Artech Artech Palm Meadows

Project Description

A Sanctuary of bliss.. on every level!

Artech Palm Meadows is our 64th project, an integrated experience for living in harmony with the natural world. Where glimpses of landscaping are worked into the design of tower block to create pockets of recreational breathing spaces. Where spacious and well-appointed residences beckon you to live life to the fullest.

The 2 & 3 BHK homes are designed with careful thought. No wonder your personal living space is in harmony with personal style. Designed to let life flow, living large comes naturally. Take your pick from the multiple units plans on offer. Whichever home you choose – well-appointed interiors and the Artech stamp of quality assurance come standard!

Categories: ,

Quick Enquire

Take your first few steps towards finding the ultimate happiness of the Perfect Home.

Floor Plans

Location

Amenities

  • Terrace Swimming pool with deck and seating
  • Full equipped Air – Conditioned Unisex Gym
  • Children’s Play Area
  • Rooftop party area
  • Plush Entrance lobby
  • Indoor Games Room
  • Multi purpose hall
  • Video door phone
  • Driver’s Dormitory
  • Furnished Guest Suite

Progress

As per the current work status from our site we are targeted to complete the following works by end of June 2020

  • Pile cap -Building area completed,retaining wall area 25nos completed (out of 26 nos)
  • Raft slab-S-E-corner side 90% completed.
  • SLAB RCC:
  1. BF Slab RCC Work-95% completed
  2. Slab RCC work GF ,FF-95% completed, 2nd -11th floor -100% completed,12th -14th floor(A,B)-100% completed,15th floor:-70% completed.
  • Column RCC Work:
  1. 1 to -12th Floor -100% completed
  2. 13th floor- 100% completed
  3. 14th floor-60% completed.
  4. 15th floor-60% completed.
  • Ceiling plastering:
  1. Ground floor :90% completed
  2. 1st -11th floor -100% completed
  3. 12th floor (A,B)- 100%completed
  • Block Masonry:
  1. 2nd -6th floor-100% completed
  2. 7th floor(A&B) -100% completed. 7th(C,D)-90% completed.
  3. 8th floor -100% completed
  4. 9th floor (A,B)-100% completed
  5. 10th floor -100% completed
  6. 11th floor (A,B)-100% completed
  • Wall Chasing :
  1. Second floor :100% completed
  2. Third Floor :100% Completed
  3. Forth floor:(A,B,C,D) -100% completed
  4. Fifth floor :100% completed
  5. Sixth floor :100% completed
  6. seventh floor :100% completed
  • Retaining wall work: 296m completed (out of 500m)
  • BALCONY HANDRAIL WORK :
  1. 2(A,B,C,D):100% Completed
  2. 3(A,B,)-60% completed
  • STAIRCASE HANDRAIL WORK:
  1. Fire stair -( GF,1st ,2nd) -100% completed
  2. Main stair(GF,1st,2nd)-100% completed
  3. 2nd floor main and fire -100% completed.
  • Internal Wall Plastering:
  1. 2nd – 5th floor(A,B,C,D): -100% completed
  2. 6th floor(A,B,C,D)-100% completed
  • FIRST COAT PUTTY (INSIDE):
  1. 2nd floor(A,B,C,D)-100% Completed
  2. 3rd floor(A,B,C,D)-100% Completed
  3. 4th floor-(A,B):-100 % Completed, 4(C,D):-50% completed.
  • WATER PROOFING:
  1. 2nd floor(A)toilet -100% completed
  2. 2nd floor (A)balcony -100% completed
  • MOCK UP FLAT (2A):
  1. 2A : Putty work 100% completed
  2. Balcony Handrail work: completed
  3. fire piping-100% completed
  4. Electrical wiring-100% completed
  5. Plumbing( toilet) -100% completed
  6. Water proofing :- 100% completed.


