Progress
As per the current work status from our site we are targeted to complete the following works by end of February 2021
Tower 1
- Internal wall plastering work -Roof-100% to be completed.
- Outside Plastering:- 100% to be completed.
- Dadoing of toilets:16th floor -100% to be completed
- Dadoing of kitchen walls:14th floor-100% to be completed,
- 16th floor -100% to be completed,
- Water Proofing work -floor, terrace -100% to be completed
- Internal Primer -second coat:-16th floor :-100% to be completed.
- External Painting -(1st coat) :-at south -100% to be completed, at west- 100% to be completed
- External Primer -(first coat) :- at south -100% to be completed, at west- 75% to be completed.
- Outside Putty work -40% to be completed
- Plumbing work -17th floor-100% to be completed.
- Flooring and skirting :-,14th floor- 100% to be completed, 15th floor:- 50% to be completed
- 13th-15th floor- 100% to be completed.
- Aluminium windows & ventilators-GF,18th floor(B)-100% to be completed.
Tower 2
- RCC for slab -11th roof slab -100% to be completed.,12th-30% to be completed.
- Ceiling plastering: 8th -9th floor,BF3 -100% to be completed
- Electrical Wall Chasing: 3rd-4th floor:-100% to be completed.
- Wall Plastering: GF:-100% to be completed, 2nd floor:-100% to be completed.
- Block Work: Basement floor:-100% to be completed, 5th & 6th floor -100% to be completed.
- Yard work: full side retaining wall-40% to be completed, STP RCC -75% to be completed.
- MLCP: BF2 ceiling & column plastering -100% to be completed, BF3 ceiling & column plastering -100% to be completed.
Work status as on 09-02-2021, we have completed the following
Tower 1
- RCC for slab -18th floor-19th floor-100% completed, water tank 100% completed.
- Block work – BF2-90% completed,BF1,1st-18 th floor:-100%completed, Roof:- 100 % completed.
- Ceiling Plastering work -(BF1- 18th floor -) 100% completed.
- Wall chasing work -BF1- 18th floor – 100% completed.
- Door Frame Fixing -BF1-90% Completed,1-18th -100% completed.
- Internal wall plastering work -upto 18th floor -100% completed, Roof-50% completed.
- Outside Plastering:- 95% completed.
- Dadoing of toilets: up to 15th floor -100% completed.
- Dadoing of kitchen walls :GF – 50% completed,1st floor-13th floor-100% completed,
- Wire pulling : GF -30%,1st and 3 rd,5 th ,7 th -90%,2,4,8th -25% completed,6th,9th-15th floor-100% completed,
- Water Proofing work – Upto 18th floor- 100% completed,terrace -25% completed
- Putty work – upto 18th floor :-100% completed.
- Internal Primer -second coat :- upto 15th floor-100% completed.
- External Painting -(1st coat) :-at south -75% completed, at west- 40% completed
- External Primer -(2nd coat) :- at south -75% completed, at west- 20% completed
- Outside Putty work -15% completed
- Plumbing work – upto 16th floor- 100% completed
- Grills /Balcony Handrail work -upto 18th floor -100% completed,
- Flooring and skirting ,, -GF,15th floor-25% Completed 3rd-5th ,7th,8th,11th,12thfloor:-100% completd,1st,6th,9th,10th floor -80% completed,,13th-14th floor:-50% completed.
- Fixing of door shutters -1st Floor -25%completed
- Fire Fighting work :GF-12th floor-75% completed,13th floor-50% completed,14th-15th floor -20%completed.
- First and second coat painting ,CP and sanitary fittings ,DB Dressing ,Switch Fixing ,Final cleaning and pointing -First floor -25% completed.
- Aluminium windows & ventilators-GF,18th floor( B)-40% completed
- mock up flat – -100% completed
Tower 2
- RCC for slab – BF2-9th floor roof slab – 100% completed
- 10th roof slab -100% completed,11th floor-30% completed.
- Ceiling plastering: BF1-7th floor -100% completed, BF3-90% completed
- Electrical Wall Chasing: Ground floor -100% completed, 1st floor-2nd floor- 100 % completed ,3rdfloor-70% completed
- Wall Plastering: GF :-35% completed, 1st floor :-100% completed, 2nd floor-50% completed.
- Block Work: GF -75% completed, Basement floor:-70% completed, 1st floor-4nd floor – 100 % completed, 5th floor-75% completed
- Yard work: STP RCC -20% completed, Front gate -100% completed, Compound wall-100% completed.
- MLCP: BF1 ceiling & column plastering -100% completed, BF2 ceiling & column plastering -80% completed.
As per the current work status from our site we are targeted to complete the following works by end of JANUARY 2021
Tower 1
- Blockwork – roof:-100% to be completed.
- Internal wall plastering work -Roof-50% to be completed.
- Outside Plastering:- 100% to be completed.
- Dadoing of toilets: 15th-16th floor -100% to be completed
- Dadoing of kitchen walls: 13th floor-14th floor-100% completed,
- 15th-17th floor -100% to be completed,
- Water Proofing work -18th floor, terrace -100% to be completed
- Putty work:- 18th floor -100% to be completed.
- Internal Primer -second coat:-15th -16th floor:-100% to be completed.
- External Primer -(first coat):- at south -100% to be completed, at west- 100% to be completed.
- External Painting -(Second coat):- at south -50% to be completed, at west- 50% to be completed.
- Outside Putty work -40% to be completed
- Plumbing work -17th floor-100% to be completed.
- Flooring and skirting :-,14th floor- 100% to be completed, 15th floor:- 50% to be completed
- 13th-15th floor- 100% to be completed.
- Aluminium windows & ventilators-GF,18th floor(B)-100% to be completed.
