Artech Flora

Project Description

RERA Number: K-RERA/PRJ/023/2020
ARTECH FLORA is our 67th project a private Eden set in the midst of the quiet charm of Poojapura, provides a modern, contemporary and luxurious lifestyle nestled in the warm embrace of nature’s many delights. This project brings to you 2 and 3 BHK apartments designed to let in an abundance of natural light.

Quick Enquire

Take your first few steps towards finding the ultimate happiness of the Perfect Home.

Amenities

  • Association Hall
  • Air-conditioned Unisex Gym
  • Indoor Games room
  • Children’s play area
  • Rooftop party area
  • Guest Suite
  • Driver’s dormitory
  • Security Kiosk
  • Common Area Surveillance
  • Access control & key-less entry (card) to each flat
  • Lobby Surveillance
  • Vehicle RFID systems & boom barriers
  • Lift Access Control
  • Sensor Lighting

Salient Features

  • G+14 floors will be provided for living purpose with 53nos of apartments.
  • This Luxury Project mix of 2 & 3 BHK Luxury apartments.
  • 2 BHK – 1220 Sq.Ft & 1255 Sq.Ft.
  • 3 BHK – 1770 Sq.Ft, 1885 Sq.Ft & 2540 Sq.Ft.

Payment Terms

  • Rs 1 lakh at the time of Booking
  • 30% of the total cost should be paid at the time of the agreement.
  • Balance 70 % of the Total cost can be arranged as Housing loan from Nationalized as well as Private Banks or you can pay in installments as per Payment Schedule in the construction agreement.
  • Square feet rate is to Rs.6250/-, Rs 2,50,000/- for Car Parking. (statutory charges and Registration will cost extra as per Government norms)

Floor Plans

PROGRESS

As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2022.

  • Civil Works – screeding – terrace to be completed
  • Internal Finishes – Main door – 11th to 13th floor 100% to be completed, Water proofing – terrace, ground floor, ramp 100% to be completed, Wall tiling- 14th floor 100% to be completed, Flooring – 14th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – balcony handrail – 90% to be completed
  • External Finishes – Windows and sliding doors – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Gas line work – 60% completed

Work status as on 15-11-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 15th floor 100% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 10th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 14th floor 98% completed, Flooring- up to 14th floor 90% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (8 flats completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – 85% completed
  • External Finishes – Windows and sliding doors – till 12 th floor 90% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 92% completed, Suspended line work – completed, Gas line work – 50% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

Work status as on 11-10-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 13th floor 100% completed & 14th floor 100% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 10th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 14th floor 90% completed, Flooring- up to 14th floor 90% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (8 flats completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – 70% completed.
  • External Finishes – Windows and sliding doors – till 12 th floor 90% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 90% completed, Suspended line work – completed, Gas line work – 50% completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.

As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2022.

  • Internal Finishes – Main door – 11th to 13th floor 100% to be completed, Water proofing – terrace (water tank)100% to be completed, Wall tiling- 14th floor 100% to be completed, Flooring – 14th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – balcony handrail – 75% to be completed.
  • External Finishes – Windows and sliding doors – 95% to be completed.
  • Electrical, Plumbing & Firefighting works – Gas line work – 60% completed.

Work status as on 17-09-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 13th floor 100% completed & 14th floor (95% completed) (except balcony) Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 10th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 13th floor 95% completed, Flooring- up to 13th floor 95% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (8 flats completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – 70% completed.
  • External Finishes – Windows and sliding doors – till 12 th floor 90% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 90% completed, Suspended line work – completed, Gas line work – 45% completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.

As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2022.

  • Internal Finishes – Main door – 11th to 13th floor 100% to be completed, Water proofing – terrace 100% to be completed, Wall tiling- 13th floor 100% to be completed, Flooring – 13th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – balcony handrail – 75% to be completed.
  • External Finishes – Windows and sliding doors – 95% to be completed.

Work status as on 09-07-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 13th floor (except balcony) Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 9th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 12th floor 80% completed, Flooring- up to 13th floor 70% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (1 to 6th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – base frame fixed till 8th floor 70% completed.
  • External Finishes – Windows and sliding doors – 1st, 2nd, 3rd and 6th floor completed, External Painting- outside primer fully completed, 1st coat putty – 60% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – Piping up to 14th floor completed, Suspended line work – till 11th floor completed, Gas line work – 25% completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2022.