As per the current work status from our site we are targeted to complete the following works by end of March 2020

  • Raft slab-100% to be completed
  • SLAB RCC work: ,11 th -100% to be completed ,12 th -80% to be completed.,15th floor:-60% to be completed.
  • Column RCC Work:
  1. 13th floor-100% to be completed
  2. 14th floor-100% to be completed
  3. 15th floor-60% to be completed
  • Ceiling plastering:
  1. 10th floor -100% to be completed
  2. 11th floor -100% to be completed
  3. 12th floor- 100% to be completed
  • Block Masonry:
  1. 7th floor(C&D) -100% to be completed
  2. 8th floor(C & D)-100% to be completed
  3. 9th floor (C&D)-100% to be completed
  4. 10th,11th,12thfloor (A&B )-100% to be completed
  • Wall chasing:
  1. sixth floor :100% to be completed
  2. seventh floor :100% to be completed
  • Retaining wall work: 326m to be completed (out of 500 m)
  • BALCONY HANDRAIL WORK: 3(A,B,)-100% to be completed
  • STAIRCASE HANDRAIL WORK: 3rd floor main and fire -100% to be completed.
  • Internal Wall Plastering: 6th floor(A,B,C,D)-100% to be completed
  • FIRST COAT PUTTY (INSIDE ):
  1. 5th floor(A,B)-100 % to be Completed
  2. 5th floor (C,D)-80% to be completed
  • RAMP WORK: 60% to be completed
  • WATERPROOFING: 2nd floor(B)-100% to be completed
  • FABRICATION WORK: Window grill (2A)-100% to be completed, (2B)-100% to be completed.

Work status as on 11.03.2020, we have completed the following

  • Pile cap -Building area completed,retaining wall area 21nos completed (out of 26 nos)
  • Raft slab-S-E-corner side 80% completed
  • SLAB RCC : BF Slab RCC Work-95% completed
  • Slab RCC work GF ,FF-95% completed, 2nd-9th floor-100% ,10 th floor -100% completed,11 th -60% completed,12 th -60% completed. 13th &14th floor-60% completed.
  • Column RCC Work:
  1. 1 to -10th Floor -100% completed
  2. 11th-12th floor -100% completed
  3. 13th-14 floor-60% completed
  • Ceiling plastering:
  1. Ground floor :90% completed
  2. 1st -9th floor -100% completed
  3. 10th -11th floor-60% completed
  • Block Masonry:
  1. 2nd -6th floor-100% completed
  2. 7th floor(A&B) -100% completed
  3. 8th floor (A,B)-100% completed
  4. 9th floor (A,B)-100% completed
  • Wall chasing:
  1. Second floor :100% completed
  2. Third Floor :100% Completed
  3. Forth floor:(A,B,C,D) -100% completed
  4. Fifth floor :100% completed
  • Retaining wall work: 296 m completed (out of 500 m)
  • BALCONY HANDRAIL WORK: 2(A,B,C,D):100% Completed
  • STAIRCASE HANDRAIL WORK:
    1. Fire stair -( GF,1st ,2nd) -100% completed.
    2. Main stair(GF,1st,2nd)-100% completed.
    3. 2nd floor main and fire -100% completed.
  • Internal Wall Plastering:
    1. 2nd floor (A,B,C,D)-100% Completed
    2. 3rd floor(A,B,C,D)-100% Completed
    3. 4th floor(A,B,C,D)-100% completed
    4. 5th floor(A,B,C,D)-100% completed
  • FIRST COAT PUTTY (INSIDE ):
    1. 2nd floor(A,B,C,D)-100% Completed
    2. 3rd floor(A,B,C,D)-100% Completed
    3. 3rd floor(C,D)-100 % Completed
  • WATERPROOFING:
    1. 2nd floor(A)toilet -100% completed
    2. 2nd floor (A)balcony -100% completed
  • MOCKUP FLAT (2A):
  1. 2A : Putty work 100% completed
  2. Balcony Handrail work: completed
  3. Fire piping-100% completed
  4. Electrical wiring-100% completed
  5. Plumbing( toilet) -100% completed