Tower 2
- RCC for slab -11th roof slab -100% to be completed.,12th-30% to be completed.
- Ceiling plastering: 8th -9th floor,BF3 -100% to be completed
- Electrical Wall Chasing: 3rd-4th floor:-100% to be completed.
- Wall Plastering: GF:-100% to be completed, 1st -2nd floor:-100% to be completed.
- Block Work: Basement floor:-100% to be completed, 5th & 6th floor -100% to be completed.
- Yard work: full side retaining wall-40% to be completed, STP RCC -75% to be completed.
- MLCP: BF2 ceiling & column plastering -100% to be completed, BF3 ceiling & column plastering -100% to be completed.
Work status as on 07-01-2021, we have completed the following
Tower 1
- RCC for slab -18th floor-19th floor-100% completed, water tank 100% completed.
- Blockwork – BF2-90% completed,BF1,1st-18 th floor:-100%completed, Roof:- 80 % completed.
- Ceiling Plastering work -(BF1- 18th floor -) 100% completed.
- Wall chasing work -BF1- 18th floor – 100% completed.
- Door Frame Fixing -BF1-90% Completed,1-18th -100% completed.
- Internal wall plastering work -up to 18th floor -100% completed, Roof-20% completed.
- Outside Plastering:- 90% completed.
- Dadoing of toilets: up to 14th floor -100% completed.
- Dadoing of kitchen walls: GF – 50% completed,1st floor-13th floor-100% completed,
- Wire pulling : GF -30%,1st and 3 rd,5 th ,7 th -90%,2,4,8th -25% completed,6th,9th,11th,13th floor-100% completed,10th,12th floor-100% completed,
- Water Proofing work – Upto 17th floor- 100% completed,18th floor-70% completed.
- Putty work – up to 17th floor:-100% completed.
- Internal Primer -second coat:- up to 14th floor-100% completed.
- External Primer -(first coat) :- at south -25% completed, at west- 25% completed
- External Painting -(Second coat) :-
- Outside Putty work -15% completed
- Plumbing work – upto 16th floor- 100% completed,16th floor-60% completed.
- Grills /Balcony Handrail work -upto 18th floor -100% completed,
- Flooring and skirting ,, -GF, floor-25% Completed ,1st,floor :-80% completed,3rd-5th ,7th,8th,11th,12thfloor:-100% completd,6th,9th,10th floor -80% completed,,13th-14th floor:-50% completed.
- Fixing of door shutters -1st Floor -25%completed
- Fire Fighting work :GF-12th floor-75% completed,13th floor-50% completed.
- First and second coat painting ,CP and sanitary fittings ,DB Dressing ,Switch Fixing ,Final cleaning and pointing -First floor -25% completed.
- Aluminium windows & ventilators-GF,18th floor( B)-40% completed
- mock up flat – -100% completed
Tower 2
- RCC for slab – BF2-9th floor roof slab – 100% completed
- 10th roof slab -100% completed,11th floor-30% completed.
- Ceiling plastering: BF1-7th floor -100% completed, BF3-90% completed
- Electrical Wall Chasing: Ground floor -100% completed, 1st floor-2nd floor- 100 % completed ,3rdfloor-70% completed
- Wall Plastering: GF :-30% completed, 1st floor :-85% completed.
- Block Work: GF -75% completed, Basement floor:-70% completed, 1st floor-2nd floor – 100 % completed, 3rd floor -100% completed, 4th floor- 100% completed,5th floor-60% completed
- Yard work: STP RCC -20% completed, Front gate -100% completed, Compound wall-100% completed.
- MLCP: BF1 ceiling & column plastering -100% completed, BF2 ceiling & column plastering -80% completed.
As per the current work status from our site we are targeted to complete the following works by end of July 2020
Tower 1
- RCC for slab – water tank 100% to be completed.
- Block work – ,18th floor-100% to be completed.
- Wall chasing work – 17th floor – 50% to be completed
- Door Frame Fixing -17th floor:-50% to be completed
- Internal wall plastering work – 17th floor-100% to be completed.
- Dadoing of toilets : 11th floor -50% to be completed
- 9th,10th,11th, 12th,13th floor -50% to be completed
- Water Proofing work -16th floor -100% to be completed
- Putty work :- 10th floor -100% to be completed.
- Plumbing work -15th floor-75% to be completed.
- Balcony Handrail work :-upto 18th floor- 100% to be completed.
- 6th ,9th,10th floor- 100% to be completed
- Fixing of door shutters -1st Floor -50% to be completed,3rd floor :-30% to be completed,5th floor :-30% to be completed.
- 13th floor- 75% to be completed.
Tower 2
- RCC for slab -9th roof slab -100% to be completed.
- Ceiling plastering: 2nd floor -100% to be completed, 3rd floor -100% to be completed, 4th floor -100% to be completed, 5th floor -100% to be completed, 6th floor -100% to be completed
- Block Work: 1st floor 100% to be completed
Work status as on 11.06.2020, we have completed the following
Tower 1
- RCC for slab -18th floor -100%completed,19 th floor-100% completed
- Block work – BF2-90% completed,BF1,(1-16 th floor )-100%completed, 17th, floor-100% completed, 18th floor :-50% completed.
- Ceiling Plastering work -(BF1- 17th floor -) 100% completed,18 th floor -100% completed.
- Wall chasing work -BF1- 16th floor – 100% completed.
- Door Frame Fixing -BF1-90% Completed,1-16 th -100% completed.
- Internal wall plastering work -upto 16th floor – 100% completed, 17th floor :-60% completed.
- Dadoing of toilets :GF -10th floor-100% completed.
