Progress
As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.
- FLOORING: 2nd-4th floor -100% to be completed
- ELECTRICAL LT WALL CHASING: Up to 15th floor:- 100% to be completed
- FIREWORK: Up to 17th floor:- 100% to be completed
- PLUMBING WORK: Up to 13th floor-90% to be completed.
- WATERPROOFING: up to level 17th:-100% to be completed
- TOWER A Footing work : 36 footings to be completed (out of 57)(UNIT A )third slab – 25% completed
C BLOCK
- Footing work: Podium level:100% to be completed, Parking slab 1st level:- 100% to be completed, second slab at( 108.35):-100% to be completed.
- Retaining area RCC work: Retaining wall RCC 100% to be completed.
CLUB HOUSE AREA
- Rock breaking work- 100% to be completed
- 1st level slab:-100% to be completed
Work status as on 09-02-2021, we have completed the following.
D BLOCK
- RCC Work – Completed
- Block Work: Up to 17th floor:- 100% completed
- CEILING PLASTERING WORK: Up to 17th floor:- 100% completed
- WALL PLASTERING: up to Level -17th:-100% completed
- FLOORING: 2nd-4th floor -90% completed
- ELECTRICAL LT WALL CHASING: Up to Level 17th -100% completed
- WALL PUTTY: Up to 9th floor:- 100% completed
- FIREWORK: Up to 15th floor :- 95% completed
- PLUMBING WORK: Up to 9th level(DBCEF):- 90% completed, up to 8th floor (AGH)-90% completed.
- WATER PROOFING: UPTO LEVEL 13th :-100% Completed (except balcony)
TOWER A
- Footing work:Total 31 footiings completed (out of 57), (UNIT A )first slab – 25% completed, (UNIT A)Second slab – 25% completed( centering and shuttering)
C BLOCK
- Footing work: Building area – 100% completed Podium level :60% completed, stilt level (104.35 slab) – 90% completed,second slab at( 108.35):-60% completed.
- RCC Work :RCC Work: Retaining wall RCC 40Meters(Out of 47 meters )
CLUB HOUSE AREA
- Rock breaking work- 95% completed
- Column footing -100% column footing work completed.
- 1st level slab:- 90% completed, 2nd level column:-90% completed, 3rd level slab-90% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2021
- FLOORING: 2nd-4th floor -100% to be completed
- ELECTRICAL LT WALL CHASING: Up to 15th floor:- 100% to be completed
- FIREWORK: Up to 15th floor:- 100% to be completed
- PLUMBING WORK: Up to 13th floor-90% to be completed.
- WATERPROOFING: up to level 17th:-100% to be completed
- TOWER A Footing work : 30 footings to be completed (out of 57)(UNIT A )third slab – 25% completed
C BLOCK
- Footing work: Podium level:100% to be completed, Parking slab 1st level:- 100% to be completed, second slab at( 108.35):-100% to be completed.
- Retaining area RCC work: Retaining wall RCC 100% to be completed.
CLUB HOUSE AREA
- Rock breaking work- 100% to be completed
- Column footing -100% column footing work completed.
- 1st level slab:-100% to be completed
Work status as on 07-01-2021, we have completed the following.
D BLOCK
- RCC Work – Completed
- Block Work: Up to 17th floor:- 100% completed
- CEILING PLASTERING WORK: Up to 17th floor:- 100% completed
- WALL PLASTERING: up to Level -17th:-100% completed
- FLOORING: 2nd-4th floor -90% completed
- ELECTRICAL LT WALL CHASING: Up to Level 17th -100% completed
- WALL PUTTY: Up to 8th floor:- 100% completed
- FIREWORK: Up to 12th floor :- 95% completed
- PLUMBING WORK: Up to 9th level(DBCEF):- 90% completed, up to 8th floor (AGH)-90% completed.