As per the current work status from our site we are targeted to complete the following works by end of February 2020

  • Raft slab-70% to be completed
  • SLAB RCC work: ,11 th -100% to be completed ,12 th -80% to be completed.,14th floor:-60% to be completed.
  • Column RCC Work:
  1. 12th floor-100% to be completed
  2. 13th floor-100% to be completed
  3. 14th floor-60% to be completed
  • Ceiling plastering:
  1. 9th floor-100% to be completed
  2. 10th floor -100% to be completed
  3. 11th floor -100% to be completed
  4. 12th floor-60% to be completed
  • Block Masonry:
  1. 7th floor(C&D) -100% to be completed
  2. 8th floor(B,C & D)-100% to be completed
  3. 9th floor (A&B)-100% to be completed
  4. 10th floor (A&B )-100% to be completed
  • Wall chasing:
  1. Forth floor:(C&D) -100% to be completed
  2. sixth floor :100% to be completed
  3. seventh floor :100% to be completed
  • Retaining wall work: 296m to be completed (out of 500 m)
  • BALCONY HANDRAIL WORK: 2(B,C,D)-100% to be completed
  • STAIRCASE HANDRAIL WORK: 2nd floor main and fire -100% to be completed.
  • Internal Wall Plastering: 5th floor(A,B,C,D)-100% to be completed
  • FIRST COAT PUTTY (INSIDE ):
  1. 4th floor(A,B)-100 % to be Completed
  2. 4th floor (C,D)-80% to be completed
  • RAMP WORK: 60% to be completed
  • WATERPROOFING: 2nd floor(B)-100% to be completed
  • FABRICATION WORK: Window grill (2A)-100% to be completed, (2B)-100% to be completed.

Work status as on 08.02.2020, we have completed the following

  • Pile cap -Building area completed,retaining wall area 21nos completed (out of 26 nos)
  • Raft slab-S-E-corner side 50% completed
  • SLAB RCC : BF Slab RCC Work-95% completed
  • Slab RCC work GF ,FF-95% completed, 2nd-9th floor-100%, 10th floor -100% completed, 11th -60% completed,12th -60% completed. 13th floor-60% completed.
  • Column RCC Work:
  1. 1 to -10th Floor -100% completed
  2. 11th floor -100% completed
  3. 12th floor-60% completed
  4. 13th floor-60% completed
  • Ceiling plastering:
  1. Ground floor :90% completed
  2. 1st -7th floor -100% completed
  3. 8th floor-100% completed
  4. 9th floor-60% completed
  5. 10th floor-60% completed
  6. 11th floor-60% completed
  • Block Masonry:
  1. 2nd -5th floor-100% completed
  2. 6th floor -100% completed
  3. 7th floor(A&B) -100% completed
  4. 8th floor (A,B)-100% completed
  5. 9th floor (A,B)-40% completed
  • Wall chasing:
  1. Second floor :100% completed
  2. Third Floor :100% Completed
  3. Forth floor:(A&B) -100% completed
  4. Fifth floor :100% completed
  • Retaining wall work: 196 m completed (out of 500 m)
  • BALCONY HANDRAIL WORK: 2A:100% Completed
  • STAIRCASE HANDRAIL WORK:
    1. Fire stair -( GF,1st ,2nd) -100% completed
    2. Main stair(GF,1st,2nd)-100% completed
  • Internal Wall Plastering:
    1. 2nd floor (A,B,C,D)-100% Completed
    2. 3rd floor(A,B,C,D)-100% Completed
    3. 4th floor(A,B,C,D)-100% to be completed
  • FIRST COAT PUTTY (INSIDE ):
    1. 2nd floor(A,B,C,D)-100% Completed
    2. 3rd floor(A,B,C,D)-100% Completed
    3. 3rd floor(C,D)-100% Completed
  • WATERPROOFING:
    1. 2nd floor(A)toilet -100% completed
    2. 2nd floor (A)balcony -100% completed
  • MOCKUP FLAT (2A):
  1. 2A : Putty work 100% completed
  2. Balcony Handrail work: completed
  3. fire piping-100% completed
  4. electrical wiring-100% completed
  5. Plumbing( toilet) -100% completed


