Work status as on 13-09-2023, we have completed the following.
- Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – completed, BF wall plastering – completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 75% Completed, 1st floor -completed
- Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – completed, Internal door shutter – 2nd to 13th floor 70% completed, Main door polish – 2nd to 8th floor one coat sealer completed, Waterproofing up to 22th floor completed, Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 95% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 16th floor completed, putty works & inside painting works – 95% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 17th floor completed, balcony drain line – 3rd – 15th floor completed, Toilet ceiling – 30 flats Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – completed, duct line up to 20th floor 85% completed, toilets suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed, Lightining arrester horizontal line completed
- External Finishes – Windows and sliding door – up to 19th floor 85% completed, External Plastering – completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external second coat putty work completed, elevation 2 – primer, 1 coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
- Mockup – Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
- Civil Works – Drive way protection coat plastering, front elevation boundary wall plastering, STP Pump room floor plastering to be completed, Screeding BF, GF, 14th floor to be completed
- Internal Finishes – Water proofing – Ground floor driveway to be completed
- Electrical, Plumbing & Firefighting works – Fire fighting works – 100% to be completed
- External Finishes – External plastering – compound wall to be completed
Work status as on 12-08-2023, we have completed the following.
- Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – completed, BF wall plastering – 90% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 75% Completed, 1st floor – 80% completed
- Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 20th floor 95% completed, internal door shutter – 2nd to 13th floor 70% completed, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – completed), Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 85% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 13th floor completed, putty works & inside painting works – 95% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 13th floor completed, balcony drain line – 3rd – 11th floor completed, Toilet ceiling – 20 flats Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 57 apartments completed, duct line up to 20th floor 80% completed, toilets suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed, Lightining arrester horizontal line completed
- External Finishes – Windows and sliding door – 2nd to 13th floor 72% completed, External Plastering – elevations completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external second coat putty work completed, elevation 2 – primer, 1 coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
- Mockup – Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
- Civil Works BF ceiling – 100% to be completed, BF wall plastering – 100% to be completed, BF – 10% more to be Completed, 1st floor – 10% more to be completed
- Internal Finishes Main door shutter fixing – 2nd to 20th floor 100% to be completed, Main door polishing – sealer finishing – 20 apartments to be completed, Water proofing – Basement floor to be completed, Putty and painting works – primer and 1st coat emulsion – stair , common area 2nd floor to 21st floor to be completed
- External Finishes – External plastering – compound wall, retaining wall to be completed
Work status as on 12-07-2023, we have completed the following.
- Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – completed, ground to basement ramp completed.
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 90% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed), BF – 70% Completed, 1st floor – 60% completed
- Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 10th floor, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – completed), Wall tiles – 80% completed till 19th floor (except client hold flats), Floor Tiling 80% completed till 19th floor completed ( except client hold flats) – BF to 22nd floor Lift lobby completed, lift cladding – 2nd to 13th floor completed, putty works & inside painting works – 90% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 15 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 11th floor, balcony drain line – 3rd – 7th floor completed, Toilet ceiling – 15 flats Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – (96%) – up to 19th floor, duct line up to 13th floor completed, suspended line up to 19th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed
- External Finishes – Windows and sliding door – 2nd to 13th floor 72% completed, External Plastering – elevations completed, External painting – Elevation 1, primer C flat external completed, C flat outside west and north Damp proof – completed, C Flat external 2 coat putty completed, B Flat external first coat putty work completed, elevation 2 – primer, 1coat emulsion completed, elevation 3 – primer completed elevation 4 – dramp proof ,1st coat putty, primer, 1st coat emulsion C Flat outside completed
- Mockup – Completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
- Civil Works – BF ceiling – 100% to be completed, BF wall plastering – 100% to be completed, BF – 10% more to be Completed, 1st floor – 10% more to be completed
- Internal Finishes – primer – passage 1st coat primer to be completed
- External Finishes – Windows and sliding door – up to 13th floor 90% to be completed, floor, amenity to be completed, External plastering – compound wall, retaining wall to be completed
Work status as on 06-06-2023, we have completed the following.
- Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 70% completed, ground to basement ramp completed.
