Artech Rainforest

Project Description

Rainforest a joint venture between Artech & B’ Canti is Kerala’s Greenest Apartment Complex and a project that is nothing like what you have seen before. With 78 ultra-luxurious Apartments, Rainforest is set in one of Trivandrum’s most prestigious locations – Jawahar Nagar, where the ‘crème de la crème’ of the city reside. The unique aspects about Rainforest are the forest inspired ground floor landscape, the tree filled void spaces and the multi-level green community.

At the Rainforest, every apartment window opens onto green vistas.The complex offers 3 & 4 BHK Apartments in 25 different layout options, measuring 2000 sq.ft. to 3840 sq.ft. Some of the select amenities offered at the Rainforest are Health Club, Concierge Service, Guest Suites, Sauna, Spa, Rain water harvesting, Pool, Party Space and so much more to make living here a hearty & serene experience. In the Rainforest you are near to it all and yet so far!

Quick Enquire

Take your first few steps towards finding the ultimate happiness of the Perfect Home.

Location

Artech Rainforest, Jawahar Nagar - Location

Layout

Amenities

  • Health Club
  • Sauna Bath/Steam bath
  • Swimming Pool
  • Association Hall
  • AV Room
  • Guest suite
  • Drivers Rest Room.
  • Party space
  • Children’s Play Area
  • WIFI Lobby
  • Spa
  • Indoor Games Room
  • Video Door Phone
  • F.T.T.H
  • Rain Water Harvesting
  • Reticulated Gas System
  • Incinerator

Progress

Work status as on 08-03-2023, we have completed the following.

  • Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – 90% completed
  • Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 50% completed
  • Internal Finishes – Main door – 42 apartments completed, Waterproofing – 15th floor – 75% completed, terrace – 25% completed, wall tiling – 43 apartments completed, flooring – 30 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 50% Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 90% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 25 apartments completed, HT work – cable tray work started
  • External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 85% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2023.

  • Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
  • Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
  • Internal Finishes – Maindoor – 56 more numbers to be fixed, Waterproofing – 15th floor 100% to be completed, terrace 50% to be completed, Flooring – 5 more apartments to be completed, Handrail – fire stair handrail – 100% to be completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, fire fighting work – 1st floor – 100% to be completed
  • External Finishes – External plastering – 100% to be completed, Painting – primer 95% to be completed

Work status as on 11-02-2023, we have completed the following.

  • Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 80% completed, Ground floor – 80% completed, OHT wall – 100% completed
  • Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 50% completed, Ground floor – 50% completed
  • Internal Finishes – Main door – 42 apartments completed, Waterproofing – 13th, 14th floor 50% completed, basement 2 50% completed, wall tiling – 42 apartments completed, flooring – 20 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 71 nos: completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 25 apartments completed, HT work – cable tray work started
  • External Finishes – Windows and sliding doors – mockup only, External plastering – 90% completed, External painting – primer 80% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2023.

  • Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 90% to be completed
  • Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
  • Internal Finishes – Waterproofing – 13th floor 100% to be completed, 1st floor – 100% to be completed, basement 2 floor – 100% to be completed, Wall tiling – 1 more apartment to be completed, Flooring – 3 more apartments to be completed, Handrail -staircase handrail – 50% to be completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, fire fighting work – 1st floor – 100% to be completed.
  • External Finishes – External plastering – 95% to be completed, Painting – primer 85% to be completed

Work status as on 14-01-2023, we have completed the following.

  • Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 80% completed, Ground floor – 75% completed, OHT Slab – 100% completed
  • Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 90% completed, basement 2 floor – 50% completed, Ground floor – 50% completed
  • Internal Finishes – Main door – 42 apartments completed, Waterproofing – 13th floor 50% completed, basement 2 50% completed, 1st – 50% completed, 2nd, 3rd floor – 100% completed, wall tiling – 42 apartments completed, flooring – 13 apartments completed, putty works – 95% completed, Door frame fixtures- 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 49 nos: completed, Corridor handrail works -90% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 15 apartments completed, HT work – cable tray work started
  • External Finishes – Windows and sliding doors – mockup only, External plastering – 90% completed, External painting – primer 80% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2023.

  • Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed, OHT wall – 100% to be completed
  • Civil Works – Masonry – Block/Brick – Basement 1 floor 100% to be completed, basement 2 floor – 75% to be completed, Ground floor – 100% to be completed
  • Internal Finishes – Waterproofing – 13th floor 100% to be completed, 1st floor – 100% to be completed, basement 2 floor – 100% to be completed, Wall tiling – 1 more apartment to be completed, putty works – 100% to be completed, Flooring – 3 more apartments to be completed, Handrail -staircase handrail – 50% to be completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 12 more apartments to be completed, fire fighting work – 1st floor – 100% to be completed
  • External Finishes – External plastering – 95% to be completed, Painting – primer 85% to be completed

Work status as on 13-12-2022, we have completed the following

As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2022.

  • Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
  • Civil Works – wall plastering – 15th floor 100% to be completed, Masonry – Block/Brick – Basement 1 floor 100% to be completed, basement 2 floor – 75% to be completed, Ground floor – 50% to be completed
  • Internal Finishes – Main door – 20 apartments more to be fixed, Waterproofing – 12th floor 100% to be completed, 13th floor 50% to be completed, Wall tiling – 1st floor 100% to be completed, putty works – 15th floor 100% to be completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Electrical LT work – wire pulling 12 more apartments to be completed
  • External Finishes – External plastering – 90% to be completed, Painting – primer 85% to be completed

Work status as on 13-12-2022, we have completed the following.

  • Structural Works – LMR – 100% completed, Swimming pool slab – 100% completed, basement 2 level parapet – 75% completed, Ground floor – 75% completed
  • Civil Works – Ceiling plastering – 15th floor 100% completed, wall plastering – 15th floor 90% completed, Masonry – Block/ brick- 15th floor 100% completed, Basement 1 floor 50% completed, basement 2 floor – 50% completed, Ground floor – 25% completed
  • Internal Finishes – Main door – 20 apartments completed, Waterproofing – 13th floor 50% completed, basement 2 50% completed, 1st, 2nd, 3rd floor – 50% completed, wall tiling – 42 apartments completed, flooring – 6 apartments completed, putty works – 95% completed, Door frame fixtures- 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 43 nos: completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 10th floor – 100% completed, Electrical LT work – wire pulling – 6 apartments completed, HT work – cable tray work started
  • External Finishes – Windows and sliding doors – mockup only, External plastering – 80% completed, External painting – primer 80% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2022.

    • Structural Works – swimming pool – 75% to be completed, basement 2 level parapet – 100% to be completed
    • Civil Works – wall plastering – 15th floor 100% to be completed, Masonry – Block/Brick – Basement 1 floor 100% to be completed
    • Internal Finishes – Main door – 15 apartments more to be fixed, Waterproofing – 12th floor 100% to be completed, 13th floor 50% to be completed, Wall tiling – 1st floor 100% to be completed, putty works – 15th floor 100% to be completed.

Electrical, Plumbing & Firefighting works – Concealed plumbing works – 2nd, 1st floor 100% to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Fire fighting work – 10th floor 100% to be completed, Electrical LT work – wire pulling 6 more apartments to be completed

  • External Finishes – External plastering – 90% to be completed, Painting – primer 85% to be completed

Work status as on 15-11-2022, we have completed the following.

  • Structural Works – Pile cap – 100% completed, slab completed – 16th Floor 100% completed, LMR – 100% completed, Swimming pool – 40% completed, basement 1 level parapet – 100% completed, basement 2 level parapet – 75% completed.
  • Civil Works – Ceiling plastering – 15th floor 100% completed, wall plastering – 15th floor 90% completed, Masonry – Block/ brick- 15th floor 100% completed, Basement 1 floor 50% completed.
  • Internal Finishes – Main door – 13 apartments completed, Waterproofing – 12th floor 50% completed, basement 1 floor 100% completed, basement 2 50% completed, wall tiling – 2nd, 3rd, 8th floor 100% completed, flooring – mock up only, putty works – 14th floor – 100% completed, Door frame fixtures-15th floor 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 8th floor 100% completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 9th floor – 100% completed, Electrical LT work – upto 15th floor 100% completed, wire pulling – 3 apartments completed, HT work – cable tray work started
  • External Finishes – Windows and sliding doors – mockup only, External plastering – 80% completed, External painting – primer 80% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.

Work status as on 11-10-2022, we have completed the following.

  • Structural Works – Pile cap – 100% completed, slab completed – 16th Floor 100% completed, LMR – 75% completed, Swimming pool – 40% completed, basement 1 level parapet – 100% completed, basement 2 level parapet – 50% completed.
  • Civil Works – Ceiling plastering – 15th floor 90% completed, wall plastering – 14th floor 100% completed, Masonry – Block/ brick- 15th floor 100% completed
  • Internal Finishes – Main door – 5 apartments completed, Waterproofing – 10th floor 90% completed, 11th floor 90% completed, wall tiling – 8th floor 80% completed, 3rd floor – 75% completed, flooring – mock up only, putty works – 14th floor – 100% completed, Door frame fixtures-15th floor 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 8th floor 100% completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 8th floor – 100% completed, Electrical LT work – upto 14th floor 100% completed, HT work – cable tray work started
  • External Finishes – Windows and sliding doors – mockup only, External plastering – 80% completed, External painting – primer 80% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2022.