  • Internal Finishes – Main door – 10th to 13th floor 100% to be completed, Water proofing – terrace 100% to be completed, Wall tiling- 12th, 13th floor 100% to be completed. Flooring – 13th floor 100% to be completed, passage and staircase till 8th floor to be completed, Putty works and painting – 50% to be completed, Hand rail – Firestair till 5th floor 100% to be completed, balcony handrail – 14 flats top frame fixing 100% to be completed.
  • External Finishes – Windows and sliding doors – 4th, 5th floor 100% to be completed.
  • Electrical, Plumbing & Firefighting works – Suspended line work – up to 15th floor to be completed, duct line work – 30% to be completed.


Work status as on 09-06-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 10th floor Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 9th floor completed, Waterproofing- till 12th floor 100 % completed, Wall tiling- up to 10th floor 90% completed, Flooring- up to 10th floor 95% completed, putty works & Painting- 45% completed (100% 1st coat putty completed (inside), 2nd coat putty (1 to 6th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed
  • External Finishes – Windows and sliding doors – 1st, 2nd, 3rd and 6th floor completed, External Painting- outside primer fully completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 13th Floor Completed, Fire fighting Works – Piping up to 14th floor completed, Suspended line work – till 10th floor completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2022.

  • Civil Works – Screeding – 11th floor 100% to be Completed
  • Internal Finishes – Main door – 10th floor 100% to be completed, Water proofing – 13th, 14th floor 100% to be completed, Wall tiling- 11th, 12th floor 100% to be completed. Flooring – 11th, 12th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – Firestair till 5th floor 100% to be completed
  • External Finishes – Windows and sliding doors – 4th, 5th floor 100% to be completed
  • Electrical, Plumbing & Firefighting works – Firefighting works Concealed plumbing works – 14th floor 100% to be completed, Fire fighting Work – Piping 14th floor to be completed, Suspended line work – 11th, 12th, 13th, 14th floor to be completed

Work status as on 12-04-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 10th floor Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 6th floor completed, Waterproofing-11th floor completed (terrace half portion , basement floor completed), Wall tiling- up to 9th floor completed, Flooring- up to 9th floor completed (passage till 4th floor 100% completed), putty works & Painting- 100% 1st coat putty completed (inside), 2nd coat putty (1 to 5th floor completed), Door frame fixtures – fully completed.
  • External Finishes – External Painting- outside primer fully completed , 20% putty work completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 12th Floor Completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2022.

  • Civil Works – Screeding – 11th floor 100% to be Completed
  • Internal Finishes – Main door – 7th to 9th floor 100% to be completed, Water proofing – 12th floor 100% to be completed, Wall tiling- 10th floor 100% to be completed. Flooring – 10th floor 100% to be completed, Putty works and painting – 2nd coat putty 6th, 7th, 8th floor 100% to be completed (inside).
  • External Finishes – 40% putty work to be completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 13th Floor 100% to be completed.

Work status as on 10-03-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding-10th floor Completed, Internal plaster Completed.
  • Internal Finishes – Main door – 4th floor completed, Waterproofing-10th floor completed, Wall tiling-7th floor completed, Flooring-9th floor completed, putty works & Painting- 100% 1st coat putty completed (inside), Door frame fixtures-fully completed, Handrails-not yet started
  • External Finishes – External Painting- outside primer fully completed, 20% putty work completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works-11th Floor Completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 95% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2022.

  • Civil Works – Screeding – 11th floor to be Completed
  • Internal Finishes – Main door – 6th floor to be completed, Water proofing – 11th floor to be completed, Wall tiling- 9th floor to be completed. Flooring – 10th floor to be completed, Putty works and painting – 30% second coat putty to be completed(inside).
  • External Finishes – 40% putty work to be completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 12th Floor to be completed.
  • Mockup – Electrical works 100% to be Completed.

Work status as on 09-04-2021, we have completed the following.

  • Floor Slab Work :
  1. Retaining wall side ground floor slab -100% completed (west side portion )
  2. GF slab – 13th floor: 100 % completed,14th floor-100% completed.
  3. Upto 15th floor column : 100% completed.
  4. Front side retaining wall slab& front side GF slab: 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING
  1. upto 10th floor -100% completed
  • WALL PLASTERING
  1. upto 8th floor -100% completed.
  • CEILING PLASTERING :
  1. Ground floor -12th floor : 100% completed
  • BLOCK WORK
  1. First floor-8th floor: 100% completed, 9th floor -100%completed.
  • PLUMBING WALL CHASING
  1. 1st-4th floor: 100% completed
  • FIRST COAT PUTTY
  1. Upto 5th floor -100% completed.
  • TILE WORK
  1. Sample falt (4C)-50% completed.
  • WATERPROOFING
  1. Upto 4th floor -100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2021.

