ArtechPalm Meadows

Kollam , Ongoing
Polayathodu | Kollam

RERA Number: K-RERA/PRJ/083/2020

Project Description

A Sanctuary of bliss.. on every level!

Artech Palm Meadows is our 64th project, an integrated experience for living in harmony with the natural world. Where glimpses of landscaping are worked into the design of tower block to create pockets of recreational breathing spaces. Where spacious and well-appointed residences beckon you to live life to the fullest.

The 2 & 3 BHK homes are designed with careful thought. No wonder your personal living space is in harmony with personal style. Designed to let life flow, living large comes naturally. Take your pick from the multiple units plans on offer. Whichever home you choose – well-appointed interiors and the Artech stamp of quality assurance come standard!

QUICK
ENQUIRE

Take your first few steps towards finding the ultimate happiness of the Perfect Home.
  • Terrace Swimming pool with deck and seating
  • Full equipped Air – Conditioned Unisex Gym
  • Children’s Play Area
  • Rooftop party area
  • Plush Entrance lobby
  • Indoor Games Room
  • Multi purpose hall
  • Video door phone
  • Driver’s Dormitory
  • Furnished Guest Suite

Work status as on 13-09-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – completed, BF wall plastering – completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 75% Completed, 1st floor -completed
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – completed, Internal door shutter – 2nd to 13th floor 70% completed, Main door polish – 2nd to 8th floor one coat sealer completed, Waterproofing up to 22th floor completed, Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 95% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 16th floor completed, putty works & inside painting works – 95% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 17th floor completed, balcony drain line – 3rd – 15th floor completed, Toilet ceiling – 30 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – completed, duct line up to 20th floor 85% completed, toilets suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed, Lightining arrester horizontal line completed
  • External Finishes – Windows and sliding door – up to 19th floor 85% completed, External Plastering – completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external second coat putty work completed, elevation 2 – primer, 1 coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.

  • Civil Works – Drive way protection coat plastering, front elevation boundary wall plastering, STP Pump room floor plastering to be completed, Screeding BF, GF, 14th floor to be completed
  • Internal Finishes – Water proofing – Ground floor driveway to be completed
  • Electrical, Plumbing & Firefighting works – Fire fighting works – 100% to be completed
  • External Finishes – External plastering – compound wall to be completed

Work status as on 12-08-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – completed, BF wall plastering – 90% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 75% Completed, 1st floor – 80% completed
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 20th floor 95% completed, internal door shutter – 2nd to 13th floor 70% completed, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – completed), Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 85% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 13th floor completed, putty works & inside painting works – 95% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 13th floor completed, balcony drain line – 3rd – 11th floor completed, Toilet ceiling – 20 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 57 apartments completed, duct line up to 20th floor 80% completed, toilets suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed, Lightining arrester horizontal line completed
  • External Finishes – Windows and sliding door – 2nd to 13th floor 72% completed, External Plastering – elevations completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external second coat putty work completed, elevation 2 – primer, 1 coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.

  • Civil Works BF ceiling – 100% to be completed, BF wall plastering – 100% to be completed, BF – 10% more to be Completed, 1st floor – 10% more to be completed
  • Internal Finishes Main door shutter fixing – 2nd to 20th floor 100% to be completed, Main door polishing – sealer finishing – 20 apartments to be completed, Water proofing – Basement floor to be completed, Putty and painting works – primer and 1st coat emulsion – stair , common area 2nd floor to 21st floor to be completed
  • External Finishes – External plastering – compound wall, retaining wall to be completed

Work status as on 12-07-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 90% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 70% Completed, 1st floor – 60% completed
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 10th floor, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – completed), Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 80% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 13th floor completed, putty works & inside painting works – 90% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 11th floor, balcony drain line – 3rd – 7th floor completed, Toilet ceiling – 15 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (96%) – up to 19th floor, duct line up to 13th floor completed, suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed
  • External Finishes – Windows and sliding door – 2nd to 13th floor 72% completed, External Plastering – elevations completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external first coat putty work completed, elevation 2 – primer, 1coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
  • Mockup – Completed

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.

  • Civil Works – BF ceiling – 100% to be completed, BF wall plastering – 100% to be completed, BF – 10% more to be Completed, 1st floor – 10% more to be completed
  • Internal Finishes – primer – passage 1st coat primer to be completed
  • External Finishes – Windows and sliding door – up to 13th floor 90% to be completed, floor, amenity to be completed, External plastering – compound wall, retaining wall to be completed

Work status as on 06-06-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 70% completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 75% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed)
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 10th floor, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, GF Lift lobby completed, lift cladding – 2nd to 6th floor completed, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 5th floor, Toilet ceiling – 8 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (96%) – up to 19th floor, duct line up to 10th floor completed, suspended line up to 17th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed
  • External Finishes – Windows and sliding door – 2nd to 10th floor 70% completed, External Plastering – elevations completed, External painting – Elevation 1 Damp proof – 90% completed, C Flat external 2 coat putty completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed, 2nd floor to 13th floor 1 coat putty completed, C flat outer area 1 coat emulsion completed
  • Mockup – Completed

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.