- Dadoing of kitchen walls :GF – 50% completed,1st floor-6th floor-100% completed, 7th floor:-50% completed.
- Wire pulling : GF -30%,1st and 3 rd,5 th ,7 th -90%,2,4,6,8,9,10th -25% completed
- Water Proofing work – Upto 15th floor- 100% completed.
- Putty work – upto 9th floor :-100% completed.
- Plumbing work – upto 13th floor- 100% completed,14th floor-100% completed,15th ffloor- 25% completed.
- Grills /Balcony Handrail work -1 st floor -65% completed,2-9th floor -80% completed,10th-12th floor-60%completed,13th-17thfloor-50% completed,18 th -40% completed
- Flooring and skirting ,, -GF-25% Completed ,1st,floor :-80% completed,3 rd floor:-100% completed. ,5 th floor:-100% completd ,7th floor-100% completed.
- Fixing of door shutters -1st Floor -25%completed
- Fire Fighting work :GF-12th floor-75% completed
- First and second coat painting ,CP and sanitary fittings ,DB Dressing ,Switch Fixing ,Final cleaning and pointing -First floor -25% completed.
- Aluminium windows & ventilators-GF,FF-25% completed
- mock up flat – 100% completed
Tower 2
- RCC for slab – BF2-7th floor roof slab – 100% completed
- 8th floor roof slab – 100% completed, 9th floor-50% completed.
- Ceiling plastering: 1st floor -90% completed, 2nd floor -90% completed, 3rd floor -90% completed, 4th floor -50% completed, 5th floor -50% completed
As per the current work status from our site we are targeted to complete the following works by end of September 2019
Tower 1
- RCC for slab -19 th floor-50% to be completed
- Block work – 13 th floor -100% ,14 th -50% to be completed
- Ceiling Plastering work – 14th floor – 100%,15 th-50% to be completed
- Wall chasing work – 12th floor – 100% ,13 thfloor -50% to be completed
- Door Frame Fixing -12 th floor (100% to be completed)
- Internal wall plastering work – 10 th ,11 th ,12 th -100% to be completed.
- Dadoing of toilets :GF -90% Completed,First floor -50% completed, 2-5 th -80% to be completed .dadoing of kitchen walls:Ground floor -30% completed,FF-35 % to be completed.
- Wire pulling : 2-6 th floor -30% to be completed.
- Water Proofing work – GF-11 th floor -100% to be completed
- Putty work – GF-7 th -100% to be completed.
- Plumbing work-GF-10 th floor -100% ,11 th floor -75% to be completed
- Balcony Handrail work -10th floor -50% to be completed
- Aluminium Fabrication work -GF,1F-25% to be completed .Fixing of door shutters -GF-11 th Floor -65% to be completed .Grills& Handrails -1F -65%,2-10 th floor -50% to be completed
Tower 2
- RCC for slab -7th roof slab -100% to be completed.
Work status as on 05.09.2019, we have completed the following
Tower 1
- RCC for slab -18th floor -100%completed,19 th floor-20% completed
- Block work – BF2-90% completed,BF1,(1-11 th floor )-100% Completed,12 th floor-100% completed,13 th -30% completed
- Ceiling Plastering work -(BF1- 12th floor -) 100% completed,13 -90% completed
- Wall chasing work -BF1- -9th floor – 100% completed,10 th floor -100% completed,11 th floor-80% to be completed,12 th-40% completed .
- Door Frame Fixing -BF1-90% Completed,1-11 th -100% completed.
- Internal wall plastering work -BF1 (70% completed); GF, 1st-6 th floor (100% completed),7th floor -90% completed,8 th-90%,9 th-100% completed ,10th -70% completed.
- Dadoing of toilets :GF -50% Completed,First floor to fourth-50% completed, dadoing of kitchen walls:1 st floor -25% completed
- Wire pulling : Ground to fourth floor -10% completed,
- Water Proofing work – BF1-30% Completed,GF to 8th floor – 100% completed;8 th -50% completed,9 th -60% ,10 th -50% completed .
- Putty work – BF1-70% Completed,GF- 4 th floor -100% completed,5 th&6 th -90% completed.
- Plumbing work -(GF-7 th floor) -100% completed,8-9 th floor -50% completed.
- Balcony Handrail work -1 st floor -65% completed,2-9 th floor -50% completed.
- Flooring and skirting ,Aluminum fabrication work ,door shutter fixing -GF-10% Completed ,1 st floor-25% completed
- Fire Fighting work :-1 st floor-15% completed
- First and second coat painting ,CP and sanitary fittings ,DB Dressing ,Switch Fixing ,Final cleaning and pointing -First floor -25% completed.
- mock up flat -ceiling plastering ,block and brick masonry ,door frame fixing ,electrical chasing ,plumbing work ,wall chasing ,wall plastering ,dadoing of toilets ,kitchen walls ,application of putty on wall sand ceiling ,water proofing ,flooring and skirting ,aluminium doors and window fixing ,door shutter fixing ,grills and handrails fixing ,wire pulling -100% completed
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rd floor -100% completed
- Column rising work – 4th floor -100% completed
- Column rising work – 5th floor -100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab -Second floor roof slab -100% completed
- RCC for slab -Third floor roof slab -100% completed
- RCC for slab -fourth roof slab -100% completed
- RCC for slab -fifth roof slab 100% completed
- RCC for slab -6th roof slab -25% to be completed.
As per the current work status from our site we are targeted to complete the following works by end of August 2019
Tower 1
- Ceiling Plastering work – 14th floor – 50% to be completed
- Wall chasing work – 11th floor – 100% completed
- Door Frame Fixing -11 th floor (100% to be completed)
- Internal wall plastering work – 9 th floor -100 %,10 th -75 %to be completed
- Dadoing of toilets :GF -90% Completed,First floor -50% completed, dadoing of kitchen walls:Ground floor -30% completed,FF-35 % to be completed.