- WATER PROOFING: UPTO LEVEL 13th :-100% Completed (except balcony)
TOWER A
- Footing work:Total 26 footiings completed (out of 57), (UNIT A )first slab – 25% completed, (UNIT A)Second slab – 25% completed( centering and shuttering)
C BLOCK
- Footing work: Building area – 100% completed,Podium level :50% completed, stilt level (104.35 slab) – 80% completed,second slab at( 108.35):-50% completed.
- RCC Work :RCC Work: Retaining wall RCC 40Meters(Out of 47 meters )
CLUB HOUSE AREA
- Rock breaking work- 95% completed
- Column footing -90% column footing work completed.
- 1st level slab:- 90% completed ,2nd level column:-90% completed,3rd level slab-90% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of July 2020
D BLOCK
- Floor Slab RCC Work: Terrace (ALL): 100% to be completed
- Ceiling plastering work: level 16th -100% to be completed, level 17th -100% to be completed
- Wall Plastering: upto level 14th- 100% to be completed.
- ELECTRICAL LT WALL CHASING: upto Level 15th:-100% to be completed
- WATER PROOFING upto level 10th: 100% to be completed
C BLOCK
- Earth work excavation at Tower C portion- 100% to be completed
- Footing work: Parking slab 1st level:-50% to be completed
- Retaining area RCC work: Retaining wall rcc 100% to be completed.
CLUB HOUSE AREA
- Rock breaking work- 100% to be completed
Work status as on 11-06-2020, we have completed the following.
D BLOCK
- Floor Slab RCC Work : 15th -17th LeveL: 100% Completed, Terrace: (AB) – 100% completed. (C,D) :- ready for casting
- Block work: Level -1 -100% completed, Level -2 -75 %(A,D,E,F,G,H) completed, Level -3-12 -100% completed, Level -13th -100% completed, (ABCDFGH) Level -14th -95% completed, Level-15th-80% completed.
- Ceiling plastering work: LEVEL :1,-12th – (A,B,C,D,E,F,G,H)1 100% completed, LEVEL -14-15th -100% completed, LEVEL16th -50% completed
- Wall Plastering: upto Level -12th:-100% completed, level 13th- 40% completed.
- ELECTRICAL LT WALL CHASING: Upto Level 13th – 100% completed
- PLUMBING WORK: LEVEL 2 -100% completed, LEVEL 3 –100% completed, LEVEL 4- (A,B,C,D,E,F,G)-100% completed, LEVEL 5 -(A,B,C,D,F,G,H)-: 100% completed, LEVEL 6 -(B,E,C,D,F,G,H)-: 100% completed, LEVEL 7 -(B,E,C,D,F)-: 100% completed
- WATER PROOFING: UPTO LEVEL 6th :-100% Completed, LEVEL 7th, 8th :-90% Completed.
C BLOCK
- Earth work excavation at Tower C portion- 95% completed
- Footing work: Building area – Total 67 nos completed, Podium level :25% completed, stilt level (104.35 slab) – 35% completed
- RCC Work :Retaining wall rcc 40Meters(Out of 47 meters )
CLUB HOUSE AREA
- Rock breaking work- 85% completed
- Column footing -90% column footing work completed.
- 1st level slab:- 90% completed, 2nd level column:-85% completed
- Painting (putty work): 2nd – 5th level-100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2020
LEGACY TOWER
- Floor Slab RCC Work : 15 th level,16 th level – 100% to be completed.
- Block work – upto Level -13-100% to be completed .
- Ceiling plastering work – LEVEL -15 -100% to be Completed
- Wall Plastering – Level10,11-100% to be completed
- ELECTRICAL LT WALL CHASING – LEVEL :9,10, 11-100% to be Completed .
- LEVEL 5:to be started
INSPIRE TOWER
Footing work
- Building area -67nos to be completed(Total 67 nos)
Retaining area RCC work
- RCC Work :Retaining wall rcc 100% to be completed .
- Silt floor slab centering and shuttering get started
Work status as on 10-01-2020, we have completed the following.