As per the current work status from our site we are targeted to complete the following works by end of January 2020

  • Pile cap -Building area completed,retaining wall area 20nos completed (out of 26 nos)
  • Raft slab-100% to be completed
  • SLAB RCC : 10 th -100%,11 th -80% ,12 th -80% to be completed
  • Column RCC Work:
  1. 10th-11th floor -100% to be completed
  2. 11th-12th floor-100% to be completed
  3. 12th-13th floor-100% to be completed
  • Ceiling plastering:
  1. 8th floor-100% to be completed
  2. 9th floor-100% to be completed
  3. 10th floor -100% to be completed
  4. 11th floor-60% to be completed
  5. 12th floor-60% to be completed
  • Block Masonry:
  1. 6th floor -100% to be completed
  2. 7th floor(C&D) -100% to be completed
  3. 8th floor(B,C & D)-100% to be completed
  4. 9th floor (A&B)-100% to be completed
  5. 10th floor (A&B )-100% to be completed
  • Wall chasing:
  1. Forth floor:(C&D) -100% to be completed
  2. Fifth floor :100% to be completed
  • Retaining wall work: 170m to be completed (out of 500 m)
  • BALCONY HANDRAIL WORK: 2(B,C,D)-100% to be completed
  • STAIRCASE HANDRAIL WORK: Main stair(GF,1st,2nd)-100% to be completed
  • Internal Wall Plastering: 4th floor(A,B,C,D)-100% to be completed
  • FIRST COAT PUTTY (INSIDE ): 3rd floor(C,D)-50 % To beCompleted
  • RAMP WORK: 60% to be completed
  • FABRICATION WORK: Window grill (2A)-100% to be completed

Work status as on 10.01.2020, we have completed the following

  • Pile chipping -100% completed
  • Pile cap -Building area completed,retaining wall area 16nos completed (out of 26 nos)
  • Raft slab-S-E corner side 40% completed
  • SLAB RCC:
  1. BF Slab RCC Work-95% completed
  2. Slab RCC work GF ,FF-95% completed, 2nd-9th floor-100% ,10 th floor -60% completed,11 th -60% completed,12 th -60% completed.
  • Column RCC Work:
  1. 1 to -10th Floor -100% completed
  2. 10th-11th floor -60% completed
  3. 11th-12th floor-60% completed
  4. 12th-13th floor-60% completed
  • Ceiling plastering:
  1. Ground floor :90% completed
  2. 1st -7th floor -100% completed
  3. 8th floor-60% completed
  4. 9th floor-60% completed
  5. 10th floor-60% completed
  • Block Masonry:
  1. 2nd -5th floor-100% completed
  2. 6th floor -40% completed
  3. 7th floor(A&B) -100% completed
  4. 8th floor (A)-100% completed , (B)-60% completed
  • Wall chasing:
  1. Second floor :100% completed
  2. Third Floor :100% Completed
  3. Fourth floor:(A&B) -100% completed
  • Retaining wall work: 156 m completed (out of 500 m)
  • BALCONY HANDRAIL WORK:
  1. 2A:100% Completed
  2. STAIRCASE HANDRAIL WORK
  3. Fire stair -( GF,1st ,2nd) -100% completed
  4. Internal Wall Plastering
  5. 2nd floor (A,B,C,D)-100% Completed
  6. 3rd floor(A,B,C,D)-100% Completed
  • FIRST COAT PUTTY (INSIDE ):
  1. 2nd floor(A,B,C,D)-100% Completed
  2. 3rd floor(A,B)-100% Completed
  • WATERPROOFING: 2nd floor(A)toilet -100% completed
  • MOCKUP FLAT (2A):
  1. 2A : Putty work 100% completed
  2. Balcony Handrail work: completed
  3. fire piping-100% completed
  4. electrical wiring-100% completed
  5. Plumbing( toilet) -100% completed