- Wire pulling : 2-6 th floor -30% completed.
- Water Proofing work – GF-10 th -100% to be completed
- Putty work – GF-7 th -100% to be completed.
- Plumbing work-GF-8 th floor 100% to be completed.
- Balcony Handrail work -10th floor -50% to be completed
Tower 2
- RCC for slab -fifth roof slab -75% to be completed,6th roof slab -25% to be completed.
Work status as on 05.08.2019, we have completed the following
Tower 1
- RCC for slab -18th floor -90%completed
- Block work – BF2-90% completed,BF1,(1-11 th floor )-100% Completed,12 th floor-80% completed.
- Ceiling Plastering work -(BF1- 12th floor -) 100% completed,13 -45% completed
- Wall chasing work -BF1- -9th floor – 100% completed,10 th floor -80% completed,11 th floor-50% to be completed.
- Door Frame Fixing -BF1-90% Completed,1-10 th -100% completed.
- Internal wall plastering work -BF1 (70% completed); GF, 1st-6 th floor (100% completed),7th floor -90% completed,8 th-90%,9 th-90% completed .
- Dadoing of toilets :GF -35% Completed,First floor to fourth-25% completed, dadoing of kitchen walls:1 st floor -25% completed
- Wire pulling : Ground to fourth floor -10% completed,
- Water Proofing work – BF1-30% Completed,GF to 7 th floor – 100% completed;8 th -50% completed.
- Putty work – BF1-70% Completed,GF- 4 th floor -100% completed,5 th&6 th -90% completed.
- Plumbing work -(GF-5 th floor) -100% completed,6 th -50% completed.
- Balcony Handrail work -1 st floor -65% completed,2-9 th floor -50% completed.
- Flooring and skirting ,Aluminum fabrication work ,door shutter fixing -GF-10% Completed ,1 st floor-25% completed
- Fire Fighting work :-1 st floor-15% completed
- First and second coat painting ,CP and sanitary fittings ,DB Dressing ,Switch Fixing ,Final cleaning and pointing -First floor -25% completed.
- mock up flat -ceiling plastering ,block and brick masonry ,door frame fixing ,electrical chasing ,plumbing work ,wall chasing ,wall plastering ,dadoing of toilets ,kitchen walls ,application of putty on wall sand ceiling ,water proofing ,flooring and skirting ,aluminium doors and window fixing ,door shutter fixing ,grills and handrails fixing ,wire pulling -100% completed
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rd floor -100% completed
- Column rising work – 4th floor -100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab -Second floor roof slab -100% completed
- RCC for slab -Third floor roof slab -100% completed
- RCC for slab -fourth roof slab -100% completed
- RCC for slab -fifth roof slab -25% completed
As per the current work status from our site we are targeted to complete the following works by end of July 2019
Tower 1
- Block work -12 th floor -50% to be completed
- Ceiling Plastering work – 14th floor – 50% to be completed
- Wall chasing work – 11th floor – 100% completed
- Door Frame Fixing -11 th floor (100% to be completed)
- Internal wall plastering work – 9 th floor 100 %to be completed
- Dadoing of toilets :GF -90% Completed,First floor -50% completed, dadoing of kitchen walls:Ground floor -30% completed,FF-25 % to be completed.
- Wire pulling : 2-6 th floor -30% completed.
- Water Proofing work – 7 th & 8 th floor -100% to be completed,9 th floor -50% to be completed.
- Putty work – GF-7 th -100% to be completed.
- Plumbing work-6 th floor -100% to be completed,7 th floor -75% to be completed
- Balcony Handrail work -10th floor -50% to be completed
Tower 2
- RCC for slab -fourth roof slab -100% to be completed,5 th roof slab -50% to be completed.
Work status as on 06.07.2019, we have completed the following
Tower 1
- Column work – 18 floor – 100% completed
- RCC for slab -18th floor -50%completed
- Block work – BF2-90% completed,BF1,(1-10 th floor )-100% Completed,11th floor -70% completed
- Ceiling Plastering work -(BF1- 12th floor -) 100% completed,13 -45% completed
- Wall chasing work -BF1- -9th floor – 100% completed,10 th floor -80% completed,11 th floor-10% to be completed.
- Door Frame Fixing -BF1-90% Completed,1-10 th -100% completed.
- Internal wall plastering work -BF1 (70% completed); GF, 1st-6 th floor (100% completed),7th floor -90% completed,8 th-90%,9 th-50% completed .
- Dadoing of toilets :GF -35% Completed,First floor -25% completed, dadoing of kitchen walls:1 st floor -25% completed
- Wire pulling : Ground to Third floor -10% completed,
- Water Proofing work – BF1-30% Completed,GF – 100% completed; 1st-3rd floor – 100% completed,4-5th floor -100% completed,6 th -50% completed.
- Putty work – BF1-70% Completed,GF- 4 th floor -100% completed,5 th&6 th -90% completed.
- Plumbing work -(GF-3rd floor) -100% completed,4 th -5 th floor -50% completed.
- Balcony Handrail work -1 st floor -65% completed,2-9 th floor -50% completed.
- Flooring and skirting ,Aluminum fabrication work ,door shutter fixing -GF-10% Completed ,1 st floor-25% completed
- Fire Fighting work :-1 st floor-15% completed
- First and second coat painting ,CP and sanitary fittings ,DB Dressing ,Switch Fixing ,Final cleaning and pointing -First floor -25% completed.