  • Internal Finishes – Main door shutter – 9 more to be fixed, Flooring – BF – 50% to be completed, putty works and painting – 1st coat emulsion 20 flats to be completed
  • External Finishes – Windows and sliding door – 10th to 13th floor, amenity to be completed, External plastering – compound wall, retaining wall to be completed

 

Work status as on 05-05-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 70% completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 60% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 85% (till 19th flat inside completed except 14th floor completed)
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 5th floor, Waterproofing up to 19th floor completed, (over head tank – completed, lift well -2, rainwater harvesting tank outside completed, aminety floor water proofing completed, UG Tank – completed, STP – Completed, BF – 80% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, GF Lift lobby completed, lift cladding – 2nd floor completed, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed).
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (95%) – up to 19th floor, Fire fighting works – (GF, 1st to 19th floor completed) 95% completed
  • External Finishes – Windows and sliding door – 2nd to 10th floor 70% completed , External Plastering – Elevation 2 (100%) & 3 (100%) Completed, Elevation 1 – completed, Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.

  • Internal Finishes – Flooring – 19th floor , lift lobby common area to be completed, putty works and painting – 90% to be completed, Handrails – 98% to be completed
  • External Finishes – External – main entrance arch, compound wall, retaining wall, drive way ceiling to be completed

Work status as on 08-04-2022, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 50% completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 50% completed, BF wall plastering – 15% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 80% (till 19th flat inside completed except 14th floor completed)
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, Waterproofing up to 19th floor completed, (over head tank – completed, lift well -2, rainwater harvesting tank outside completed, aminety floor water proofing completed, UG Tank – completed, STP – 75% Completed, BF – 75% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 95% completed (main stair – completed , fire stair -completed, balcony handrail – till 19th floor completed).
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (95%) – up to 19th floor, Fire fighting works – (GF, 1st to 19th floor completed) 95% completed
  • External Finishes – Windows and sliding door – 2nd to 10th floor 60% completed , External Plastering – Elevation 2 (100%) & 3 (100%) Completed, Elevation 1 – 92% completed (B Flat portion), Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.

  • Internal Finishes – Waterproofing – Balcony (B flat & F flat living) to be completed, flooring – 19th floor , lift lobby common area to be completed, putty works and painting – 90% to be completed, Handrails – 98% to be completed
  • External Finishes – External Palstering – Elevation 1 100% to be completed

Click here to see the previous work progress updates.

  • Terrace Swimming pool with deck and seating
  • Full equipped Air – Conditioned Unisex Gym
  • Children’s Play Area
  • Rooftop party area
  • Plush Entrance lobby
  • Indoor Games Room
  • Multi purpose hall
  • Video door phone
  • Driver’s Dormitory
  • Furnished Guest Suite

Work status as on 13-09-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – completed, BF wall plastering – completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 75% Completed, 1st floor -completed
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – completed, Internal door shutter – 2nd to 13th floor 70% completed, Main door polish – 2nd to 8th floor one coat sealer completed, Waterproofing up to 22th floor completed, Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 95% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 16th floor completed, putty works & inside painting works – 95% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 17th floor completed, balcony drain line – 3rd – 15th floor completed, Toilet ceiling – 30 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – completed, duct line up to 20th floor 85% completed, toilets suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed, Lightining arrester horizontal line completed
  • External Finishes – Windows and sliding door – up to 19th floor 85% completed, External Plastering – completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external second coat putty work completed, elevation 2 – primer, 1 coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.

  • Civil Works – Drive way protection coat plastering, front elevation boundary wall plastering, STP Pump room floor plastering to be completed, Screeding BF, GF, 14th floor to be completed
  • Internal Finishes – Water proofing – Ground floor driveway to be completed
  • Electrical, Plumbing & Firefighting works – Fire fighting works – 100% to be completed
  • External Finishes – External plastering – compound wall to be completed

Work status as on 12-08-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – completed, BF wall plastering – 90% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 75% Completed, 1st floor – 80% completed
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 20th floor 95% completed, internal door shutter – 2nd to 13th floor 70% completed, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – completed), Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 85% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 13th floor completed, putty works & inside painting works – 95% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 13th floor completed, balcony drain line – 3rd – 11th floor completed, Toilet ceiling – 20 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 57 apartments completed, duct line up to 20th floor 80% completed, toilets suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed, Lightining arrester horizontal line completed
  • External Finishes – Windows and sliding door – 2nd to 13th floor 72% completed, External Plastering – elevations completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external second coat putty work completed, elevation 2 – primer, 1 coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.