  • Structural Works – LMR – 100% to be completed, swimming pool – 75% to be completed, basement 2 level parapet – 100% to be completed
  • Civil Works – Ceiling plastering – 15th Floor 100% to be completed, wall plastering – 15th floor 100% to be completed
  • Internal Finishes – Main door – 15 apartments more to be fixed, Waterproofing – 12th floor 100% to be completed, Wall tiling – 1st & 2nd, 3rd, 8th floor – 100% to be completed, putty works – 15th floor 100% to be completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 2nd, 1st floor 100% to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Fire fighting work – 9th floor 100% to be completed, Electrical LT work – up to 15th floor to be completed
  • External Finishes – External plastering – 90% to be completed, Painting – primer 85% to be completed

Work status as on 17-09-2022, we have completed the following.

  • Structural Works – Pile cap – 100% completed, slab completed – 16th Floor 100% completed, LMR – 50% completed, Swimming pool – 40% completed
  • Civil Works – Ceiling plastering – 15th floor 85% completed, wall plastering – 14th floor completed, Masonry – Block/ brick- 15th floor 100% completed
  • Internal Finishes – Main door – MOCKUP only, Waterproofing – 10th floor 90% completed, 11th floor 75% completed, wall tiling – 5th floor 60% completed, 3rd floor – 30% completed, flooring – mock up only, putty works – 13th floor 70% completed, 14th floor – 100% completed, Door frame fixtures-14th floor 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 7th floor 100% completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 3rd to 7th floor – 100% completed, Electrical LT work – upto 14th floor 100% completed, HT work – cable tray work started
  • External Finishes – External plastering – 75% completed, External painting – primer 50% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed

As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2022.

  • Structural Works – LMR – 100% to be completed, swimming pool – 75% to be completed, basement 1 level parapet – 100% to be completed
  • Civil Works – Ceiling plastering – 15th Floor 100% to be completed, wall plastering – 15th floor 100% to be completed
  • Internal Finishes – Main door – 10 apartments more to be fixed, Waterproofing – 10th,11th floor 100% to be completed, Wall tiling – 5th floor 100% to be completed, 3rd floor – 100% to be completed, putty works – 15th floor 100% to be completed, Door frame fixtures – 15th floor 100% to be completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 3rd floor 100% to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Fire fighting work – 8th floor 100% to be completed, Electrical LT work – up to 15th floor to be completed
  • External Finishes – External plastering – 85% to be completed, Painting – primer 75% to be completed.

Work status as on 09-07-2022, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed. GF north side drive way – 50% completed
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, Masonry – Block/ brick- inside flat area completed , Screeding – 45% (till 10th floor – 100% completed).
  • Internal Finishes – Main door – frame only -100% completed, Waterproofing up to 13th floor completed, (lift well -2, rainwater harvesting tank outside completed), Wall tiles – up to 11th floor completed, Floor Tiling up to 10th floor inside flat area completed, putty works & inside painting works – 72% completed (2nd coat putty completed, 1 coat primer completed), Handrails – 87% completed (main stair – till 14 th floor completed , fire stair – till 14 th floor completed, balcony handrail – till 19th floor completed).
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 13th floor, 18th floor completed, Fire fighting works – (2nd, 3rd, 5th, 6th floor – 70% completed) 20% completed
  • External Finishes – Windows and sliding door – mockup only, External Plastering – Elevation 2 (100%) & 3 (97%)Completed, Elevation 1 – 90% completed, Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work – 70% completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2022.

  • Structural Works – All Sub-Structural and Structural work 98% Completed. GF north side drive way – 50% completed
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, Masonry – Block/ brick- inside flat area completed , Screeding – 45% (till 10th floor – 100% completed).
  • Internal Finishes – Main door – frame only -100% completed, Waterproofing up to 13th floor completed, (lift well -2, rainwater harvesting tank outside completed), Wall tiles – up to 11th floor completed, Floor Tiling up to 10th floor inside flat area completed, putty works & inside painting works – 72% completed (2nd coat putty completed, 1 coat primer completed), Handrails – 87% completed (main stair – till 14 th floor completed , fire stair – till 14 th floor completed, balcony handrail – till 19th floor completed).
  • Electrical, Plumbing & Firefighting works -Concealed plumbing works- up to 13th floor, 18th floor completed, Fire fighting works – (2nd, 3rd, 5th, 6th floor – 70% completed) 20% completed
  • External Finishes – Windows and sliding door – mockup only, External Plastering – Elevation 2 (100%) & 3 (97%)Completed, Elevation 1 – 90% completed, Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work – 70% completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
  • Mockup – Completed.