- mock up flat -ceiling plastering ,block and brick masonry ,door frame fixing ,electrical chasing ,plumbing work ,wall chasing ,wall plastering ,dadoing of toilets ,kitchen walls ,application of putty on wall sand ceiling ,water proofing ,flooring and skirting ,aluminium doors and window fixing ,door shutter fixing ,grills and handrails fixing (100% completed),wire pulling (80% completed)
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rd floor -100% completed
- Column rising work – 4th floor -100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab -Second floor roof slab -100% completed
- RCC for slab -Third floor roof slab -100% completed
- RCC for slab -fourth roof slab -75% completed
As per the current work status from our site we are targeted to complete the following works by end of June 2019
Tower 1
- Block work -12 th floor -50% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Wall chasing work – 10th floor – 100% completed
- Door Frame Fixing -11 th floor (13% to be completed)
- Internal wall plastering work – 7 th ,8 th floor 100 %to be completed
- Water Proofing work – 6 th floor -100% to be completed
- Putty work – 5 th&6 th -100% to be completed.
- Plumbing work :4 th floor -100% to be completed,5 th floor -40% to be completed
- Balcony Handrail work -10th floor -50% to be completed
Tower 2
- Column rising work – 4th floor -100% completed
- RCC for slab -fourth roof slab -100% completed
Work status as on 06.06.2019, we have completed the following
Tower 1
- Column work – 16 floor – 100% completed
- RCC for slab -17 th floor -100%completed
- Block work – BF2-90% completed,BF1(1-9)-100% Completed,10 th floor -90% completed,11 th floor -70% completed.
- Ceiling Plastering work -(BF1- 12th floor -) 100% completed,13 -45% completed
- Wall chasing work -BF1- -9th floor – 100% completed,10 th floor -40% completed.
- Door Frame Fixing -BF1-90% Completed,GF-4 th floor -100% completed,5-10 th floor (13% completed)
- Internal wall plastering work -BF1 (70% completed); GF, 1st-6 th floor (100% completed),7th floor -90% completed,8 th-30%,9 th-50% completed.
- Dadoing of toilets :GF -15% Completed,First floor -25% completed, dadaoing of kitchen walls:1 st floor -25% completed
- Wire pulling : 1st-floor -10% completed
- Water Proofing work – BF1-30% Completed,GF – 100% completed; 1st-3rd floor – 100% completed,4-5th floor -100% completed,6 th -50% completed.
- Putty work – BF1-70% Completed,GF- 4 th floor -100% completed,5 th&6 th -90% completed.
- Plumbing work -(GF-2nd floor) -100% completed,3rd floor -90% completed,4 th floor -50% completed.
- Balcony Handrail work -1 st floor -65% completed,2-9 th floor -50% completed.
- Flooring and skirting ,Aluminum fabrication work ,door shutter fixing –1 st floor-25% completed
- Fire Fighting work :-1 st floor-15% completed
- mock up flat -ceiling plastering ,block and brick masonry ,door frame fixing ,electrical chasing ,plumbing work ,wall chasing ,wall plastering ,dadoing of toilets ,kitchen walls ,application of putty on wall sand ceiling ,water proofing ,flooring and skirting ,aluminium doors and window fixing ,door shutter fixing ,grills and handrails fixing (100% completed),wire pulling (80% completed)
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rd floor -100% completed
- Column rising work – 4th floor -75% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab -Second floor roof slab -100% completed
- RCC for slab -Third floor roof slab -100% completed
- RCC for slab -fourth roof slab -60% completed
As per the current work status from our site we are targeted to complete the following works by end of May 2019
Tower 1
- Column work – 16th floor – 100% to be completed
- RCC for slab – 17th floor – 100% to be completed
- Block work – 10-th floor -100% to be completed,11 th floor -60% to be completed,12 th floor -50% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Wall chasing work – 10th floor – 100% completed
- Door Frame Fixing -10-11 th floor (13% to be completed)
- Internal wall plastering work – 8 th floor 100 %to be completed
- Water Proofing work – 4-5th floor -100% to be completed,6 th floor -50% to be completed
- Plumbing work 3rd floor -100% completed,4 th floor -50% completed,5 th floor -20% to be completed
- Balcony Handrail work -up to -10th floor -100% to be completed
Tower 2
- Column rising work – 4th floor -100% completed
- RCC for slab -fourth roof slab -100% completed
Work status as on 06.05.2019, we have completed the following
Tower 1
- Column work – 16 floor – 75% completed
- RCC for slab -17 th floor -50%completed
- Block work – BF2-90% completed,BF1(1-9)-100% Completed,10 th floor -75% completed,11 th floor -70% completed.
- Ceiling Plastering work -(BF1- 12th floor -) 100% completed,13 -30% completed
- Wall chasing work -BF1- -9th floor – 100% completed.
- Door Frame Fixing -BF1-90% Completed,GF-4 th floor -100% completed,5-9 th floor (13% completed)
- Internal wall plastering work -BF1 (70% completed); GF, 1st-6 th floor (100% completed),7th floor -50% completed.
- Dadoing of toilets :GF -15% Completed,First floor -25% completed, dadaoing of kitchen walls:1 st floor -25% completed
- Wire pulling : 1st-floor -10% completed
- Water Proofing work – BF1-30% Completed,GF – 100% completed; 1st-3rd floor – 100% completed,4-5th floor -50% completed
- Putty work (2coat) – BF1-70% Completed,GF- 4 th floor -100% completed
- Plumbing work -(GF-2nd floor) -100% completed,3rd floor -50% completed,4 th floor -20% completed.
- Balcony Handrail work -1 st floor -65% completed,2-9 th floor -50% completed.
- MLCP Pile cap work completed.
