Work status as on 13-09-2023, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet – 99% completed, Ground floor parapet – 50% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 85% completed, Ground floor – completed, water tank plastering – 100% completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – completed, OHT – Completed, wall tiling – 57 apartments completed, flooring – 56 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Balcony handrails – 25% completed
- Electrical, Plumbing & Firefighting works – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – completed, OHT – Completed, wall tiling – 57 apartments completed, flooring – 56 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Balcony handrails – 25% completed
- External Finishes – Windows and sliding doors – 50% completed, duct door – 66% completed, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor parapet – 75% to be completed
- Civil Works – basement 2 level parapet – 100% to be completed, Ground floor parapet – 75% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 4 more apartments to be completed, Wall tiling – 4 more apartments to be completed, Balcony handrail – 35% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 12th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 7 more apartments to be completed
- External Finishes – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 12th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 7 more apartments to be completed
Work status as on 12-08-2023, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet – 95% completed, Ground floor parapet – 35% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 95% completed, water tank plastering – 100% completed
- Internal Finishes – Main door – 80 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – completed, OHT – Completed, wall tiling – 53 apartments completed, flooring – 51 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Balcony handrails – 15% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 1st to 10th floor – 100% completed, Electrical LT work – wire pulling – 60 apartments completed, HT work – 66 apartments completed, HVAC work – 14 apartments completed
- External Finishes – Windows and sliding doors – 40% completed, duct door – 65% completed, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor parapet – 50% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 4 more apartments to be completed, Wall tiling – 4 more apartments to be completed, Balcony handrail – 25% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 11th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 7 more apartments to be completed
- External Finishes – Windows and sliding doors – 50% to be completed, Duct door – 75% to be completedExternal plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 12-07-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 90% completed
- Internal Finishes – Main door – 80 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – 100% completed, OHT – Completed, wall tiling – 43 apartments completed, flooring – 40 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 47 apartments completed, HT work – 34 apartments completed, HVAC work – 4th floor completed
- External Finishes – Windows and sliding doors – mockup only, duct door – 50% completed, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
- Structural Works – basement 2 level parapet – 100% to be completed
- Civil Works – Masonry – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 5 more apartments to be completed, Wall tiling – 7 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 11th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 5th floor to be completed
- External Finishes – Duct door – 75% to be completedExternal plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 06-06-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 90% completed
- Internal Finishes – Main door – 80 apartments completed, Waterproofing – terrace – 75% completed, Sump tank – 100% completed, OHT – 75% Completed, wall tiling – 43 apartments completed, flooring – 40 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 45 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
- Structural Works – basement 2 level parapet – 100% to be completed,
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Maindoor – 3 more numbers to be fixed, Waterproofing – OHT Tank – 100% to be completed, terrace 85% to be completed, Flooring – 5 more apartments to be completed, Wall tiling – 7 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, Electrical LT work – wire pulling 7 more apartments to be completed
- External Finishes – External plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 05-05-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – 90% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 80% completed
- Internal Finishes – Main door – 63 apartments completed, Waterproofing – terrace – 40% completed, Sump tank – 100% completed, wall tiling – 43 apartments completed, flooring – 37 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 40 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Maindoor – 11 more numbers to be fixed, Waterproofing – OHT Tank – 75% to be completed, terrace 75% to be completed, Flooring – 5 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed
- External Finishes – External plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 08-04-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – 90% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 75% completed
- Internal Finishes – Main door – 56 apartments completed, Waterproofing – 15th floor – 75% completed, terrace – 40% completed, Sump tank – 75% completed, wall tiling – 43 apartments completed, flooring – 35 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 35 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 90% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Maindoor – 18 more numbers to be fixed, Waterproofing – sump tank – 100% to be completed, terrace 75% to be completed, Flooring – 5 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed
- External Finishes – External plastering – 100% to be completed, Painting – primer 95% to be completed