Work status as on 09-06-2022, we have completed the following.

  • Structural Works – Pile cap – 99% completed, slab completed – 16th Floor 100% completed
  • Civil Works – Ceiling plastering- Basement 2 – 100% completed, 15th floor 70% completed, wall plastering- 13th floor 50% completed, Masonry – Block/ brick- 14th floor 100% completed
  • Internal Finishes – Main door – MOCKUP only, Waterproofing- 9th floor 50% completed, 10th floor – 50% completed, wall tiling – mockup only, flooring – mock up only, putty works – 12th floor 20% completed, Door frame fixtures-14th floor 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- 6th floor 75% completed, Corridor handrail works -12th floor 100% completed
  • External Finishes – External plastering – 50% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed, HVAC -50% completed, Toilet tile work-90% completed

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2022.

  • Structural Works – Pile cap – 100% to be completed
  • Civil Works – Ceiling plastering-15th Floor 100% to be completed, wall plastering – 13th floor 100% to be completed, Masonry – Block/ brick- 15th floor 100% to be completed
  • Internal Finishes – Waterproofing – 9th floor, 10th floor 100% to be completed, putty works- 12th floor 100% to be completed
  • Electrical, Plumbing & Firefighting works -Concealed plumbing works – 7th floor 100% to be completed, Corridor handrail works – 13 floor 100% to be completed
  • External Finishes – External plastering – 75% to be completed

Work status as on 12-04-2022, we have completed the following.

  • Structural Works – Entire structure is completed
  • Civil Works – Ceiling plastering- Basement 2 – 50% completed, 14th floor 100% completed, , wall plastering- 11th floor 70% completed, Masonry – Block/ brick- 14th floor 90% completed
  • Internal Finishes – Main door – MOCKUP only, Waterproofing- 8th floor 50% completed, putty works – 8th floor 100% completed, Door frame fixtures-13th floor 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- 4th floor, 5th floor 90% completed, Corridor handrail works -12th floor 100% completed.
  • External Finishes – External plastering – 30% completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed, HVAC -50% completed, Toilet tile work-90% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2022.

  • Civil Works – Ceiling plastering-15th Floor 100% to be completed, wall plastering-11th floor 100% to be completed, 12th floor – 30% to be completed, Masonry – Block/ brick- 14th floor 100% to be completed
  • Internal Finishes – Waterproofing-8th floor 100% to be completed, putty works- 9th floor 50% to be completed, Door frame fixtures- 14th floor 100% to be completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- 4th, 5th floor – 100% to be completed, 6th floor – 50% to be completed, Corridor handrail works -13 floor 100% to be completed.
  • External Finishes – External plastering – 50% to be completed.

Work status as on 10-03-2022, we have completed the following.

  • Structural Works – Pile cap – 99% completed, slab completed – 16th Floor 80% completed
  • Civil Works – Ceiling plastering-14th floor100% completed, wall plastering- 11th floor 30% completed, Masonry – Block/ brick- 14th floor 60% completed
  • Internal Finishes – Main door – MOCKUP only, Waterproofing- 7th floor 100% completed, putty works – 6th floor 100% completed, Door frame fixtures-12th floor 100% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- 13% completed, Corridor handrail works -11th floor 100% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed, HVAC -50% completed, Toilet tile work-90% completed

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2022.

  • Structural Works – Pile cap – 100% to be completed, slab – 16th floor100% to be completed
  • Civil Works – Ceiling plastering-15th Floor 100% to be completed, wall plastering-11th floor 100% to be completed, 12th floor – 30% to be completed, Masonry – Block/ brick- 14th floor 100% to be completed
  • Internal Finishes – Waterproofing-8th floor 100% to be completed, putty works- 7th floor 100% to be completed, Door frame fixtures- 13th floor 100% to be completed, 14th floor 100% to be completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- 20% to be completed, Corridor handrail works -12 floor 100% to be completed

Work status as on 09-04-2021, we have completed the following.