- Foundation work -60% completed
- mock up flat -ceiling plastering ,block and brick masonry ,door frame fixing ,electrical chasing ,plumbing work ,wall chasing ,wall plastering ,dadoing of toilets ,kitchen walls ,application of putty on wall sand ceiling ,water proofing ,flooring and skirting ,aluminium doors and window fixing ,door shutter fixing ,grills and handrails fixing (100% completed),wire pulling (25% completed)
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rd floor -100% completed
- Column rising work – 4th floor -75% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab -Second floor roof slab -100% completed
- RCC for slab -Third floor roof slab -100% completed
- RCC for slab -fourth roof slab -40% completed
As per the current work status from our site we are targeted to complete the following works by end of April 2019
Tower 1
- Column work – 16th floor – 100% to be completed
- RCC for slab – 17th floor – 100% to be completed
- Block work – 11th floor – 100% to be completed,12 th floor -50% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Wall chasing work – 10th floor – 100% completed
- Internal wall plastering work – 8 th floor 100 %to be completed
- Plumbing Sleeve Fixing -8 th floor -100% to be completed
- Balcony Handrail work -up to -10th floor -100% to be completed
Tower 2
- Column rising work – 4th floor -100% completed
- RCC for slab -fourth roof slab -100% completed
Work status as on 05.04.2019, we have completed the following
Tower 1
- Column work – 16 floor – 75% completed
- RCC for slab -17 th floor -45%completed
- Block work – 11 th floor -70% completed
- Ceiling Plastering work – 12th floor – 100% completed,13 -30% completed
- Wall chasing work – 8th floor – 100% completed,9 th floor completed
- Internal wall plastering work -BF1 (70% completed); GF, 1st-6 th floor (100% completed),7th floor -80% to becompleted.
- Water Proofing work – GF – 100% completed; 1st 6 th floor – 100% completed.
- Putty work (2coat) – GF- 4 th floor -100% completed
- Plumbing Sleeve Fixing -6 th floor -100% completed
- Balcony Handrail work -up to -8 th floor -100% completed
- MLCP Pile cap work completed.
- Foundation work -60% completed
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rd floor -100% completed
- Column rising work – 4th floor -75% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab -Second floor roof slab -100% completed
- RCC for slab -Third floor roof slab -100% completed
- RCC for slab -fourth roof slab -10% completed
As per the current work status from our site we are targeted to complete the following works by end of March 2019
Tower 1
- Column work – 16th floor – 100% to be completed
- RCC for slab – 17th floor – 50% to be completed
- Block work – 11th floor – 100% to be completed,12 th floor -50% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Wall chasing work – 10th floor – 100% completed
- Internal wall plastering work – 6 th floor 100 %to be completed
- Water Proofing work -6 th floor (100% to be completed)
- Putty work (2coat) – 6th floor – 100% to be completed
Tower 2
- Column rising work – 4th floor -100%to be completed
- RCC for slab -Third floor roof slab -100% tobe completed
Work status as on 06-03-2019, we have completed the following
Tower 1
- Column work – 15th floor – 100% completed
- RCC for slab -16 th floor -50%completed
- Block work – 11 th floor -70% completed
- Ceiling Plastering work – 12th floor – 100% completed,13 -10% completed
- Wall chasing work – 8th floor – 100% completed,10 on progress
- Internal wall plastering work -BF1 (70% completed); GF, 1st,2nd floor (100% completed);3rd floor -(100%completed ),4 th floor -100%completed,5 th floor -100 %completed,6 th floor -25%completed.
- Water Proofing work – GF – 100% completed; 1st floor – 100% completed.2,3,4,5(100% to be completed)
- Putty work (2coat) – GF, 1st floor (100% completed),2nd floor -100% completed,3 rd floor -100% completed
- MLCP Pile cap work completed.
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rd floor -100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab -Second floor roof slab -100% completed
- RCC for slab -Third floor roof slab -Shuttering on progress
As per the current work status from our site we are targeted to complete the following works by end of February 2019
Tower 1
- Column work – 15th floor – 100% to be completed
- RCC for slab – 16th floor – 80% to be completed
- Block work – 11th floor – 100% to be completed,12 th floor -50% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Wall chasing work – 10th floor – 100% completed
- Internal wall plastering work – 6 th floor 100 %to be completed
- Water Proofing work -2-3rd floor (100% to be completed)
- Putty work (2coat) – 3rd floor – 100% to be completed
- MLCP Pile cap work 85% to be completed
Tower 2
- Column rising work – 3rdfloor -100% to be completed
- RCC for slab -third floor roof slab – 50% to be completed
Work status as on 05-02-2019, we have completed the following
Tower 1
- Column work – 14th floor – 100% completed,15 th floor -30%completed
- RCC for slab -15 th floor -50%completed
- Block work – 11 th floor -70% completed
- Ceiling Plastering work – 12th floor – 100% completed,13 -10% completed
- Wall chasing work – 9th floor – 100% completed,10 on progress
- Internal wall plastering work -BF1 (70% completed); GF, 1st,2nd floor (100% completed);3rd floor -(100%completed ),4 th floor -100%completed,5 th floor -100 %completed,6 th floor -25%completed.