As per the current work status from our site we are targeted to complete the following works by end of September 2019

  • SLAB RCC work -5 th &6 th -100 % ,9 th -60% ,10 th -40% to be completed
  • Ceiling plastering: Sixth floor -75%,7 th -60% ,8 th -40% to be completed
  • Block Masonry: Second floor :100% to be completed
  • Block Masonry: Third floor :100% completed
  • Block Masonry: Fourth floor :80% completed
  • Electrical wall chasing: Second floor :100% to be completed
  • Electrical wall chasing: Third floor :60% to be completed
  • Retaining wall work : 130m to be completed (out of 500m)

Work status as on 05.09.2019, we have completed the following

  • Pile chipping -100% completed
  • Pile cap -Building area completed,retaining wall area 10nos completed (out of 26 nos)
  • BF Slab RCC Work-95% completed
  • Slab RCC work GF ,FF-95% completed,SF-100% , 3 rd -100%,4 th -100% ,5 th -100% ,6 th -60% completed ,7 th -60% ,8 th -60%,9 th -50%,10 th floor -40% completed
  • Column RCC Work: 1 to -2 nd Floor -100% completed
  • Column RCC Work: 2 to -3rd Floor -100% completed
  • Column RCC Work: 3rd to -4 th Floor -100% completed
  • Column RCC Work: 4 th to -5 th Floor -100% completed
  • Column RCC Work: 5th to -6 th Floor -100% completed
  • Column RCC Work: 6 th to -7 th Floor -100% completed
  • Column RCC Work: 7 th to -8 th Floor -60% completed
  • Column RCC Work: 8th to -9 th Floor -60% completed
  • Column RCC Work: 9th to -10th Floor -40% completed
  • Ceiling plastering: Ground floor :90% completed
  • Ceiling plastering: First floor :90% completed
  • Ceiling plastering: Second floor :100% completed
  • Ceiling plastering: Third floor :75% completed
  • Ceiling plastering: Fourth Floor :75% completed
  • Ceiling plastering: Fifth floor :75% completed
  • Ceiling plastering: Sixth floor :60% completed
  • Block Masonry: Second floor :95% completed
  • Block Masonry: Third floor :70% completed
  • Block Masonry: Fourth floor :70% completed
  • Block Masonry: Fifth floor :40% completed
  • Electrical wall chasing: Second floor :40% completed
  • Retaining wall work :80 m completed (out of 500 m)

As per the current work status from our site we are targeted to complete the following works by end of August 2019

  • SLAB RCC work -5 th &6 th -100 % ,9 th -60% ,10 th -40% to be completed
  • Column RCC Work : 5th to -6th Floor -100% completed
  • Column RCC Work : 6th to -7thFloor -60% to be completed
  • Column RCC Work : 8th to 9thFloor , 9th-10th -60% to be completed
  • Ceiling plastering: Second floor :100% to be completed
  • Ceiling plastering: Third floor :100% tobe completed
  • Ceiling plastering: Fourth floor -100% to be completed ,fifth & Sixth floor -100% to be completed
  • Block Masonry: Second floor :100% to be completed
  • Block Masonry: Third floor :100% completed
  • Block Masonry: Fourth floor :100% completed
  • Electrical wall chasing: First floor :100% to be completed
  • Electrical wall chasing: Second floor :100% to be completed
  • Electrical wall chasing: Third floor :100% to be completed
  • Retaining wall work :70m to be completed (out of 500 m)