    • Earthwork – 90% completed
    • Pile chipping work – completed
    • Pile cap work -92% completed
    • RCC for slab
      • BF2-11th floor slab -RCC work -100% completed
    • Column work :
      • BF2 – 10 th floor -100% completed ,11th floor -50% completed.
    • RCC for Ramp
      • BF2- 80% completed, BF1- 90% completed
    • Ceiling Plastering
      • 1st floor:- 70% completed
      • Ceiling Plastering (2nd floor-9th floor ):90% completed
    • Electrical wall chasing
      • 2nd floor – 20% completed,3rd floor-70% completed,4th floor-80% completed.
    • wall plastering
      • 2nd floor – 20% completed.
    • Blockwork
      • 1st floor-50% completed ,2ndfloor -75% completed, 3rd-5th floor -90% completed,6th floor – 25% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2021.

        • RCC for slab
          • 12th floor-75% to be completed
        • Column work :
          • 11th floor – 100% to be completed
          • 12th floor-20% to be completed.
        • Rcc for Retaining wall
          • Base floor2-25% to be completed.
        • RCC for Ramp
          • Ceiling – 1st floor:- 90% to be completed
        • Electrical wall chasing
          • 2nd floor – 25% to be completed
        • Blockwork
          • 6th floor:-90% to be completed, 7th floor-30% to be completed.

Work status as on 11-03-2021, we have completed the following.

Tower 1

            • Internal wall plastering work -up to 18th floor -100% completed, Roof-75% completed.
            • Dadoing of toilets: up to 15th floor -100% completed.
            • Dadoing of kitchen walls :GF – 50% completed,1st floor-13th floor-100% completed,
            • Wire pulling : GF -30%,1st and 3 rd,5 th ,7 th  -90%,2,4,8th -25% completed,6th,9th-15th floor-100% completed,16th floor- 50% completed.
            • Water Proofing work – Upto 18th floor- 100% completed,terrace -75% completed
            • External (1st coat) Putty work  -at south and west -85% completed.
            • External (2nd coat) Putty work  -at south and west -85% completed.
            • Primer – at south and west -85% completed.’
            • Plumbing  work – upto 17th floor- 100% completed
            • Flooring and skirting ,, -GF,15th floor-25% Completed 3rd-5th ,7th,8th,11th,12thfloor:-100% completd,1st,6th,9th,10th floor -80% completed,,13th-14th floor:-50% completed.
            • Fixing of door shutters -1st Floor -25%completed
            • Fire Fighting work :GF-18th floor-85% completed

Tower 2

            • RCC for slab – Upto 10th floor- 100% completed, 11th floor-60% completed.
            • Ceiling plastering : BF3-90% completed
            • Electrical Wall Chasing: 1st floor-4th floor- 100 %  completed.
            • Wall Plastering: 1st – 2nd floor-100% completed.
            • Block Work
              • GF -75%  completed, BF2 :-70% completed, BF1-50% completed , BF3-25% completed.
              • 1st floor-5th floor – 100 %  completed
            • Yard work
              • STP RCC -100%  completed.
              • Front gate -100%  completed.
              • Compound wall-100% completed.
            • MLCP
              • BF1 ceiling & column plastering -100% completed.
              • BF2 ceiling & column plastering -80%  completed.
              • BF3 ceiling & column plastering -50%  completed.

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2021.

Tower 1

            • Internal wall plastering work -Roof-100% to be completed.
            • Dadoing of toilets:16th floor -100% to be completed
            • Dadoing of kitchen walls:14th floor-100% to be completed,
              16th floor -100% to be completed,
            • Water Proofing work -floor, terrace -100% to be completed
            • External (1st coat) Putty work -at north 85%to be completed.
            • External (2nd coat) Putty work -.at north 85%to be completed.
            • Primer – at north -85% to be completed.
            • Plumbing work -18th floor-100% to be completed
            • Flooring and skirting :-,14th floor- 100% to be completed, 15th floor:- 50% to be completed
              GF-18th floor- 90% to be completed.

Tower 2

            • RCC for slab -11th roof slab -100% to be completed.,12th-50% to be completed.
            • Ceiling plastering
            • 8th  -100% to be completed
            • Electrical Wall Chasing
            • 5th floor :-100% to be completed.
            • Wall Plastering
            • 3rd floor :-100% to be completed.
            • Block Work
            • BF2:-100% to be completed.
            • 6th floor -100% to be completed.
            • Yardwork: full side retaining wall-50% to be completed.

As per the current work status from our site, we are targeted to complete the following works by the end of February 2021

            • RCC for slab: 11th floor-100% to be completed.
            • Column work: 10th floor – 100% to be completed
            • Rcc for Retaining wall: Base floor2-25% to be completed.
            • RCC for Ramp: BF2- 100% to be completed, BF1- 60% to be completed
            • Ceiling: 9th floor:-50% to be completed
            • Wall plastering: 2ndfloor – 25% to be completed
            • Blockwork: 5th floor:-50% to be completed

Work status as on 09-02-2021, we have completed the following.

