- Concealed plumbing works – 95% completed (till 19th floor completed CP Sanitary – 10 flats completed,Corecutting – till 19th floor – 95% completed,Centralised Gas piping system- 70% completed Firefighting final fixtures – Horizontal pipe line till GF -19th floor completed, Vertical pipe line work – 98% completed Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed, 13 30% completed 14 ,15 -in progress Switch fixing – 27 flats completed
- External Finishes- Windows & Sliding doors – 65 %completed,External Plastering – 96% completed External Painting – 95% completed
- Mockup – Completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2024.
- Internal Finishes- Balcony handrail – 13th floor – 19th floor- 100% to be completed
- Electrical, Plumbing & Firefighting works- CP Sanitary – 15 more flats to be completed, Electrical wire pulling – 10 flats to be completed, switch fixing – 10 more flats to be completed
- External Finishes- Windows & Sliding doors – 100% to be completed, External Plastering – 100% to be completed, External Painting – 100% to be completed
Work status as on 11-06-2024, we have completed the following.
- Internal Finishes – Main door – completed, Wall tiling – 3rd to 14th floor (toilets) – 90% completed, 15th,18th floor – 40% completed, 17th floor – 60% completed, Flooring – 3rd,4th ,5th , 6th , 7th floor completed, 2nd floor – 80% completed, 1st floor – 60%, 8th to 18th floor – 80% completed, passage floor tiling – BF to 19th floor – 100% completed, lift cladding – p3 lift completed, GF Interlock – 20% completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, painting 1st coat – 70% completed (70 flats), Water proofing – 3rd to 19th floor 98% completed, OHT- 80% completed, open terrace – 70% completed, Sump tank – 40% completed, GF – 50% Completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed (2nd – 12th floor – 90% completed)
- Electrical, Plumbing & Firefighting works- Concealed plumbing works – 90% completed (till 19th floor completed, CP Sanitary – 4 flats completed, Corecutting – till 19th floor – 95% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 98% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed, switch fixing – 27 flats completed
- External Finishes- Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th,6th,7th floor – 75% completed, 8th, to 19th – 60% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
- Internal Finishes- Water proofing – open terrace – 90% to be completed, GF – 90% to be completed, Handrail – 1st to 12th Floor – 90% to be completed, balcony handrail – 12th floor – 19th floor- 90% to be completed
- Electrical, Plumbing & Firefighting works- CP Sanitary – 10 flats to be completed, Electrical wire pulling – 10 flats to be completed, switch fixing – 10 more flats to be completed
- External Finishes- Windows & Sliding doors – 8th to 19th floor – 80% to be completed
Work status as on 09-05-2024, we have completed the following.
- Internal Finishes – Main door – completed, Wall tiling – 3rd to 14th floor (toilets) – 90% completed, 15th,18th floor – 40% completed, 17th floor – 60% completed, Flooring – 3rd,4th ,5th , 6th , 7th floor completed, 2nd floor – 80% completed, 1st floor – 40%, 8th to 15th floor – 80% completed, 16th – 60%, 17th floor – 40%, 18th floor – 20% completed, passage floor tiling – BF to 19th floor – 100% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, painting 1st coat – 65% completed (50 flats), Water proofing – 3rd to 19th floor 98% completed, OHT- 80% completed, open terrace – 60% completed, Sump tank – 40% completed, GF – 30% COMPLETED, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed)
- Electrical, Plumbing & Firefighting works- Concealed plumbing works – 90% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 95% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 98% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed, switch fixing – 17 flats completed
- External Finishes- Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th,6th,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line completed
- Mockup-Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
-
- Internal Finishes- Flooring – 8th to 15th 100% 100% to be completed, Handrail – 1st to 12th Floor – 90% to be completed
- Electrical, Plumbing & Firefighting works-Concealed plumbing works – till 19th floor 100% to be completed, CP Sanitary – 5 flats to be completed, Electrical wire pulling – 10 flats to be completed, switch fixing – 10 more flats to be completed.
- External Finishes- Windows & Sliding doors – 11th to 18th floor – 70% to be completed
Work status as on 12-04-2024, we have completed the following.