  • Floor Slab Work :
  1. 15th-Floor Slab: 100% to be completed
  • ELECTRICAL WALL CHASING
  1. 11th floor -100% to be completed
  • WALL PLASTERING
  1. 9th floor -100% to be completed.
  • CEILING :
  1. 13th floor: 100% to be completed.
  • BLOCK WORK
  1. 10th floor- 100% to be completed.
  • PLUMBING WALL CHASING
  1. 5th floor-: 100% to be completed.
  • FIRST COAT PUTTY
  1. 6th column -100% to be completed
  • TILE WORK
  1. Sample falt (4C)-100% to be completed.
  2. 1st floor:-100% to be completed.
  • WATERPROOFING
  1. 5th floor -100% to be completed.

Work status as on 11-03-2021, we have completed the following.

  • Floor Slab Work :
  1. Retaining wall side ground floor slab -85%  completed (west side portion )
  2. GF slab – 13th floor: 100 % completed,14th floor-50% completed.
  3. Up to 14th floor column : 100% completed.
  4. Front side retaining wall slab& front side GF slab: 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING: 2nd floor-8th floor -100%  completed
  • WALL PLASTERING: 1st floor-6th floor -100%  completed.
  • CEILING: Ground floor -11th floor : 100% completed
  • BLOCK WORK: First floor-8th floor: 100% completed.,9th floor -50%completed.
  • Plumbing Wall Chasing: 1st-4th floor: 100%  completed
  • FIRST COAT PUTTY: Up to 4th floor, -100% completed.
  • WATERPROOFING: Up to 3rd floor, -100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.

  • Floor Slab Work :
  1. Retaining wall work – 95%  to be completed
  2. 14th-Floor Slab: 100% to be completed
  3. 15th column: 100% to be completed
  • ELECTRICAL WALL CHASING: 9th-10th floor -100% to be completed
  • WALL PLASTERING: 7th-8th floor -100% to be completed.
  • CEILING : 12th floor: 100% to be completed.
  • BLOCK WORK: 9th floor- 100% to be completed.
  • Plumbing Wall Chasing: 5th floor-: 100% to be completed.
  • FIRST COAT PUTTY: 5th,6th column -100% to be completed
  • WATERPROOFING: 4th floor  -100% to be completed

As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.

  • Floor Slab Work:
  1. Retaining wall work – 95% to be completed
  2. 14th-Floor Slab: 100% to be completed
  3. 14th column: 100% to be completed
  • ELECTRICAL WALL CHASING: 7th-8th floor -100% to be completed
  • WALL PLASTERING: 6th floor -100% to be completed.
  • CEILING : 11th floor: 100% to be completed.
  • BLOCK WORK: 9th floor- 100% to be completed.
  • Plumbing Wall Chasing: 4th floor-: 100% to be completed.

Work status as on 09-02-2021, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed (west side portion )
  2. GF slab – 13th floor : 100 % completed
  3. Upto 13th floor column : 100% completed,14th floor -50% completed.
  4. Front side retaining wall slab& front side GF slab: 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING: 2nd floor-6th floor -100% completed
  • WALL PLASTERING: 1st floor-5th floor -100% completed.
  • CEILING: Ground floor -10th floor: 100% completed
  • BLOCK WORK: first floor-8th floor: 100% completed.
  • Plumbing Wall Chasing: 1st-3rd floor: 100% completed,4th floor -50% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2021

  • Floor Slab Work:
  1. Retaining wall work – 95% to be completed
  2. 13th-Floor Slab: 100% to be completed
  3. 14th column: 100% to be completed
  • ELECTRICAL WALL CHASING: 5th-6th floor -100% to be completed
  • WALL PLASTERING: 4th floor(CD): 100% to be completed, 5th floor -100% to be completed.
  • CEILING : 10th floor: 100% to be completed.
  • BLOCK WORK: 8th floor- 100% to be completed.
  • Plumbing Wall Chasing: 4th floor-: 100% to be completed.

Work status as on 07-01-2021, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed (west side portion )
  2. GF slab – 12th floor : 100 % completed
  3. Upto 13th floor column : 100% completed
  4. Front side retaining wall slab& front side GF slab : 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING: 2nd floor- 4th floor 100% completed, 5th-6th floor -50% completed
  • WALL PLASTERING: 1st floor-3rd floor -100% completed, 4th floor(AB): 100% completed.
  • CEILING: Ground floor -9th floor : 100% completed
  • BLOCK WORK: first floor-7th floor: 100% completed.
  • Plumbing Wall Chasing: 1st-3rd floor: 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of July 2020

  • Retaining wall work -80% to be completed
  • Sixth floor Slab : 100% to be completed
  • Seventh floor Slab : 60% to be completed
  • Front portion GF slab : 100% to be completed
  • Fifth floor: 100% to be completed.
  • First floor- 50% to be completed.