Work status as on 05.08.2019, we have completed the following

  • Pile chipping -100% completed
  • Pile cap -Building area completed,retaining wall area 10nos completed (out of 26 nos)
  • BF Slab RCC Work-95% completed
  • Slab RCC work GF ,FF-95% completed,SF-100% , 3 rd -100%,4 th -100% ,5 th -60% ,6 th -60% completed ,7 th -60% ,8 th -60%,9 th -40%
  • Column RCC Work: 1 to -2 nd Floor -100% completed
  • Column RCC Work: 2 to -3rd Floor -100% completed
  • Column RCC Work: 3rd to -4 th Floor -100% completed
  • Column RCC Work: 4 th to -5 th Floor -100% completed
  • Column RCC Work: 5th to -6 th Floor -60% completed
  • Column RCC Work: 6 th to -7 th Floor -60% completed
  • Column RCC Work: 7 th to -8 th Floor -60% completed
  • Column RCC Work: 8th to -9 th Floor -40% completed
  • Ceiling plastering: Ground floor :90% completed
  • Ceiling plastering: First floor :90% completed
  • Ceiling plastering: Second floor :75% completed
  • Ceiling plastering: Third floor :75% completed
  • Ceiling plastering: Fourth Floor :75% completed
  • Block Masonry: Second floor :95% completed
  • Block Masonry: Third floor :60% completed
  • Block Masonry: Fourth floor :40% completed
  • Retaining wall work :50 m completed (out of 500 m)


As per the current work status from our site we are targeted to complete the following works by end of July 2019

  • SLAB RCC work -7 th & 8 th Floor -60% completed.
  • Column RCC Work : 2 to -3rd Floor -100% to be completed
  • Column RCC Work : 3rd to -4 th Floor -100% to be completed
  • Column RCC Work : 6 th to -7 thFloor -60% to be completed
  • Ceiling plastering: Ground floor :75% to be ompleted
  • Ceiling plastering: First floor :75% to be completed
  • Ceiling plastering: Second floor :100% to be completed
  • Ceiling plastering: Fourth floor :75% to be completed
  • Block Masonry: Second floor :60% to be completed
  • Block Masonry: Third floor :40% to be completed
  • Electrical wall chasing: First floor :60% to be completed
  • Electrical wall chasing: Second floor :60% to be completed
  • Retaining wall work :60m to be completed (out of 500 m)

Work status as on 06.07.2019, we have completed the following

  • Pile chipping -100% completed
  • Pile cap -Building area completed,retaining wall area 10nos completed (out of 26 nos)
  • BF Slab RCC Work-95% completed
  • Slab RCC work GF ,FF-95% completed,SF-100% , 3 rd -85%,4 th -75% ,5 th -60% ,6 th -60% completed
  • Column RCC Work: 1 to -2 nd Floor -100% completed
  • Column RCC Work: 2 to -3rd Floor -95% completed
  • Column RCC Work: 3rd to -4 th Floor -75% completed
  • Column RCC Work: 4 th to -5 th Floor -60% completed
  • Ceiling plastering: Ground floor :60% completed
  • Ceiling plastering: First floor :70% completed
  • Ceiling plastering: Second floor :75% completed
  • Ceiling plastering: Third floor :75% completed
  • Block Masonry: Second floor :40% completed
  • Retaining wall work :30 m completed (out of 500 m)


As per the current work status from our site we are targeted to complete the following works by end of June 2019

  • pile cap (Retaining wall area)-15nos to be completed out of 26 nos
  • BF Slab RCC Work-95% to be completed
  • GF Slab RCC Work-95% to be completed
  • second floor Slab -90% to be completed
  • Column work -FF-SF Column work -100% to be completed,2nd -3rd Column work- 100% completed,4 th -5 th floor Column work -60% completed.
  • Ceiling plastering- 1st floor -75% to be completed ,2 nd floor -75% to be completed
  • Brick masonry work -2 nd floor -40% to be completed
  • Electrical chasing work -2 nd floor -40% to be completed

Work status as on 06.06.2019, we have completed the following

  • Pile chipping -100% completed
  • Pile cap -Building area completed,retaining wall area 9nos completed (out of 26 nos)
  • BF Slab RCC Work-90% completed
  • GF ,FF slab RCC work -90% completed
  • 2 nd ,3 rd,4 th floor Slab RCC Work-75% completed
  • GF-FF Column work -100% completed,FF-SF Column work -85% completed,2ND-3RD Column work -85% completed,3 rd -4 TH Column work -75% completed.
  • Ceiling plastering- 1st floor -60% completed ,2 nd floor -40% completed