- Water Proofing work – GF – 100% completed; 1st floor – 100% completed.2-3rd floor (50% to be completed)
- Putty work (2coat) – GF, 1st floor (100% completed),2nd floor -100% completed
- MLCP Pile cap work 70%completed, rising work on progress
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- Column rising work – 3rdfloor -50% to be completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- RCC for slab – second floor roof slab – 100%completed
As per the current work status from our site we are targeted to complete the following works by end of January 2019
Tower 1
- Column work – 15th floor – 100% to be completed
- RCC for slab – 15th floor – 100% to be completed
- Block work – 11th floor – 100% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Wall chasing work – 10th floor – 100% completed
- Internal wall plastering work – 5 th floor.6 th floor 100 %to be completed
- Putty work (2coat) – 3rd floor – 100% to be completed
Tower 2
- Column rising work – 3rdfloor – 50% to be completed
- RCC for slab – second floor roof slab – 100%to be completed
Work status as on 08-01-2019, we have completed the following
Tower 1
- Column work – 13th floor – 100% completed,14 th floor -90%completed
- RCC for slab – 14 th floor -100% completed,15 th floor -50%completed
- Block work – 10th floor – 100% completed,11 th floor -40% completed
- Ceiling Plastering work – 12th floor – 100% completed,13 on progress
- Wall chasing work – 9th floor – 100% completed,10 on progress
- Internal wall plastering work -BF1 (70% completed); GF, 1st,2nd floor (100% completed);3rd floor -(100%completed ),4 th floor -100%completed,5 th floor -25 %completed.
- Water Proofing work – GF – 100% completed; 1st floor – 100% completed;
- Putty work (2coat) – GF, 1st floor (100% completed),2nd floor -100% completed
- MLCP Pile cap work 60%completed, rising work on progress
Tower 2
- Column work – BF1 – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
As per the current work status from our site we are targeted to complete the following works by end of Decemeber 2019
Tower 1
- Column work – 14th floor – 100% to be completed
- RCC for slab – 14th floor – 100% to be completed
- Block work – 11th floor – 100% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Wall chasing work – 10th floor – 100% completed
- Internal wall plastering work – 3rd floor – 100% to be completed
- Putty work (2coat) – 2nd floor – 100% to be completed
- Pile cap work 50% to be completed
Tower 2
- RCC for slab – secon floor roof roof slab – 100% to becompleted
- Column rising work – 2nd floor – 100% to be completed
Work status as on 06-12-2018, we have completed the following
Tower 1
- Column work – 13th floor – 100% completed,14 th floor on progress
- RCC for slab – 13th floor – 100% completed,14 th floor -50% completed
- Block work – 10th floor – 100% completed,11 th floor -20% completed
- Ceiling Plastering work – 12th floor – 100% completed,13 on progress
- Wall chasing work – 9th floor – 100% completed,10 on progress
- Internal wall plastering work -BF1 (70% completed); GF, 1st,2nd floor (100% completed);3rd floor -(20%completed )
- Water Proofing work – GF – 100% completed; 1st floor – 100% completed;
- Putty work (2coat) – GF, 1st floor (100% completed),2nd floor on progress
- MLCP Pile rising work on progress
Tower 2
- Column work – BF1 – 100% completed
- RCC for slab – BF3 roof slab – 100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- RCC for slab – First floor roof slab – 100% completed
- Column rising work – 1st floor – 100% completed
- Column rising work – 2nd floor -40% completed
As per the current work status from our site we are targeted to complete the following works by end of November 2018
Tower 1
- Column work – 13th floor – 100% to be completed
- RCC for slab – 14th floor – 100% to be completed
- Block work – 12th floor – 100% to be completed
- Ceiling Plastering work – 13th floor – 100% to be completed
- Internal wall plastering work – 2nd floor – 100% to be completed
- Putty work (2coat) – GF – 100% to be completed
Tower 2
- Column rising work – 2nd floor – 100% to be completed
- Slab Rcc work – 2nd floor – 100% to be completed
Work status as on 16-11-2018, we have completed the following
Tower 1
- Column work – 13th floor – 50% completed
- RCC for slab – 13th floor – 100% completed
- Block work – 12th floor – 50% completed
- Ceiling Plastering work – 12th floor – 100% completed
- Wall chasing work – 9th floor – 100% completed
- Internal wall plastering work -BF1 (70% completed); GF (100% completed); 1st floor (100% completed)
- Water Proofing work – GF – 100% completed; 1st floor – 100% completed;
- Putty work (2coat) – GF (80% completed); 1st floor (100% completed)
Tower 2
- Column work – BF1 – 100% completed
- RCC for slab – BF3 roof slab – 100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – BF1 roof slab – 100% completed
- Column rising work – 1st floor – 100% completed
- Slab Rcc work – 2nd floor – 50% completed
Work Schedule for the Month of July 2018
Tower 1
- Column work – 12th floor – 100% to be completed.
- RCC for slab – 12th & 13th floor – 100% to be completed.
- Block work – 10th floor – 100% to be completed.
- Ceiling Plastering work – 11th floor – 100% to be completed.
- Wall chasing work – 8th floor – 100% to be completed.
Tower 2
- GF column work – 100% to be completed.
- GF roof rcc work – 60% to be completed.
Work status as on 05-06-2018, we have completed the following
Tower 1
- Column work – 12th floor – 50% completed.
- RCC for slab – 12th floor half portion – 50% completed.
- Block work – 10th floor – 25% completed.
- Ceiling Plastering work – 10th floor – 100% completed.
- Wall chasing work – 8th floor – started.
- Internal wall plastering work – GF (100% completed); 1st floor (100% completed).
- Water Proofing work – GF – 50% completed; 1st floor – 100% completed.
Tower 2
- Column work – 12th floor – 100% to be completed.
- RCC for slab – 12th & 13th floor – 100% to be completed.
- Block work – 10th floor – 100% to be completed.
- Ceiling Plastering work – 11th floor – 100% to be completed.
- Wall chasing work – 8th floor – 100% to be completed.
- Water Proofing work – GF – 100% to be completed.