            • Earthwork – 90% completed
            • Pile chipping work – completed
            • Pile cap work -92% completed
            • RCC for slab: BF2-10th floor slab-RCC work 100% completed
            • Column work : BF2 – 9 th floor -100% completed ,10th floor -45% completed, RCC for ramp, BF1,BF2 :80% completed,
            • RCC for Ramp: BF2- 60% completed, BF1- 30% completed
            • Ceiling Plastering: 1st floor:- 70% completed
            • Ceiling Plastering (2nd floor-8th floor ):90% completed
            • wall plastering: 2ndfloor – 20% completed
            • Block work: 2ndfloor -3rd floor-75% completed, 4th floor -90% completed,5th floor – 10% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2021
RCC for slab

            • 11th floor-100% to be completed.

Column work :

            • 10th floor – 70% to be completed

Rcc for Retaining wall

            • Base floor2-25% to be completed.

RCC for Ramp

            • BF2- 100% to be completed, BF1- 30% to be completed

Ceiling

            • 9th floor:-50% to be completed

Wall plastering

            • 2ndfloor – 25% to be completed

Blockwork

            • 4th floor:- 100% to be completed

Work status as on 07-01-2021, we have completed the following.

            • Earth work – 90% completed
            • Pile chipping work – completed
            • Pile cap work -92% completed

RCC for slab

            • BF2-10th floor slab -RCC work 100% completed

Column work :

            • BF2 – 9 th floor -100% completed
            • RCC for ramp, BF2 :50% completed

RCC for Ramp

            • BF2- 60% completed, BF1- 30% completed

Ceiling

            • Ceiling Plastering (2nd floor-8th floor ):90% completed, 1st floor:- 70% completed

wall plastering

            • 2ndfloor – 20% completed

Block work

            • 2ndfloor – 50% completed,3rd floor-25% to be completed, 4th floor -80% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of July 2020
RCC for slab

            • 8th floor -90% to be completed.

Column work :

            • 8th floor -20% to be completed.

Ceiling

            • Third floor:-100% to be completed,Fourth floor:-90% completed.

Block work

            • Second floor:50% Completed

Work status as on June, we have completed the following.

            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -92% completed

RCC for slab

            • BF2-7th floor slab -RCC work 100% completed
            • 8th floor slab -RCC work 60% completed

Column work :

            • BF2 – 6 th floor -100% completed.
            • 7 th floor -85% completed .
            • RCC for ramp, BF2 :35% completed

Ceiling

            • Ceiling Plastering (2nd floor ):90% completed (3rd floor); 90% completed, forth floor :- 35% completed.

Block work

            • Second floor:10% Completed

As per the current work status from our site, we are targeted to complete the following works by the end of March 2020

            • Rcc for slab upto 8th floor -100% to be completed.
            • Column work : 7th-100% to be completed, 8th floor – 30% to be completed
            • Ceiling: Second floor :100% to be completed, Third floor;100% to be completed.
            • Block work: Second floor:50% to be Completed

Work status as on 11-03-2020, we have completed the following.

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -92% completed
            • RCC for slab – BF1-6th floor slab -RCC work 100% completed, 7th floor slab -RCC work 90% completed
            • Column work: 6th floor -100% completed, 7th floor -40% completed, RCC for ramp, BF2 :35% completed
            • Ceiling Plastering (2nd floor ):90% completed (3rd floor); 70% completed
            • Block work: Second floor:10% Completed

As per the current work status from our site, we are targeted to complete the following works by the end of February 2020

            • Rcc for slab 7th 100% to be completed.
            • Column work : 6th-100% to be completed, 7th 30% to be completed, Base floor 2 : 35% to be completed
            • Ceiling: Second floor: 100% to be completed, Third floor: 70% to be completed
            • Block work (2ndfloor): 50% to be Completed

Work status as on 08-02-2020, we have completed the following.

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • RCC for slab – BF2 slab – 100%completed.
            • BF1-6th floor slab -RCC work 100% completed
            • Column work: 6th -45% completed.
            • RCC for ramb, BF2 :15% Completed
            • Ceiling Plastering (2nd floor ): 90% completed, (3rd floor): 20% completed
            • Block work (2nd floor): 10% Completed

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2020

            • 6th floor slab -100% to be completed.
            • Column work : 5 th -6 th -100%,6-7 th -25% to be completed
            • Block work (2 ndfloor):25% to be Completed

Work status as on 10-01-2020, we have completed the following.