Work status as on 11-06-2020, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed (west side portion )
  2. GF slab – 4th floor : 100 % completed
  3. Fifth floor Slab : 100% completed
  4. Sixth floor Slab : 60% completed
  5. Back side retaining wall area : 100%
  6. Fround side retaining wall area slab& front side GF slab : 50% completed.
  • CEILING:
  1. Ground floor ceiling plastering : 100% completed
  2. first floor : 100 % completed
  3. second floor : 100 %completed
  4. Third floor: 100% completed.
  5. Forth floor: 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of March 2020

  • Retaining wall work: 100% to be (west side) completed
  • Third floor Slab: 100% to be completed
  • Fourth floor Slab: 100% to be completed
  • Front side retaining wall area slab: 100% to be completed
  • CEILING: ground floor & first floor- 100 will be completed

Work status as on 11-03-2020, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed(west side portion)
  2. Ground floor slab : 100 % completed
  3. First floor Slab :100% completed
  4. Second floor Slab :100% completed
  5. Third floor Slab : 100% completed
  6. Fourth floor Slab : 100% completed
  7. Back side retaining wall area : 100%
  8. Fround side retaining wall area slab& front side GF slab : 50% to be completed.
  • CEILING:
  1. Ground floor ceiling plastering : 100% completed
  2. first floor : 100 %completed
  3. second floor : 50 %completed

As per the current work status from our site, we are targeted to complete the following works by the end of February 2020

  • Retaining wall work: 100% to be (west side)completed
  • Third floor Slab: 100% to be completed
  • Fourth floor Slab: 100% to be completed
  • Front side retaining wall area slab: 100% to be completed
  • CEILING: ground floor & first floor- 100 will be completed

Work status as on 08-02-2020, we have completed the following.

  • Retaining wall side ground floor slab -85% completed(west side portion)
  • Ground floor slab: 100% completed
  • First floor Slab: 100% completed
  • Second floor Slab: 100% completed
  • Third floor Slab: 60% completed
  • Ground floor ceiling plastering : 20% completed
  • Back side retaining wall area: 100%
  • Front side retaining wall area: 50%

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2020

  • Retaining wall work -100% to be (west side )completed
  • Second floor Slab :100% to be completed
  • Third floor Slab :100% to be completed

Work status as on 10-01-2020, we have completed the following.

  • Retaining wall side ground floor slab -85% completed(west side portion )
  • Ground floor slab : 100 % completed
  • First floor Slab :100% completed
  • Second floor Slab :60% completed

As per the current work status from our site we are targeted to complete the following works by end of September 2019

  • Retaining wall work -25% to be completed
  • Basement floor slab :75 % to be completed

Work status as on 05.09.2019, we have completed the following

  • Retaining wall work -5% completed
  • Basement floor slab :30 % completed

Work status as on 05.08.2019, we have completed the following

  • Retaining wall work -on progressing
  • Earth work excavation- on Progressing
  • Raft slab work -On progressing