LEGACY TOWER
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- Floor Slab RCC Work : 15th Level (A,B,G,H) Completed ,16(A,B,G,H )Casted ,(C,D )-Centering and shuttering on progressing .
Block work
- Level -1 -100% completed
- Level -2 -75 %(A,D,E,F,G,H) completed
- Level -3-11 -100% completed .
- Level -12th -65% completed
Ceiling plastering work
- LEVEL :1,-12th – (A,B,C,D,E,F,G,H)1 100% completed.
- LEVEL -14-75% completed
Wall Plastering
- Level -1-10%(1D,1C,1B) completed
- Level -2 -75 %(A,D,E,F,G,H) completed
- Level -3-8*(A,B,C,D,E,F,G,H)-100%completed
- Level -9-(A,H)100%completed
ELECTRICAL LT WALL CHASING
- LEVEL :1,3,4,5,6,7,8(A,B,C,D,E,F,G,H)-100% Completed
- LEVEL :2(A,D,H,G,E,F)-75% Completed
- LEVEL :9(A,C)-100% Completed ,10th -(A,H) Completed
PLUMBING WORK
- LEVEL 2 -(A,D,,E,F,G,H )-In progressing
- LEVEL 3 -(A,C,D,E,F,H )-in progressing
- LEVEL 4-6 -(D,E,F)-in progressing
WATER PROOFING
- LEVEL 2-3(A,H,G,E,F,D) 100% Completed
- LEVEL 3: 100% Completed ,LEVEL 4:In progress
INSPIRE TOWER
- Earth work excavation at Tower C portion- 95% completed
Footing work
- Building area -60nos completed(Total 67 nos)
- Podium level :7Nos completed
Retaining area RCC work
- RCC Work :Retaining wall rcc 40Meters(Out of 47 meters )
CLUB HOUSE AREA
- Rock breaking work- 80% completed
- Column footing -65% column footing work completed.
As per the current work status from our site we are targeted to complete the following works by end of September 2019
D Block
- Floor Slab RCC Work : 13 th level& 14 th level – 100% to be completed.
- Block work upto Level -11-100% to be completed .
- Ceiling plastering work: LEVEL -12,13 -100% to be Completed
- Wall Plastering: Up to Level -10-100% to be comppleted
C Block
- Footing work – Building area -49nos to be completed(Total 67 nos)
- Retaining area RCC Work :Retaining wall rcc 100% to be completed
Work status as on 05.09.2019, we have completed the following
D block
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- Floor Slab RCC Work : 1-12th level completed,13th- level( A ,B ),-Casted ,G&H -Rebar fixing on progress
- Block work -Level -1-100% completed
- Block work -Level -2 -75%(A,D,E,F,G,H) completed
- Level -3-,4,5,6,7 ,8 th -100%completed
- Ceiling plastering work: LEVEL :1,-10 th – (A,B,C,D,E,F,G,H)1 100% completed.
- Ceiling plastering work: LEVEL -11 -40% Completed
- Wall Plastering: Level -1-10%(1D,1E,1F) completed
- Wall Plastering: Level -2 -75 %(A,D,E,F,G,H) completed
- Wall Plastering: Level -3-90%(A,B,C,E,F,G,H)completed
- Wall Plastering: Level -4-50%(A.E,F)completed
- Wall Plastering: Level -5-D(Completed )-A in Progress
- Wall Plastering: Level -6-E& F Completed ,B& G in Progress
- Electrical LT Work -Wall Chasing: LEVEL :1(C,D,E,F )-75% Completed
- Electrical LT Work -Wall Chasing: LEVEL :2(A,D,H,G,E,F)-75% Completed
- Electrical LT Work -Wall Chasing: LEVEL :3(A,B,F,E,D,G )-100% Completed
- Electrical LT Work -Wall Chasing: LEVEL :4(A,B,F,E,D,G )-100% Completed
- Electrical LT Work -Wall Chasing: LEVEL :5(B,C,D,F,E,G )-80% Completed
C block
- Earth work excavation at Tower C portion- 95% completed
- Footing work – Building area -34nos completed(Total 67 nos)
- Footing work – Retaining wall area-7 nos completed (Total 18 nos)
- RCC Work :RCC Work :Retaining wall rcc 39 Meters(Out of 47 meters )
As per the current work status from our site we are targeted to complete the following works by end of August 2019
D Block
- Floor Slab RCC Work : Floor Slab RCC Work : 12th &13 th level- 100 to be completed.