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • RCC for slab – BF2 slab – 100%completed.
            • BF1-5 th floor slab -RCC work 100% completed
            • 6 th floor -60% completd.
            • Column work : 5-6 th -75% completed .
            • Ceiling Plastering (2nd floor ): 50% completed
            • Block work (2nd floor): 10% Completed

As per the current work status from our site we are targeted to complete the following works by end of September 2019

            • 5 th floor slab -45% to be completed,6 th floor slab -30% to be completed .
            • Third floor Column work-80% completed, 4 th floor column work -45% completed,5 th floor -25% to be completed.

Work status as on 05.09.2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • RCC for slab – BF2 slab – 100%completed.
            • BF1 slab -RCC work 100% completed
            • Ground floor slabs -RCC Work100%completed.
            • First floor slab -100%completed
            • Second floor slab -100% completed
            • Third floor slab -100% completed 4th floor -45% completed 5 th -30% completed
            • BF2- 1st floor Column Rcc work -100% completed,Second floor Column work – 100% completed
            • Third floor Column work-51% completed, 4 th floor column work -37% completed,5 th floor -25% completed.

As per the current work status from our site we are targeted to complete the following works by end of August 2019

            • Third floor slab -100% ,4 th floor slab -60%,5 th floor slab -45% to be completed.
            • Fourth floor Column work-40% to be completed,5 th floor column work -25% to be completed

Work status as on 05.09.2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • RCC for slab – BF2 slab – 100%completed.
            • BF1 slab -RCC work 100% completed
            • Ground floor slabs -RCC Work100%completed.
            • First floor slab -100%completed
            • Second floor slab -100% completed
            • Third floor slab -75% completed, 4th floor -45% completed, 5th -30% completed
            • BF2- 1st floor Column Rcc work -100% completed,Second floor Column work – 100% completed
            • Third floor Column work-42% completed, 4 th floor column work -36% completed.

As per the current work status from our site we are targeted to complete the following works by end of July 2019

            • Third floor slab -100% ,4 th floor slab -45%,5 th floor slab -30% to be completed.
            • Second floor Column work -100% to be completed
            • Fourth floor Column work-40% to be completed

Work status as on 06.07.2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • RCC for slab – BF2 slab – 100%completed.
            • BF1 slab -RCC work 100% completed
            • Ground floor slabs -RCC Work100%completed.
            • First floor slab -100%completed
            • Second floor slab -100% completed
            • Third floor slab -60% completed,4th floor -30% completed
            • BF2- 1st floor Column Rcc work -100% completed
            • Second floor Column work – 95% completed
            • Third floor Column work-42% completed, 4 th floor column work -10% to be completed.

As per the current work status from our site we are targeted to complete the following works by end of June 2019

            • Pile chipping work -321 nos to be completed
            • Third floor slab -100% to be completed
            • Second floor Column work -100% to be completed
            • Third floor Column work-40% to be completed
            • Retaining wall -10% to be completed

Work status as on 06.06.2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • RCC for slab – BF2 slab – 100%completed.
            • BF1 slab -RCC work 100% completed
            • Ground floor slabs -RCC Work100%completed.
            • First floor slab -100%completed
            • Second floor slab -100% completed
            • Third floor slab -45% completed
            • BF2- 1st floor Column Rcc work -100% completed
            • Second floor Column work – 84% completed
            • Third floor Column work-24% completed

As per the current work status from our site we are targeted to complete the following works by end of May 2019

            • Pile chipping work -321 nos to be completed
            • Pile cap work – 68 to be completed (out of 72)
            • Second floor slab -100% tobe completed
            • Third floor slab -45% to be completed
            • Second floor Column work – 70% completed

Work status as on 06.05.2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • RCC for slab – BF2 slab – 100%completed.
            • BF1 slab -RCC work 100% completed
            • Ground floor slabs -RCC Work100%completed.
            • First floor slab -100%completed
            • Second floor slab -90% completed
            • Third floor slab -30% completed
            • BF2- 1st floor Column Rcc work -100% completed
            • Second floor Column work – 53.50% completed
            • Third floor Column work-15% completed

As per the current work status from our site we are targeted to complete the following works by end of April 2019

            • Pile chipping work -321 nos to be completed
            • Pile cap work – 68 to be completed (out of 72)
            • Second floor column work -40% completed
            • Second floor roof slab -40% to be completed