As per the current work status from our site we are targeted to complete the following works by end of May 2019

  • pile cap (Retaining wall area)-11 nos to be completed out of 26 nos
  • BF Slab RCC Work-90% to be completed
  • First floor Slab -90% to be completed
  • Fourth floor slab & fifth floor slab RCC Work-60% to be completed.
  • BF -GF Column work -90% to be completed
  • GF-FF Column work -90% to be completed,4 th to 5 th floor column -60% to be completed.
  • Ceiling plastering 1& 2 nd floor -60% to be completed
  • Brick masonry work -2 nd floor -40% to be completed
  • Electrical chasing work -2 nd floor -40% to be completed

Work status as on 06.05.2019, we have completed the following

  • Pile chipping -100% completed
  • Pile cap -Building area completed,retaining wall area 6 nos completed (out of 26 nos)
  • BF Slab RCC Work-80% completed
  • GF slab RCC work – 80% completed
  • FF,SF,TF Slab RCC Work-75% completed
  • Fourth floor slab RCC Work-Shuttering completed
  • BF -GF Column work -80% completed
  • GF-FF Column work -70% completed,FF-SF Column work -60% completed,2ND-3RD Column work -60% completed,3 RD-4 TH Column work -60% completed.


As per the current work status from our site we are targeted to complete the following works by end of April 2019

  • BF Slab RCC Work-100% to be completed
  • GF slab RCC work – 100% to be completed
  • FF Slab RCC Work-100% to be completed,SF,TF-65% to be completed,Forth floor slab -60% to be completed.
  • Column RCC work (Building)basement – 100% to be completed
  • Column RCC work (Building) Ground- 100% to be completed (out of 53)
  • Column RCC work (Building) First floor-65% Completed,SF (65% to be completed),TF Column -60% tobe completed)

Work status as on 05.04.2019, we have completed the following

  • Piling work – 100% completed
  • Pile chipping – 100% completed (out of 148)
  • Pile chipping – Retaining wall area 6completed(out of 26)
  • Pile cap (retaining wall area) – 6completed(out of 26)
  • Pile cap work – 13nos completed (out of 14);
  • BF Slab RCC Work-80% completed
  • GF slab RCC work – 75% completed
  • FF Slab RCC Work-75% completed
  • Column RCC work (Building)basement – 80% completed
  • Column RCC work (Building) Ground-90% completed (out of 53)
  • Column RCC work (Building) First floor-40% Completed


As per the current work status from our site we are targeted to complete the following works by end of March 2019

  • Pile chipping – 148 to be completed (out of 148)
  • BF Slab RCC Work-100% to be completed
  • GF slab RCC work – 100% to be completed
  • FF Slab RCC Work-70% to be completed
  • Column RCC work (Building)basement – 100% to be completed
  • Column RCC work (Building) Ground- 100% to be completed (out of 53)

Work status as on 06-03-2019, we have completed the following

  • Piling work – 100% completed
  • Pile chipping – 142 nos completed (out of 148)
  • Pile chipping – Retaining wall area 3 completed(out of 26)
  • Pile cap work – 13nos completed (out of 14);
  • BF Slab RCC Work-70% completed
  • GF slab RCC work – 70% completed
  • FF Slab RCC Work-40% completed
  • Column RCC work (Building)basement – 80% completed
  • Column RCC work (Building) Ground- 65% completed (out of 53)
  • Column RCC work (Building) First floor-40% Completed

As per the current work status from our site we are targeted to complete the following works by end of February 2019

  • BF Slab RCC Work-100% to be completed
  • GF slab RCC work – 100% to be completed
  • Column RCC work (Building)basement – 100% to be completed