As per the current work status from our site we are targeted to complete the following works by end of May 2018
Tower 1
- Column work – 11th floor – 50% to be completed
- RCC for slab – 11th floor – 100% to be completed
- Block work – 9th floor – 100% to be completed
- Wall chasing work -6th floor – 100% to be completed
- Internal wall plastering work – 1st floor -100% to be completed
Tower 2
- Column work – BF1 – 100% to be completed
- RCC for slab – GF roof slab -100% to be completed
Work status as on 05-05-2018, we have completed the following.
Tower 1
- Column work – 10th floor – 100% completed
- RCC for slab – 1st to 9th floor (100% completed);10th floor (100% completed)
- Block work – 8th floor (100% completed); 9th floor (50% completed)
- Ceiling Plastering work – BF2, BF1 & GF to 9th floor (100% completed)
- Wall chasing work – GF ,1st,2nd,3rd, 4th & 5th floor (100% completed)
- Internal wall plastering work – GF (50% completed); 1st floor (90% completed)
Tower 2
- Column work – BF1 – 90% completed
- RCC for slab – BF3 roof slab – 100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab – GF roof slab – 70% completed
- RCC for slab – BF1 roof slab – 100% completed
Work status as on 9-5-2017, we have completed the following.
Tower 1
- Pile cap – completed
- Plinth beam – progressing
- Column work – 100% completed
- Column work – 100% completed
- RCC for slab – 100% completed
Tower 2
- Plinth beam – completed
- RCC for slab – completed
As per the current work status from our site we are targeted to complete the following works by end of April 2018
Tower 1
- Column work – 100% to be completed
- RCC for slab – 10th floor – 100% to be completed
- Block work -8th floor – 100% to be completed
- Ceiling Plastering work – 100% to be completed
- Wall chasing work -100% to be completed
- Internal wall plastering work – 1st floor-100% to be completed
Work status as on 14-04-2018, we have completed the following.
Tower 1
- RCC for slab – 1st to 9th floor (100% completed);10th floor(50% completed)
- Block work – BF2, BF1,GF & 1st to 7th floor(100% completed);8th floor (50% completed)
- Ceiling Plastering work – BF2, BF1 & GF to 8th floor (100% completed)
- Wall chasing work – GF ,1st,2nd,3rd & 4th floor (100% completed)
- Internal wall plastering work – 1st floor (75% completed)
Tower 2
- Plinth beam – 100% completed
- Column work – BF3 – 100% completed
- Column work – BF2 – 100% completed
- Column work – BF1 – 90% completed
- RCC for slab – BF3 roof slab – 100% completed
- RCC for slab – BF2 roof slab – 100% completed
- RCC for slab -GF roof slab – 40% completed
- RCC for slab – BF1 roof slab – 100% completed
-
As per the current work status from our site we are targeted to complete the following works by end of March 2018
Tower 1
- Column work – 9th floor – 100% to be completed
- RCC for slab – 10th floor – 100% to be completed
- Block work -7th floor – 100% to be completed
- Ceiling Plastering work – 100% to be completed
- Internal wall plastering work – 1st floor-100% to be completed
- Wall chasing work -3rd floor-100% to be completed
Work status as on 10-03-2018, we have completed the following.
Tower 1
- Pile cap – 100% completed
- Plinth beam – 100% completed
- Column work – 2nd, 3rd,4th, 5th, 6th& 7th floor- 100% completed; 8th floor(100% completed);9th floor(60% completed)
- RCC for slab – 1st,2nd,3rd, 4th ,5th,6th,7th & 8th floor roof(100% completed);9th floor (100% completed);10th floor(progressing)
- Block work – BF2, BF1,GF -100% completed; 1st , 2nd, 3rd, 4th& 5th floor(100% completed);6th floor(100% completed);7th floor(50% completed)
- Ceiling Plastering work – BF2, BF1,& GF to 5th floor (100% completed);6th,7th floor (100% completed)
- Internal wall plastering work – 1st floor (25% completed)
- Wall chasing work – GF & 1st floor (100% completed);2nd floor(100% completed);3rd floor(60% completed)
Work status as on 09 -02-2018, we have completed the following.
Tower 1
- Column work – 2nd, 3rd,4th, 5th, 6th& 7th floor- 100% completed; 8th floor-60% completed
- RCC for slab – 1st,2nd,3rd, 4th ,5th,6th,7th & 8th floor roof(100% completed);9th floor (50% completed)
- Block work – BF2, BF1,GF -100% completed; 1st , 2nd, 3rd, 4th& 5th floor(100% completed);6th floor(25% completed)
- Ceiling Plastering work – BF2, BF1,& GF to5th floor – (100% completed);6th floor (90% completed)
- Wall chasing work – GF & 1st floor (100% completed);2nd floor(75% completed)
As per the current work status from our site we are targeted to complete the following works by end of February 2018
Tower 1
- Column work – 8th floor – 100% to be completed
- RCC for slab – 9th floor – 100% to be completed
- Block work -6th floor – 100% to be completed
- Ceiling Plastering work – 6th floor – 100% to be completed
- Wall chasing work -100% to be completed
- Internal wall plastering work – 100% to be completed
Work status as on 5-7-2017, we have completed the following.
Tower 1
- Pile cap – completed
- Plinth beam – progressing
- Column work -progressing
Work status as on 9-6-2017, we have completed the following.
Tower 1
- Pile cap – completed
- Plinth beam – completed
- Column work – BF3 – completed
- Column work – BF2 – completed
- Column work – BF1 – completed
- RCC for slab – BF3 roof slab – completed
- RCC for slab – BF2 roof slab – progressing
- RCC for slab – BF1 roof slab – progressing
Work status as on 8-2-2017, we have completed the following.
Tower 1
- Pile cap – progressing
- Column work – progressing
- RCC for slab – progressing
Tower 2
- Plinth beam – completed
- Column work -preogressing
- RCC for slab – progressing