-
-
- Internal Finishes Main door – completed, Wall tiling – 3rd to 12th floor (toilets) – 90% completed, 13th floor – 60% completed, 14th,15th,18th floor – 40% completed, 17th floor – 60% completed, Flooring – 3rd,4th ,5th floor completed, 2nd floor – 80% completed, 6th floor – 95% , 7th – 12th floor – 80% completed, 15th floor- 40%, 13th floor – 80% completed, 14th – 60%, 16th – 60%, 17th floor – 40%, 18th floor – 20% completed, passage floor tiling – 1st to 14th floor – 100% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, painting 1st coat – 30% completed (25 flats), Water proofing – 3rd to 19th floor 98% completed, OHT- 80% completed, open terrace – 60% completed, Sump tank – 30% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed)
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 90% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 98% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed, switch fixing – 12 flats completed
- External Finishes Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th,6th,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2024.
-
-
- Internal Finishes wall tiling up to 14th floor 90% to be completed, Flooring – up to 17th floor 100% to be completed, passage floor tiling – 15th,16th, 17th,18th, GF floor 100% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – till 19th floor 100% to be completed, CP Sanitary – 5 flats to be completed, Electrical wire pulling – 10 flats to be completed, switch fixing – 10 more flats to be completed
- External Finishes Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 12-03-2024, we have completed the following.
-
-
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 12th floor (toilets) – 90% completed, 13th floor – 40% completed, 14th,15th,18th floor – 40% completed, 17th floor – 60% completed, Flooring – 3rd floor completed, 2nd floor – 70% completed, 4th – 12th floor – 80% completed,15th floor- 40%, 13th floor – 80% completed, 14th – 40%,16th – 60%, 17th floor – 30%,18th floor – 20% completed, passage floor tiling – 1st to 12th floor – 95% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 19th floor 98% completed, OHT- 80%completed, open terrace – 40% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed).
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 98% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed
- External Finishes Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2024.
-
-
- Internal Finishes Main door – 100% to be completed, wall tiling up to 14th floor 90% to be completed, Flooring – up to 15th floor 80% to be completed, passage floor tiling – up to 15th floor 95% to be completed, water proofing works – OHT – 100% to be completed, open terrace – 80% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – up to 15th floor – 90% to be completed
- External Finishes Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 10-02-2024, we have completed the following.
-
-
- Structural Works – Pile cap – completed, slab – 95% completed, retaining wall – 70% completed, compound wall – 80% completed (110m), GF, BF floor slab – 70% completed
- Civil Works Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 12th floor (toilets) – 90% completed, 13th floor – 40% completed, 14th,15th,18th floor – 20% completed, 17th floor – 40% completed, Flooring – 3rd floor completed, 4th – 12th floor – 80% completed,15th floor- 40%, 13th floor – 40% completed, 14th,16th,18th floor – 20% completed, passage floor tiling – 1st to 12th floor – 95% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 19th floor 98% completed, OHT- 80%completed, open terrace – 40% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed)
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2024.
-
-
- Structural Works – Ground floor slab – 80% to be completed, Raft slab – 80% to be completed, BF column 1 more No: to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling up to 14th floor 90% to be completed, Flooring – up to 15th floor 80% to be completed, passage floor tiling – up to 15th floor 95% to be completed, water proofing works – OHT – 100% to be completed, open terrace – 80% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – up to 15th floor – 90% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 13-01-2024, we have completed the following.
-
-
- Structural Works – Pile cap – completed, slab – 95% completed, retaining wall – 70% completed, compound wall – 80% completed (110m), GF, BF floor slab – 70% completed
- Civil Works Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 11th floor (toilets) – 90% completed, 13th floor – 40% completed, 14th,15th,18th floor – 20% completed, 17th floor – 40% completed, Flooring – 3rd floor completed, 4th – 11th floor – 80% completed,15th floor- 40%, 13th floor – 40% completed, 14th,16th,18th floor – 20% completed, passage floor tiling – 1st to 6th floor – 95% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 19th floor 95% completed, OHT- 80%completed, open terrace – 30% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed)
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor 90% completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 11th floor – 90% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2024.