- Block work upto Level -11-100% to be completed .
- Ceiling plastering work: LEVEL -12,13 -100% to be Completed
- Wall Plastering: Up to Level -10-100% to be comppleted
C Block
- Footing work – Building area -45nos to be completed(Total 67 nos)
- Retaining area RCC Work :Retaining wall rcc 45 Meters to be completed (Out of 47 meters )
Work status as on 05.08.2019, we have completed the following
D block
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- Floor Slab RCC Work : 1-11th level completed,12th- level( A ,B ,G,H),-Casted ,C&D -Rebar fixing ,(E&F)Centering and shuttering on Progressing
- Block work -Level -1-100% completed
- Block work -Level -2 -75 %(A,D,E,F,G,H) completed
- Level -3-,4,5,6,7 ,8 th -100%completed
- Ceiling plastering work: LEVEL :1,-10 th – (A,B,C,D,E,F,G,H)1 100% completed.
- Ceiling plastering work: LEVEL -11 -40% Completed
- Wall Plastering: Level -1-10%(1D,1E,1F) completed
- Wall Plastering: Level -2 -75 %(A,D,E,F,G,H) completed
- Wall Plastering: Level -3-90%(A,B,C,E,F,G,H)completed
- Wall Plastering: Level -4-50%(A.E,F)completed
- Electrical LT Work -Wall Chasing: LEVEL :1(C,D,E,F )-75% Completed
- Electrical LT Work -Wall Chasing: LEVEL :2(A,D,H,G,E,F)-75% Completed
- Electrical LT Work -Wall Chasing: LEVEL :3(A,B,F,E,D,G )-75% Completed
C block
- Earth work excavation at Tower C portion- 95% completed
- Footing work – Building area -30nos completed(Total 67 nos)
- Footing work – Retaining wall area-7 nos completed (Total 18 nos)
- RCC Work :RCC Work :Retaining wall rcc 35 Meters(Out of 47 meters )
As per the current work status from our site we are targeted to complete the following works by end of July 2019 D Block
- Floor Slab RCC Work : 11th level- 100 to be completed,12 th level -50% to be completed.
- Block work -Level -5&6-100% to be completed.
- Ceiling plastering work: LEVEL -7,8,9 -100% to be Completed
- Wall Plastering: Up to Level -6 -100% to be comppleted
C Block
- Footing work – Building area -33nos to be completed(Total 67 nos)
- RCC Work :Retaining wall rcc 45 Meters to be completed (Out of 47 meters)
Work status as on 06.07.2019, we have completed the following
D block
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- Floor Slab RCC Work : 1-10 th level completed,11 th- level A &B -Casted.
- Block work -Level -1-100% completed
- Block work -Level -2 -75 %(A,D,E,F,G,H) completed
- Block work -Level -3-100%completed
- Block work -Level -4 -50% (A,B,C,D) completed
- Block work -Level -5- On Progressing
- Ceiling plastering work: LEVEL :1,2,3,4,5,6- (A,B,C,D,E,F,G,H)1 100% completed.