Work status as on 05.04.2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work -66nos completed (out of 72)
            • Grade slab work – 100% completed
            • RCC for slab – BF2 roof slab – 100%completed.
            • BF1roof slab -RCC work 100% completed
            • Ground floor roof slabs -RCC Work100%completed.
            • First floor roof slab -100%completed
            • BF1 Column Rcc work -100% completed
            • GF Column work – 100% completed
            • First Floor Column work-100% completed
            • Second floor column work -20% completed
            • Second floor roof slab -20%completed

As per the current work status from our site we are targeted to complete the following works by end of March 2019

            • Second floor roof slab -40% to be completed
            • Pile chipping work -321 nos to be completed
            • Pile cap work – 100% to be completed (out of 72)

Work status as on 06-03-2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 319 nos completed (out of 323)
            • Pile cap work – 69 nos completed (out of 72)
            • Grade slab work – 100% completed
            • RCC for slab – BF2 roof slab – 100%completed.
            • BF1 roof slab -RCC work 100% completed
            • Ground floor roof slabs -RCC Work 100%completed.
            • First floor roof slab -100%completed
            • Rear Portion Transfer Slab -100% completed
            • BF1 Column Rcc work -100% completed
            • GF Column work – 100% completed
            • First Floor Column work-100% completed
            • Second floor roof slab -20%completed

As per the current work status from our site we are targeted to complete the following works by end of February 2019

            • Pile chipping work – 100% to be completed
            • Pile cap work – 100% to be completed (out of 72)
            • Rear Portion Transfer Slab -100% to be completed
            • Second floor roof slab -40% to be completed

Work status as on 05-02-2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 317 nos completed (out of 323)
            • Pile cap work – 69nos completed (out of 72)
            • Grade slab work – 100% completed
            • RCC for slab – BF2 roof slab – 100%completed.
            • BF1 roof slab -RCC work 100% completed
            • Ground floor roof slabs -RCC Work100%completed.
            • First floor roof slab -100%completed
            • Rear Portion Transfer Slab -90% completed
            • BF1 Column Rcc work -100% completed
            • GF Column work – 100% completed
            • First Floor Column work-100% completed
            • Second floor roof slab -20%completed

As per the current work status from our site we are targeted to complete the following works by end of January 2019

            • Earth work – 100% to be completed
            • Pile cap work – 67 nos to be completed (out of 72)
            • Rear Portion Transfer Slab -100% to be completed

Work status as on 08-01-2019, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 317 nos completed (out of 323)
            • Pile cap work – 66 nos completed (out of 72)
            • Grade slab work – 100% completed
            • RCC for slab – BF2 roof slab – 100%completed.
            • BF1roof slab -RCC work 100% completed
            • Ground floor roof slabs -RCC Work100%completed.
            • First floor roof slab -60%completed
            • Rear Portion Transfer Slab -50% completed
            • BF1 Column Rcc work -100% completed
            • GF Column work – 100% completed
            • First Floor Column work-60% completed

As per the current work status from our site we are targeted to complete the following works by end of December 2019

            • Earth work – 100% to be completed
            • Pile cap work – 67 nos to be completed (out of 72)
            • First floor roof slab (A flat portion)-100% to be completed
            • Rear Portion Transfer slab -100% to be completed.
            • GF Column work – 100% to be completed

Work status as on 06-12-2018, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 317 nos completed (out of 323)
            • Pile cap work – 66 nos completed (out of 72)
            • Grade slab work – 100% completed
            • RCC for slab – BF2 roof slab – 100%completed.
            • Ground floor slab RCC Work-100%completed.
            • BF1 Column Rcc work -100% completed
            • BF1 roof slab work – 100% completed
            • GF Column work – 85% completed
            • First Floor Column work-10% completed

As per the current work status from our site we are targeted to complete the following works by end of November 2018

            • Earth work – 100% to be completed
            • Pile cap work – 67 nos to be completed (out of 72)
            • Grade slab work – 100% to be completed
            • RCC for slab – BF2 roof slab – 100% to be completed
            • B1 Column Rcc work – 100% to be completed
            • BF1 roof slab work – 100% to be completed
            • GF Column work – 50% to be completed
            • GF Slab RCC work – 50% to be completed

Work status as on 16-11-2018, we have completed the following

            • Piling work – 100% completed
            • Earth work – 90% completed
            • Pile chipping work – 317 nos completed (out of 323)
            • Pile cap work – 66 nos completed (out of 72)
            • Grade slab work – 94% completed
            • RCC for slab – BF2 roof slab – 90% completed
            • BF1 Column Rcc work – 95% completed
            • BF1 roof slab work – 95% completed
            • GF Column work – 25% completed
            • GF Slab RCC work – 10% completed