Work status as on 05-02-2019, we have completed the following

  • Piling work – 100% completed
  • Pile chipping – 112 nos completed (out of 148)
  • Pile chipping – Retaining wall area 3completed(out of 26)
  • Pile cap work – 11nos completed (out of 14);
  • BF Slab RCC Work-50% completed
  • GF slab RCC work – 50% completed
  • FF Slab RCC Work-50% completed
  • Column RCC work (Building)basement – 60% completed
  • Column RCC work (Building) Ground- 60% completed (out of 53)
  • Column RCC work (Building) First floor- 30% Completed


As per the current work status from our site we are targeted to complete the following works by end of January 2019

  • BF Slab RCC Work-60% to be completed
  • GF slab RCC work – 60% to be completed

Work status as on 08-01-2019, we have completed the following

  • Piling work – 100% completed
  • Pile chipping – 112 nos completed (out of 148)
  • Pile chipping – Retaining wall area 3completed(out of 26)
  • Pile cap work – 10nos completed (out of 14);
  • BF Slab RCC Work-45% completed
  • GF slab RCC work – 40% completed
  • FF Slab RCC Work-40% completed
  • Column RCC work (Building)basement – 31nos completed (out of 53)
  • Column RCC work (Building) Ground- 19nos completed (out of 53)


As per the current work status from our site we are targeted to complete the following works by end of December 2019

  • Pile chipping – 122 nos to be completed (out of 148)
  • Pile cap work – 11nos to be completed (out of 14)
  • GF slab RCC work – 60% to be completed
  • FF Slab RCC Work-20%to be completed

Work status as on 06-12-2018, we have completed the following

  • Piling work – 100% completed
  • Pile chipping – 102 nos completed (out of 148)
  • Pile chipping – Retaining wall area 2 completed(out of 26)
  • Pile cap work – 8nos completed (out of 14);
  • GF slab RCC work – 40% completed
  • FF Slab RCC Work-on progress
  • Column RCC work (Building)basement – 19nos completed (out of 53)
  • Column RCC work (Building) Ground- 15nos completed (out of 53)

As per the current work status from our site we are targeted to complete the following works by end of November 2018 

  • Pile chipping – 100 nos to be completed (out of 148)
  • Pile cap work – 6nos to be completed (out of 14)
  • GF slab RCC work – 60% to be completed
  • Column RCC work (Building) – 28 nos to be completed (out of 52)

Work status as on 16-11-2018, we have completed the following. 

  • Piling work – 100% completed
  • Pile chipping – 85 nos completed (out of 148)
  • Pile cap work – 5nos completed (out of 14);
  • GF slab RCC work – 30% completed
  • Column RCC work (Building) – 19nos completed (out of 53)


 Work Schedule for the Month of July 2018

  • Pile chipping – 60nos to be completed (out of 148)
  • Pile cap work – 4nos to be completed (out of 14)
  • Column RCC work (Building) – 8 nos to be completed (out of 52)

Work status as on 05-06-2018, we have completed the following. 

  • Piling work – 100% completed
  • Pile chipping – 40 nos completed (out of 148)
  • Pile cap work – 1no completed (out of 14)
  • Column RCC work (Building) – 5 nos completed (out of 52)


 Work Schedule for the Month of June 2018

  • Piling work – 158 nos completed (out of 174)
  • Pile chipping – 9 nos completed (out of 148)
  • Pile cap work – 1no completed (out of 14)
  • Column RCC work (Building) – 5 nos completed (out of 52)

 As per the current work status from our site we are targeted to complete the following works by end of June 2018

  • Piling work – 100% to be completed
  • Pile chipping – 18 nos to be completed (out of 148)
  • Column RCC work (Building) – 8 nos to be completed (out of 52)


As per the current work status from our site we are targeted to complete the following works by end of March 2018

  • Piling work -134 to be completed (out of 174)

Work status as on 1 3 -03 -2018, we have completed.

  • Piling work – 104 nos completed (out of 174)