- Ceiling plastering work: LEVEL -7 -65% Completed
- Wall Plastering: Level -1-10%(1D,1E,1F) completed
- Wall Plastering: Level -2 -75 %(A,D,E,F,G,H) completed
- Wall Plastering: Level -3-50%(A,E,F,G,H)completed
- Electrical LT Work -Wall Chasing: LEVEL :1(C,D,E,F )-75% Completed
- Electrical LT Work -Wall Chasing: LEVEL :2(A,D,H,G,E,F)-75% Completed
- Electrical LT Work -Wall Chasing: LEVEL :3(A,B,F,E,D,G )-75% Completed
C block
- Earth work excavation at Tower C portion- 95% completed
- Footing work – Building area -23nos completed(Total 67 nos)
- Footing work – Retaining wall area-7 nos completed (Total 18 nos)
- RCC Work :Retaining wall rcc 35 Meters(Out of 47 meters )
As per the current work status from our site we are targeted to complete the following works by end of June 2019 D Block
- column RCC work -10 th level – (A,B,C,D,E,F,G,H)100%completed
- 10th level,11th level floor slab Rcc work -(100% to be completed)
- Ceiling plastering work – upto 8th level -100% to be completed
- Block work -upto 6 th level -100% to becompleted
- Wall Plastering – up to -level-5-100% to be Completed
C Block
- Footing work – 34nos to be completed(Total 67 nos)
- Retaining wall work -100% to be completed
Work status as on 06.06.2019, we have completed the following
D block
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- 1st level, 2nd leve3rd level,4th level ,5th level,6 th level ,7 th level ,8 th level ,9 th level .column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 1-9 th level floor slab -100% completed,10 th level floor slab A,B,G,H (100%Completed),C,D,E,F(Shuttering completed),
- Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed,5level -100% completed,6 th level -60% completed
- Block work – level -1,3 (A,B,C,D,E,F,G,H)100%completed -level -2- (A,D,E,F,G,H)100%completed ,level -4 (A,B,C,D)100%,,E(90%),F(50%), 5 th level -A,B,C,D(Started )-Level -6(A-30%)
- Wall Plastering -level-2(A ,E,G,H)-100% Completed,level 1(1D -100% Completed),3A-(75% Completed)
C Block
- Earth work excavation at Tower C portion- 95% completed
- Soil Investigation test -completed
- Footing work – 23nos completed(Total 67 nos)
- Retaining wall area PCC work on progress













As per the current work status from our site we are targeted to complete the following works by end of May 2019
D Block
- 8 th level column RCC Work :100% to be completed,9 th level column RCC Work :100% to be completed,
- 9th level,10 th level floor slab Rcc work -(100% to be completed)
- Ceiling plastering work – 5,6 th level -100% to be completed
- Block work -upto 6 th level -100% to becompleted
- Wall Plastering – up to -level-3-100% to be Completed
Work status as on 06.05.2019, we have completed the following
D block
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- 1st level, 2nd leve3rd level,4th level ,5th level,6 th level ,7 th level ,column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 8 th level column RCC Work :75%(A,B,C,D,G,H) completed
- 1-8 th level floor slab -100% completed,9th level floor slab Rcc work – (A,B)100% completed ,(G,H ) Reinforcement completed,(C.D) Shuttering completed.
- Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed,5level -40% completed
- Block work – level -1,2,3 (A,B,C,D,E,F,G,H)100%completed -level -4 (A,D)-100% completed,B-75 % Completed
- Wall Plastering -level-2(A ,H)-100% Completed,G -wall plastering -25% completed,level 1(1B -90% Completed)
C Block
- Earth work excavation at Tower C portion- 95% completed
- Soil Investigation test -completed
- Footing work – 14nos completed
As per the current work status from our site we are targeted to complete the following works by end of April 2019 D Block
- 7th level column RCC – (C,D,E,F )100% to be Completed,
- 8th level floor slab,9 th level RCC work – (A,B,C,D,E,F,G,H)100%completed
- Block work -upto 6 th level -100% to becompleted
- Wall Plastering – up to -level-3-100% Completed
C Block
- Footing work – 100% to be completed
Work status as on 05.04.2019, we have completed the following
D Block
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- 1st level column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 2nd level floor slab Rcc work – (A,B,C,D,E,F,G,H)100% completed
- 2nd level column RCC work – (A,B,C,D,E,F,G,H)100% completed
- 3rd level floor Slab rcc work – (A,B,C,D,E,F,G,H)100% completed
- 3rd level column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 4th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 4th level column RCC – (A,B,C,D,E,F,G,H)100%completed
- 5th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 5th level column RCC – (A,B,C,D,E,F,G,H)100%completed
- 6th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 7th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 7th level column RCC – (A,B,G,H )100% Completed
- 8th level floor slab RCC work – (A,B,G,H)100%completed
- Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed,5,6 th level (A,B,C,D,E,F,G,H)95% completed
- Block work – level -1 (A,B,C,D,E,F,G,H)100%completed ,level -1 (A,D,E,F,G,H)-100% completed,level -2 (A,E,F,G,H)-100% completed,
- Wall Plastering -level-2(A )-100% Completed
C Block
- Earth work excavation at Tower C portion- 95% completed
- Soil Investigation test -completed
- Footing work – 11nos completed
As per the current work status from our site we are targeted to complete the following works by end of March 2019 D Block
- 7th level column RCC – (A,B,C,D,E,F,G,H)100% to be completed
- 7th level floor slab RCC work – 100% to be completed
- Ceiling plastering work – 5 th Level 100%to be completed
- Block work -upto 5 th level -100% to be completed
C Block
- Footing work – 15 nos to be completed
Work status as on 06-03-2019, we have completed the following
D Block
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- 1st level column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 2nd level floor slab Rcc work – (A,B,C,D,E,F,G,H)100% completed
- 2nd level column RCC work – (A,B,C,D,E,F,G,H)100% completed
- 3rd level floor Slab rcc work – (A,B,C,D,E,F,G,H)100% completed
- 3rd level column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 4th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 4th level column RCC – (A,B,C,D,E,F,G,H)100%completed
- 5th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 5th level column RCC – (A,B,C,D,E,F,G,H)100%completed
- 6th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 6th level column RCC – (A,B,C,D,E,F,G,H)100%completed
- 7th level floor slab RCC work – centering and shuttering on progress
- Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed
- Block work -upto 5 th level -50% completed
C Block
- Earth work excavation at Tower C portion- 95% completed
- Soil Investigation test -completed
- Rock breaking work at Tower C portion- on progressing
- Footing work – 6 nos completed
As per the current work status from our site we are targeted to complete the following works by end of February 2019
D BLOCK
- 4th level column RCC – (C,D,E,F)100 %to be completed
- 5th level floor slab RCC work – (C,D,E,F)100% to be completed
- 6th level column RCC – (A,B,G &H)100% to be completed7th level floor slab RCC work –
- (A,B,G &H)100% to be completed
- Ceiling plastering work – 5 th Level(A,B,G,H flats) 100%to be completed
- Block work -2nd and third level A,G,H-100% to be completed
C & D BLOCK
- Upper Basement floor Slab RCC work – 100% to be completed
Work status as on 05-02-2019, we have completed the following
D BLOCK
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 100% completed
- Stilt level (Podium slab) – 100% completed
- 1st level column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 2nd level floor slab Rcc work – (A,B,C,D,E,F,G,H)100% completed
- 2nd level column RCC work – (A,B,C,D,E,F,G,H)100% completed
- 3rd level floor Slab rcc work – (A,B,C,D,E,F,G,H)100% completed
- 3rd level column RCC work – (A,B,C,D,E,F,G,H)100%completed
- 4th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
- 4th level column RCC – (A,B,G &H)100%completed
- 5th level floor slab RCC work – (A,B.G &H)100%completed
- 5th level column RCC – (A,B.G &H)100%completed
- 6th level floor slab RCC work – (A,B.G &H)100%completed
- Ceiling plastering work – 1,2,3,4- 100% completed (A,B,G, H flats),1,2(C,D,E,F)completed.