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 75% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 90% (till 19th flat inside completed except 14th floor completed)
- Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 10th floor, Waterproofing up to 19th floor completed, (over head tank, lift well -2, rainwater harvesting tank outside, aminety floor water proofing, UG Tank, STP – Completed, BF – 80% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, GF Lift lobby completed, lift cladding – 2nd to 6th floor completed, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed), False Ceiling – Common area fire pipe covering – Up to 5th floor, Toilet ceiling – 8 flats Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – (96%) – up to 19th floor, duct line up to 10th floor completed, suspended line up to 17th floor completed, Fire fighting works – (GF, 1st to 19th floor completed) 98% completed, Electrical HT completed, cable tray and cabling completed, electrical room panel board fixing completed
- External Finishes – Windows and sliding door – 2nd to 10th floor 70% completed, External Plastering – elevations completed, External painting – Elevation 1 Damp proof – 90% completed, C Flat external 2 coat putty completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed, 2nd floor to 13th floor 1 coat putty completed, C flat outer area 1 coat emulsion completed
- Mockup – Completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
- Internal Finishes – Main door shutter – 9 more to be fixed, Flooring – BF – 50% to be completed, putty works and painting – 1st coat emulsion 20 flats to be completed
- External Finishes – Windows and sliding door – 10th to 13th floor, amenity to be completed, External plastering – compound wall, retaining wall to be completed
Work status as on 05-05-2023, we have completed the following.
- Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 70% completed, ground to basement ramp completed.
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 90% completed, BF wall plastering – 60% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 85% (till 19th flat inside completed except 14th floor completed)
- Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, internal door shutter – 2nd to 5th floor, Waterproofing up to 19th floor completed, (over head tank – completed, lift well -2, rainwater harvesting tank outside completed, aminety floor water proofing completed, UG Tank – completed, STP – Completed, BF – 80% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, GF Lift lobby completed, lift cladding – 2nd floor completed, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 100% completed (main stair – completed , fire stair -completed, balcony handrail – completed).
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – (95%) – up to 19th floor, Fire fighting works – (GF, 1st to 19th floor completed) 95% completed
- External Finishes – Windows and sliding door – 2nd to 10th floor 70% completed , External Plastering – Elevation 2 (100%) & 3 (100%) Completed, Elevation 1 – completed, Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
- Mockup – Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
- Internal Finishes – Flooring – 19th floor , lift lobby common area to be completed, putty works and painting – 90% to be completed, Handrails – 98% to be completed
- External Finishes – External – main entrance arch, compound wall, retaining wall, drive way ceiling to be completed
Work status as on 08-04-2022, we have completed the following.
- Structural Works – All Sub-Structural and Structural work 98% Completed, GF north side drive way – 50% completed, ground to basement ramp completed.
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, BF ceiling – 50% completed, BF wall plastering – 15% completed, Masonry – Block/ brick- inside flat area completed, Screeding – 80% (till 19th flat inside completed except 14th floor completed)
- Internal Finishes – Main door – frame only – 100% completed, Door shutter fixing – 2nd to 11th floor completed, Waterproofing up to 19th floor completed, (over head tank – completed, lift well -2, rainwater harvesting tank outside completed, aminety floor water proofing completed, UG Tank – completed, STP – 75% Completed, BF – 75% Completed, 1st floor drive way – 60% completed), Wall tiles – up to 13th floor completed, 16th floor completed, 18th floor Completed, Floor Tiling till 18th floor – 70% completed except 14th floor, putty works & inside painting works – 85% completed (2nd coat putty completed, 1 coat primer completed, 1st coat emulsion – 11 flats completed), Handrails – 95% completed (main stair – completed , fire stair -completed, balcony handrail – till 19th floor completed).
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – (95%) – up to 19th floor, Fire fighting works – (GF, 1st to 19th floor completed) 95% completed
- External Finishes – Windows and sliding door – 2nd to 10th floor 60% completed , External Plastering – Elevation 2 (100%) & 3 (100%) Completed, Elevation 1 – 92% completed (B Flat portion), Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work completed, 2nd coat putty completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
- Mockup – Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
- Internal Finishes – Waterproofing – Balcony (B flat & F flat living) to be completed, flooring – 19th floor , lift lobby common area to be completed, putty works and painting – 90% to be completed, Handrails – 98% to be completed
- External Finishes – External Palstering – Elevation 1 100% to be completed