-
-
- Structural Works – Ground floor slab – 80% to be completed, Raft slab – 80% to be completed, BF column 1 more No: to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling up to 14th floor 90% to be completed, Flooring – up to 15th floor 80% to be completed, passage floor tiling – up to 15th floor 95% to be completed, water proofing works – OHT – 100% to be completed, open terrace – 80% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – up to 15th floor – 90% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 08-12-2023, we have completed the following.
-
-
- Structural Works Pile cap – completed, slab – 95% completed, retaining wall – 45% completed, compound wall – 60% completed (42m), GF, BF floor slab – 50% completed
- Civil Works Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 10th floor (toilets) – 90% completed, 13th floor – 20% completed, 14th,15th,18th floor – 20% completed, Flooring – 3rd floor completed, 4th floor – 80%, 5th floor – 80%, 6th floor – 80%, 7th floor – 80%, 8th floor – 80%, 9th floor – 80% completed, 10th floor – 80%, 11th floor – 80% completed 15th floor- 40%, 13th,14th,16th,18th floor – 20% completed, passage floor tiling – 2nd floor – 95% completed putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 16th floor 98% completed, 17 to 19th floor – 70% completed, terrace water tank completed, Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till 19th floor completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 90% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, plumbing duct line – 2nd to 14th floor – 60% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
-
-
- Structural Works – Ground floor slab – 50% more to be completed, Raft slab – 80% to be completed, BF column 12 Nos: to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling 11th,12th, 13th floor to be completed, Flooring – 12th,13th,14th floor to be completed,passage floor tiling – 1st,3rd,4th,5th floor 95% to be completed, water proofing works – balcony and toilets – 3rd to 19th floors 95% to be completed,
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – 10th,11th,12th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – 2nd to 14th floor 90% to be completed
Work status as on 10-11-2023, we have completed the following.
-
-
- Structural Works – Pile cap – completed, slab – 95% completed, retaining wall – 45% completed, compound wall – 60% completed (42m)
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster -Ground floor – completed, 98% completed (till 19th floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 10th floor (toilets) – 90% completed, 13th floor – 20% completed, 14th,15th,18th floor – 20% completed, Flooring – 3rd floor completed, 4th floor – 80%, 5th floor – 80%, 6th floor – 80%, 7th floor – 80%, 8th floor – 80%, 9th floor – 80% completed, 10th floor – 70%, 15th floor- 40%, 13th,14th,16th,18th floor – 20% completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 70% one coat putty and primer completed, Water proofing – 3rd to 13th floor 98% completed, 14 to 17th floor – 70% completed, terrace water tank 98% completed, Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – 95% completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 15th floor completed, 16th, 17th,18th floor – 40% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 40% completed, Firefighting final fixtures – horizontal pipe line till 16th floor completed, 17th floor – 60% completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 70% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D outside area – 2 coat damp proof, 2 coat putty, one coat primer completed , E, A – 2 coat damp proof completed, 2 coat putty, one coat primer work – 80% completed, plumbing duct line – 2nd to 14th floor – 60% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2023.
-
-
- Inside plastering – 19th floor 100% to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling -up to 10th floor 100% to be completed, 11th ,12th – 80% to be completed, Flooring – 4th to 10th floor 100% to be completed, 11th ,12th – 50% to be completed, water proofing works – balcony and toilets – 3rd to 19th floors 100% to be completed, Handrails – balcony handrail 40% including glass portion to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Gas piping system- 50% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – 4th to 9th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 50% to be completed, External Plastering – 100% to be completed, External painting – E,A – 2 coat putty and one coat primer 100% to be completed, plumbing duct line – 2nd to 14th floor 90% to be completed
Work status as on 10-10-2023, we have completed the following.