- Block work – 1st level (A,G,H)Completed.
C BLOCK
- Earth work excavation at Tower C portion- 95% completed
- Soil Investigation test -completed
- Rock breaking work at Tower C portion- on progressing
As per the current work status from our site we are targeted to complete the following works by end of January 2019 D BLOCK
- 3rd level column RCC work – 100% to be completed
- 4th level floor Slab RCC work – 100% to be completed
- 4th level column RCC -100 to be completed
- 5th level floor slab RCC work – 100% to be completed
- Ceiling plastering work – 1,2,3,4 Level 100%to be completed (A,B,G,H flats)
- Block work -level(1,2,3) A,G,H-100% to be completed
C & D BLOCK
- Upper Basement floor Slab RCC work – 100% to be completed
Work status as on 08-01-2019, we have completed the following
D BLOCK
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 99.50% completed
- Stilt level (Podium slab) – 100% completed
- 1st level column RCC work – 100%completed
- 2nd level floor slab Rcc work – 100% completed
- 2nd level column RCC work – 100% completed
- 3rd level floor Slab rcc work – 100% completed
- 3rd level column RCC work – (A,B.G &H)100%completed
- 4th level floor slab RCC work – (A,B.G &H)100%completed
- 4th level column RCC – (A,B.G &H)100%completed
- 5th level floor slab RCC work – (A,B.G &H)100%completed
- Ceiling plastering work – 1,2, 100% completed (A,B,G, H flats),3rd level- G,H in progress
- Block work – 1st level (A,B )Completed.
C BLOCK
- Earth work excavation at Tower C portion- 95% completed
- Soil Investigation test -completed
As per the current work status from our site we are targeted to complete the following works by end of December 2019 D BLOCK
- Footing work -100% to be completed
- Stilt level (Podium slab) – 100% to be completed
- 1st level column RCC work – 100% to be completed
- 2nd level floor slab Rcc work – 80% to be completed
- 2nd level column RCC work – 80% to be completed
- 3rd level floor Slab rcc work – 60% to be completed
- 3rd level column RCC work – 60% to be completed
- 4th level floor Slab RCC work – 60% to be completed
- 4th level column RCC – 60% to be completed(A,B&H flats)
- 5th level floor slab RCC work – 60% to be completed(A,B,G&H flats)
- Ceiling plastering work – 1,2,3,4,5 Level 100%to be completed (A,B,H flats)
- Block work – 1st level -A,G,H,B-100% to be completed
Work status as on 06-12-2018, we have completed the following
D BLOCK
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 99.50% completed
- Stilt level (Podium slab) – 90% completed
- 1st level column RCC work – 60% completed (A,B,G&H)
- 2nd level floor slab Rcc work – 60% completed (A,B.G &H)
- 2nd level column RCC work – 60% completed (A,B.G &H)
- 3rd level floor Slab rcc work – 60% completed (A,B.G &H)
- 3rd level column RCC work – 60% completed (A,B.G &H)
- 4th level floor slab RCC work – 60% completed (A,B.G &H)
- 4th level column RCC – 60% completed (A,B.G &H)
- 5th level floor slab RCC work – 50% completed(A,B, G&H flats)
- Ceiling plastering work – 1,2, 80% completed (A,B,G, H flats),3rd ,4th ,5 th level on progressing
- Block work – 1st level -A,G,H,B On progressing
C BLOCK
- Earth work excavation at Tower C portion- 95% completed
- Soil Investigation test -on progress
C & D BLOCK
- Upper Basement floor Slab RCC work – 100% to be completed
As per the current work status from our site we are targeted to complete the following works by end of November 2018 D BLOCK- Footing work -100% to be completed
- 1st level column RCC work – 100% to be completed
- 2nd level floor slab Rcc work – 100% to be completed
- 2nd level column RCC work – 90% completed
- 3rd level floor Slab rcc work – 80% to be completed
- 4th level floor Slab RCC work – 85% to be completed
- 4th level column RCC – 80% to be completed
- 5th level floor slab RCC work – 100% to be completed
- Ceiling plastering work – 1st level and 2nd level – 100% to be completed
- Block work – 1st level – 50% to be completed
C BLOCK
- Earth work excavation at Tower C portion- 100% to be completed
- Rock breaking work at Tower C portion- 100% to be completed
C & D BLOCK
- Upper Basement floor Slab RCC work – 100% to be completed
Work status as on 16-11-2018, we have completed.