  • Civil Works BF ceiling – 100% to be completed, BF wall plastering – 100% to be completed, BF – 10% more to be Completed, 1st floor – 10% more to be completed
  • Internal Finishes Main door shutter fixing – 2nd to 20th floor 100% to be completed, Main door polishing – sealer finishing – 20 apartments to be completed, Water proofing – Basement floor to be completed, Putty and painting works – primer and 1st coat emulsion – stair , common area 2nd floor to 21st floor to be completed
  • External Finishes – External plastering – compound wall, retaining wall to be completed

Work status as on 12-07-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 90% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 70% Completed, 1st floor – 60% completed
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 10th floor, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – completed), Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 80% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 13th floor completed, putty works & inside painting works – 90% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 11th floor, balcony drain line – 3rd – 7th floor completed, Toilet ceiling – 15 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (96%) – up to 19th floor, duct line up to 13th floor completed, suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed
  • External Finishes – Windows and sliding door – 2nd to 13th floor 72% completed, External Plastering – elevations completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external first coat putty work completed, elevation 2 – primer, 1coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
  • Mockup – Completed

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.

  • Civil Works – BF ceiling – 100% to be completed, BF wall plastering – 100% to be completed, BF – 10% more to be Completed, 1st floor – 10% more to be completed
  • Internal Finishes – primer – passage 1st coat primer to be completed
  • External Finishes – Windows and sliding door – up to 13th floor 90% to be completed, floor, amenity to be completed, External plastering – compound wall, retaining wall to be completed

Work status as on 06-06-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 70% completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 75% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed)
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 10th floor, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, GF Lift lobby completed, lift cladding – 2nd to 6th floor completed, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 5th floor, Toilet ceiling – 8 flats Completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (96%) – up to 19th floor, duct line up to 10th floor completed, suspended line up to 17th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed
  • External Finishes – Windows and sliding door – 2nd to 10th floor 70% completed, External Plastering – elevations completed, External painting – Elevation 1 Damp proof – 90% completed, C Flat external 2 coat putty completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed, 2nd floor to 13th floor 1 coat putty completed, C flat outer area 1 coat emulsion completed
  • Mockup – Completed

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.

  • Internal Finishes – Main door shutter – 9 more to be fixed, Flooring – BF – 50% to be completed, putty works and painting – 1st coat emulsion 20 flats to be completed
  • External Finishes – Windows and sliding door – 10th to 13th floor, amenity to be completed, External plastering – compound wall, retaining wall to be completed

 

Work status as on 05-05-2023, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 70% completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 60% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 85% (till 19th flat inside completed except 14th floor completed)
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 5th floor, Waterproofing up to 19th floor completed, (over head tank – completed, lift well -2, rainwater harvesting tank outside completed, aminety floor water proofing completed, UG Tank – completed, STP – Completed, BF – 80% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, GF Lift lobby completed, lift cladding – 2nd floor completed, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed).
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (95%) – up to 19th floor, Fire fighting works – (GF, 1st to 19th floor completed) 95% completed
  • External Finishes – Windows and sliding door – 2nd to 10th floor 70% completed , External Plastering – Elevation 2 (100%) & 3 (100%) Completed, Elevation 1 – completed, Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.

  • Internal Finishes – Flooring – 19th floor , lift lobby common area to be completed, putty works and painting – 90% to be completed, Handrails – 98% to be completed
  • External Finishes – External – main entrance arch, compound wall, retaining wall, drive way ceiling to be completed

Work status as on 08-04-2022, we have completed the following.

  • Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 50% completed, ground to basement ramp completed.
  • Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 50% completed, BF wall plastering – 15% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 80% (till 19th flat inside completed except 14th floor completed)
  • Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, Waterproofing up to 19th floor completed, (over head tank – completed, lift well -2, rainwater harvesting tank outside completed, aminety floor water proofing completed, UG Tank – completed, STP – 75% Completed, BF – 75% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 95% completed (main stair – completed , fire stair -completed, balcony handrail – till 19th floor completed).
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – (95%) – up to 19th floor, Fire fighting works – (GF, 1st to 19th floor completed) 95% completed
  • External Finishes – Windows and sliding door – 2nd to 10th floor 60% completed , External Plastering – Elevation 2 (100%) & 3 (100%) Completed, Elevation 1 – 92% completed (B Flat portion), Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.

  • Internal Finishes – Waterproofing – Balcony (B flat & F flat living) to be completed, flooring – 19th floor , lift lobby common area to be completed, putty works and painting – 90% to be completed, Handrails – 98% to be completed
  • External Finishes – External Palstering – Elevation 1 100% to be completed

Click here to see the previous work progress updates.

RELATED PROJECTS

DISCLAIMER

The information provided on this website is meant for general guidance. Though we have taken utmost care on the accuracy of the contents, the customer should make an autonomous assessment of the contents. However, the prospective buyers should rely upon the terms and conditions of the sale and construction agreement between the Builder and the Client.

The visuals of the projects symbolize artistic impression only. The information contained herein including the fittings, finishes, features, floor size and color etc. in the visuals are subject to change. However, the plans & specifications indicated in the Builder and Client agreements are final and we have not authorized anyone to make any oral commitments or promises on our behalf in regard to the plans and specifications of the apartments/projects.

For any clarification please feel free to call +91 9847 600 600 or walk into our offices. Our representatives will always be at your service.