Specification

Structure
  • Column footing complying with seismic 3 zones.
  • RCC frame structure with brickwork and or concrete block partitions. Concrete grade and Steel grade as per structural consultant’s advice.
Flooring, Tiling & Railings
  • Main entrance lobby, Lift lobby and Lift fascia (wall & floor) using composite marble/granite/ vitrified tiles, as per the architect’s design.
  • Staircases using granite / vitrified tile flooring with hand railing using SS / MS / GI with or without toughened glass as per architect’s design.
  • Car park Area: Grano flooring with grooves or exterior grade paving tiles.
  • Foyer / Living / Dining using 80cm X 80cm Premium Double charged vitrified tiles.
  • Kitchen: 60cm X 60cm premium double charged Vitrified tiles for the flooring
  • All Bedrooms: 60cm X 60cm Premium Double Charged Vitrified Tiles.
  • All Bedroom Toilets: Designer ceramic tile concepts 30cm X 30cm for floor and 60cm X 30cm for walls up to ceiling height of 8’ 0.
  • Servants Toilet : Ceramic tile 30cm X 30cm for floor and 30cm X 45cm for walls upto 7’6″ height.
  • Utility Room: 30cm X 30cm for floor and 30cm X 45cm for (kitchen wall) walls at a height of 2’ above the counter if any
  • Balconies / Open Terraces /Decks: Rustic /Antiskid/ceramic tiles 30cm X 30cm or (wood finished vitrified tiles) with SS / MS / GI with or without toughened glass as per architect’s design up to 1.2m height.
Sanitary & Plumbing
  • Sanitary fittings: will be of KOHLER or ROCA.
  • All Sanitary wares shall be of white color only.
  • Concealed cisterns (concealed flushing system) will be of GEBERIT from Switzerland or GROHE from Germany. Actuator plates shall be in CP Finish dual flushing system.
  • Faucets: for all the bedroom toilets will be single lever concealed diverters CP finish, heavy body metal fittings of ROCA from Spain or GROHE from Germany or KOHLER. Provision for hot water connection shall be provided for an overhead shower.
  • Wall mounted single lever faucet make ROCA from Spain or GROHE from Germany or KOHLER will be provided for the wash basins, Kitchen and utility area sink.
  • Plumbing: All water supply lines shall be in ISI marked CPVC pipes. Drainage lines and stormwater drain pipes shall be in PVC, Cockroach traps make CHILLI shall be provided as gratings for all necessary locations, Health Faucet ROCA from Spain or GROHE from Germany or KOHLER shall be provided near EWC in all the toilets.
  • Stainless Steel Sink multi-bowl with drain board of make NIRALI / FRANKE shall be provided for the kitchen and stainless steel sink without drain board shall be provided for the utility areas.
  • Towel rods, towel ring, soap dish shall be provided inside the toilets.
Doors & Windows
  • Window shutters: Prefabricated color anodized aluminum sliding shutters by (Hindalco). One pane of Insect screen also shall be provided in each window.
  • Door Frames: Main door frame and shutter shall be of seasoned teak wood. Outer and Inner face to be PU coated and finished as per the Architect’s design.
  • Door Shutters: All internal door frames shall be of seasoned hardwood with flush door shutters. All internal and external faces shall be melamine finish or Paint finish as per the Architects design.
  • Hardware: All hardware shall be in C.P Brass, tower bolts, door stoppers, ball bearing hinges. Locks shall be mortise of DORSET / YALE make from USA/UNION.
    Entrance door shall have hardware such as Magic Eye, Safety Chain, Door Stopper and a Digital lock from HAFELE / YALE.
Electrical
  • Concealed copper wiring using FINOLEX / V-GUARD / HAVELLS make cables with modular plate switches, centralized cabling system for all electrical and communication requirements.
  • Wiring shall be done for lighting, 6 Amps, 16 Amps and AC points in the Apartment.
    Switches: All switches shall be LEGRAND or SCHNEIDER.
  • Generator: Power backup will be provided for all common services and selected light and fan point each in living, bedrooms inside apartment and a refrigerator point, plus additional one 6 Amp plug point in the Kitchen, one light point in all the toilets, one 6 Amp plug point at Living for emergency charging of devices shall be provided (Air-conditioning and Geyser points and other 16 Amp points will not be considered for the power back up).
  • Light fixtures for the Common areas, external areas, apartment balconies and at the entrance door of the individual apartments shall be provided.
  • All light fixtures shall be of PHILIPS / HAVELLS.
  • Adequate ELCB and MCB shall be provided in each apartments SIEMENS / HAVELLS.
  • Provision for the GEYSER points and fresh air fans shall be provided for all toilets.
  • Provision for telephone and Internet shall be provided in the living room and master bedroom.
  • Provision for Cable TV / DTH shall be provided in the Living and Master Bedroom.
Paint Finishes
  • Premium emulsion paint shall be applied for the ceiling and interior walls of the apartments excluding Utility and Services.
  • Internal Walls: Acrylic/cement based Putty with Premium emulsion paint.
  • External Walls: Weather shield exterior grade emulsion/texture paint.
Elevators
  • The high-speed lift shall be provided as per the Govt. norms in each core with automatic doors & SS brush finish of KONE / SCHINDLER / MITSUBISHI.
  • ARD (Automatic Rescue Device) shall be installed in the passenger lift as a premium feature.
Air Conditioning
  • Provision for Air-Conditioning in Living, Dining and all bedrooms.
Home Automation
  • Multi-level security systems for common areas and lobbies, Access control entry to the common entrance/foyers and gymnasium.
  • Light motion sensors for selected common areas.
  • Home security monitoring, gas leakage detectors, emergency panic intrusion alarm, visitor tracking.
Landscaping
  • Provision for sprinklers and a drip system shall be provided for necessary common area landscaping.
  • Interlock Pavers to be laid in driveways and walkways.
  • Hard and soft landscaping shall be provided as per the landscape consultant’s design.