D BLOCK
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 100% completed
- Footing work – 98% completed
- Stilt level (Podium slab) – 85% completed
- 1st level column RCC work – 85% completed
- 2nd level floor slab Rcc work – 60% completed
- 2nd level column RCC work – 80% completed
- 3rd level floor Slab rcc work – 60% to be completed
- 3rd level column RCC work – 60% completed
- 4th level floor Slab work – shuttering & steel work- 70% completed
C BLOCK
- Earth work excavation at Tower C portion- 95% completed
- Rock breaking work at Tower C portion – 95% completed
Work Schedule for the Month of July 2018 .- Rock breaking work at Tower D portion- 100% to be completed
- Footing work – 100% to be completed
- RCC for structure (Podium slab) – 95% to be completed
- 1st floor Slab rcc work – 60% to be completed
- Earth work excavation at Tower C portion- 100% to be completed
- Rock breaking work at Tower C portion- 100% to be completed
Work status as on 05-06-2018, we have completed the following.
- Earth work excavation at Tower D portion- 100% completed
- Rock breaking work at Tower D portion- 95% completed
- Footing work – 90% completed
- 1st floor column steel work – started
- Earth work excavation at Tower C portion- 65% completed
- Rock breaking work at Tower C portion – 65% completed
As per the current work status from our site we are targeted to complete the following works by end of May 2018.- Earth work excavation at Tower D portion- 100% to be completed
- Rock breaking work at Tower D portion- 100% to be completed
- Footing work – 80% to be completed
- Earth work excavation at Tower C portion- 100% completed
- Rock breaking work at Tower C portion- 100% completed
Work status as on 05-05-2018, we have completed the following.
- Earth work excavation at Tower D portion- 95% completed
- Rock breaking work at Tower D portion- 95% completed
- Footing work – 65% completed
- RCC for structure – 20% completed
- Earth work excavation at Tower C portion- 50% completed
- Rock breaking work at Tower C portion- 35% completed
As per the current work status from our site we are targeted to complete the following works by end of April 2018- Earth work excavation at Tower D portion- 100% to be completed
- Rock breaking work at Tower D portion- 100% to be completed
- Footing work – 60% to be completed
- Earth work excavation at Tower C portion- 100% completed
- Rock breaking work at Tower C portion- 100% completed
Work status as on 1 9 -0 4-2018, we have completed.
- Earth work excavation at Tower D portion- 95% completed
- Rock breaking work at Tower D portion- 95% completed
- Footing work – 40% completed
- Earth work excavation at Tower C portion- 35% completed
- Rock breaking work at Tower C portion- 30% completed
As per the current work status from our site we are targeted to complete the following works by end of March 2018- Earth work excavation at Tower D portion- 100% to be completed
- Rock breaking work at Tower D portion- 100% to be completed
- Footing work – 60% to be completed
- Earth work excavation at Tower C portion- 100% completed
- Rock breaking work at Tower C portion- 100% completed
Work status as on 1 3 -0 3 -2018, we have completed.
- Earth work excavation at Tower D portion- 90% completed
- Rock breaking work at Tower D portion- 90% completed
- Footing work – 30% completed
- Earth work excavation at Tower C portion- 30% completed
- Rock breaking work at Tower C portion- 20% completed