-
-
- Structural Works – Pile cap – completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall completed, ramp completed, retaining wall – 45% completed, compound wall – 60% completed (42m), LMR Base slab, roof completed, main and fire stair head room completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster -Ground floor – completed, 98% completed (till 19th floor completed)
- Internal Finishes – Main door -1st to 3rd floor completed, Wall tiling – 3rd to 8th floor (toilets) – 90% completed, 9th floor – 80% completed, 13th floor – 20% completed, 14th,15th,18th floor – 20% completed, Flooring – 3rd floor completed, 4th floor – 80%, 5th – 80%, 6th – 80%, 7th – 80%, 8th – 50%, 9th floor – 50% completed, 13th,14th,16th,18th floor – 20% completed, putty works & Painting – putty 50% completed 1st to 19th floor 2 coat putty & 2 coat primer 90% completed, Water proofing – 40% completed (till 16th floor bathrooms only, balcony – upto 16th floor 100% completed), Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – GF to 2nd floor, 1st to 19th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 15th floor completed,16th, 17th,18th floor – 40% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 10% completed, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 80% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 40% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D outside area – 2 coat damp proof, 2 coat putty, one coat primer completed , E, A – 2 coat damp proof completed, 2 coat putty, one coat primer work – 50% completed, plumbing duct line – 40% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2023.
-
-
- Civil Works – Inside plastering – 19th floor 100% to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling -up to 10th floor 80% to be completed, Flooring – 4th to 10th floor 100% to be completed, Water proofing – 11th,12th – 50% to be completed, water proofing works – balcony and toilets – till 19th floors 100% to be completed, Handrails – balcony handrail 40% including glass portion to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Gas piping system- 50% to be completed, Firefighting final fixtures – 100% to be completed, Electrical wire pulling – 4th to 9th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 50% to be completed, External Plastering – 100% to be completed, External painting – E,A – 2 coat putty and one coat primer 100% to be completed, plumbing duct line – 80% to be completed
Work status as on 13-09-2023, we have completed the following.
-
-
- Structural Works – Pile cap – completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall completed, ramp completed, retaining wall – 40% completed, compound wall – 60% completed (42m), LMR Base slab, roof completed, main and fire stair head room completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – 70% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 8th floor (toilets) – 90% completed, Flooring – 3rd floor completed, 4th, 5th, 6th, 7th, 8th, 9th floor (45% completed), putty works & Painting – putty 50% completed (till 11th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 90% completed, 18th floor – 80% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, primer after two coat putty till 9th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 12th floor 100% completed), Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – GF to 2nd floor, 17th to 19th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 15th floor completed,16th, 17th,18th floor – 40% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 60% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 40% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D outside area – 2 coat damp proof, 2 coat putty, one coat primer completed , E, A – 2 coat damp proof completed), plumbing duct line – 3rd to 9th floor floor completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
-
-
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 19th floor 100% to be completed, GF to be completed
- Internal Finishes – Main door – 50% to be completed, wall tiling – 3rd to 13th floor 100% to be completed, Flooring – 4th to 10th floor 100% to be completed, Water proofing – 11th,12th – 50% to be completed, putty and painting – 10th to 16 th floor 2nd coat putty – 80% to be completed, primer after two coat putty till 14th floor to be completed, water proofing works – balcony and toilets – till 18th floors 100% to be completed, Handrails – Main stair 100% to be completed, balcony handrail 40% including glass portion to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 100% to be completed, Electrical wire pulling – 4th to 9th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 50% to be completed, External Plastering – 100% to be completed, External painting – E,A – 2 coat putty and one coat primer to be completed, plumbing duct line – till 19th floor to be completed
Work status as on 12-08-2023, we have completed the following.
-
-
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall completed, ramp completed, retaining wall – 40% completed, compound wall – 60% completed (42m), LMR Base slab completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – 70% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 8th floor (toilets) – 60% completed, Flooring – 3rd floor (A,B,C,D,E – 82% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (25% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 90% completed, 18th floor – 80% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 12th floor 100% completed), Door frame fixtures -completed, Handrails – 20% completed (firestair handrail GF to 14th floor completed, Main stair – GF to 2nd floor, 17th to 19th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 12th floor, 13th floor – 60% completed , 14th,15th,16th floor – 20% completed, Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 50% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 20% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 70% completed, one putty – 30% completed, 2nd coat – 15% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
-
-
- Structural Works – LMR roof to be completed, main and fire stair head room to be completed
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 19th floor 100% to be completed, GF to be completed
- Internal Finishes – Main door – 50% to be completed, wall tiling – 3rd to 13th floor 100% to be completed, Flooring – 3rd to 10th floor 100% to be completed, Water proofing – 11th,12th – 50% to be completed, putty and painting – 10th to 18 th floor 2nd coat putty – 80% to be completed, water proofing works – balcony and toilets – till 18th floors 100% to be completed, Haindrails – Main stair and Fire stair 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 17th floor – 100% to be completed, Firefighting final fixtures – 100% to be completed, Electrical wire pulling – 4th to 9th floor – 50% to be completed
- External Finishes – External Plastering – 100% to be completed, External painting – Damp proof – 90% to be completed, one putty – 50% to be completed, 2nd coat – 50% to be completed, plumbing duct line – 50% to be completed
Work status as on 12-07-2023, we have completed the following.
-
-
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 30% completed, compound wall – 40% completed (42m), LMR – 30% Completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – 50% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 96% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 8th floor (toilets) – 15% completed, Flooring – 3rd floor (A,B,C,D,E – 82% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (25% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 90% completed, 18th floor – 80% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), 3rd,4th,5th floor 2nd coat putty completed, primer up to 18th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 10th floor 75% completed), Door frame fixtures – 97% completed (18th floor – completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 58% completed (till 12th floor, 13th floor – 25% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 20% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
-
-
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor 100% to be completed
- Internal Finishes – Water proofing – 11th,12th – 50% to be completed
Work status as on 06-06-2023, we have completed the following.
-
-
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 25% completed, compound wall – 40% completed (42m), LMR – 30% Completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 70% completed, Ground floor – 25% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 96% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 7th floor (toilets) – 15% completed, Flooring – 3rd floor (A,B,C,D,E – 82% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (23% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 80% completed, 18th floor – 50% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), 3rd,4th,5th floor 2nd coat putty completed, primer up to 18th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 10th floor 75% completed), Door frame fixtures – 97% completed (18th floor – completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed))
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 58% completed (till 11th floor), Corecutting – till 18th floor completed, 19th floor – 50% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 15% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
-
-
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor 100% to be completed
- Internal Finishes – Water proofing – 11th,12th – 50% to be completed
Work status as on 05-05-2023, we have completed the following.
-
-
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 25% completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 95% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 7th floor (toilets) – 15% completed, Flooring – 3rd floor (A,B,C,D,E – 80% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (20% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 80% completed, 18th floor – 50% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, Water proofing – 37% completed (till 12th floor bathrooms only, balcony – upto 8th floor 75% completed), Door frame fixtures – 95% completed (18th floor – completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed))
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 56% completed (till 10th floor), Corecutting – till 18th floor completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 15th floor completed, fire alarm work started
- External Finishes – Windows & Sliding doors – 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor,6th floor,7th floor – 50% completed, 8th, 9th, 10th – 20% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
-
-
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – 19th floor 100% to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor to be completed
- Internal Finishes – Wall tiling – 8th, 9th floor 50% to be completed, Waterproofing – balcony 9th, 10th – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing work – 60% to be completed
- External Finishes – Windows & Sliding doors – up to 10th floor 80% to be completed
Work status as on 08-04-2023, we have completed the following.
-
-
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 25% completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 90% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 7th floor (toilets) – 14% completed, Flooring – 3rd floor (A,B,C,D,E – 80% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (18% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 80% completed, 18th floor – 50% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, Water proofing – 37% completed (till 12th floor bathrooms only, balcony – upto 8th floor 75% completed), Door frame fixtures – 95% completed (18th floor – 80% completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed))
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 56% completed (till 10th floor), Corecutting – till 16th floor completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 15th floor completed, fire alarm work started
- External Finishes – Windows & Sliding doors – 3rd floor – 75% completed, 4th floor – 75% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
-
-
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – 19th floor 100% to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor to be completed
- Internal Finishes – Wall tiling – 8th, 9th floor 50% to be completed, Waterproofing – balcony 9th, 10th – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing work – 60% to be completed
- External Finishes – Windows & Sliding doors – up to 7th floor 80% to be completed
Click here to see the previous work progress updates.