PROGRESS
Work status as on 09-06-2022, we have completed the following.
- Structural Works – All sub-structural and structural works-Completed.
- Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 10th floor Completed, Internal plaster Completed.
- Internal Finishes – Main door – up to 9th floor completed, Waterproofing- till 12th floor 100 % completed, Wall tiling- up to 10th floor 90% completed, Flooring- up to 10th floor 95% completed, putty works & Painting- 45% completed (100% 1st coat putty completed (inside), 2nd coat putty (1 to 6th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed
- External Finishes – Windows and sliding doors – 1st, 2nd, 3rd and 6th floor completed, External Painting- outside primer fully completed, External Plastering- fully completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 13th Floor Completed, Fire fighting Works – Piping up to 14th floor completed, Suspended line work – till 10th floor completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2022.
- Civil Works – Screeding – 11th floor 100% to be Completed
- Internal Finishes – Main door – 10th floor 100% to be completed, Water proofing – 13th, 14th floor 100% to be completed, Wall tiling- 11th, 12th floor 100% to be completed. Flooring – 11th, 12th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – Firestair till 5th floor 100% to be completed
- External Finishes – Windows and sliding doors – 4th, 5th floor 100% to be completed
- Electrical, Plumbing & Firefighting works – Firefighting works Concealed plumbing works – 14th floor 100% to be completed, Fire fighting Work – Piping 14th floor to be completed, Suspended line work – 11th, 12th, 13th, 14th floor to be completed
Work status as on 12-04-2022, we have completed the following.
- Structural Works – All sub-structural and structural works-Completed.
- Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 10th floor Completed, Internal plaster Completed.
- Internal Finishes – Main door – up to 6th floor completed, Waterproofing-11th floor completed (terrace half portion , basement floor completed), Wall tiling- up to 9th floor completed, Flooring- up to 9th floor completed (passage till 4th floor 100% completed), putty works & Painting- 100% 1st coat putty completed (inside), 2nd coat putty (1 to 5th floor completed), Door frame fixtures – fully completed.
- External Finishes – External Painting- outside primer fully completed , 20% putty work completed, External Plastering- fully completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 12th Floor Completed.
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2022.
- Civil Works – Screeding – 11th floor 100% to be Completed
- Internal Finishes – Main door – 7th to 9th floor 100% to be completed, Water proofing – 12th floor 100% to be completed, Wall tiling- 10th floor 100% to be completed. Flooring – 10th floor 100% to be completed, Putty works and painting – 2nd coat putty 6th, 7th, 8th floor 100% to be completed (inside).
- External Finishes – 40% putty work to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 13th Floor 100% to be completed.
Work status as on 10-03-2022, we have completed the following.
- Structural Works – All sub-structural and structural works-Completed.
- Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding-10th floor Completed, Internal plaster Completed.
- Internal Finishes – Main door – 4th floor completed, Waterproofing-10th floor completed, Wall tiling-7th floor completed, Flooring-9th floor completed, putty works & Painting- 100% 1st coat putty completed (inside), Door frame fixtures-fully completed, Handrails-not yet started
- External Finishes – External Painting- outside primer fully completed, 20% putty work completed, External Plastering- fully completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works-11th Floor Completed.
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 95% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2022.
- Civil Works – Screeding – 11th floor to be Completed
- Internal Finishes – Main door – 6th floor to be completed, Water proofing – 11th floor to be completed, Wall tiling- 9th floor to be completed. Flooring – 10th floor to be completed, Putty works and painting – 30% second coat putty to be completed(inside).
- External Finishes – 40% putty work to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 12th Floor to be completed.
- Mockup – Electrical works 100% to be Completed.
Work status as on 09-04-2021, we have completed the following.
- Retaining wall side ground floor slab -100% completed (west side portion )
- GF slab – 13th floor: 100 % completed,14th floor-100% completed.
- Upto 15th floor column : 100% completed.
- Front side retaining wall slab& front side GF slab: 80% completed.
- Backside retaining wall area: 100% completed
- upto 10th floor -100% completed
- upto 8th floor -100% completed.
- Ground floor -12th floor : 100% completed
- First floor-8th floor: 100% completed, 9th floor -100%completed.
- 1st-4th floor: 100% completed
- Upto 5th floor -100% completed.
- Sample falt (4C)-50% completed.
- Upto 4th floor -100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2021.
- 15th-Floor Slab: 100% to be completed
- 11th floor -100% to be completed
- 9th floor -100% to be completed.
- 13th floor: 100% to be completed.
- 10th floor- 100% to be completed.
- 5th floor-: 100% to be completed.
- 6th column -100% to be completed
- Sample falt (4C)-100% to be completed.
- 1st floor:-100% to be completed.
- 5th floor -100% to be completed.
Work status as on 11-03-2021, we have completed the following.
- Retaining wall side ground floor slab -85% completed (west side portion )
- GF slab – 13th floor: 100 % completed,14th floor-50% completed.
- Up to 14th floor column : 100% completed.
- Front side retaining wall slab& front side GF slab: 80% completed.
- Backside retaining wall area: 100% completed
- ELECTRICAL WALL CHASING: 2nd floor-8th floor -100% completed
- WALL PLASTERING: 1st floor-6th floor -100% completed.
- CEILING: Ground floor -11th floor : 100% completed
- BLOCK WORK: First floor-8th floor: 100% completed.,9th floor -50%completed.
- Plumbing Wall Chasing: 1st-4th floor: 100% completed
- FIRST COAT PUTTY: Up to 4th floor, -100% completed.
- WATERPROOFING: Up to 3rd floor, -100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.
- Retaining wall work – 95% to be completed
- 14th-Floor Slab: 100% to be completed
- 15th column: 100% to be completed
- ELECTRICAL WALL CHASING: 9th-10th floor -100% to be completed
- WALL PLASTERING: 7th-8th floor -100% to be completed.
- CEILING : 12th floor: 100% to be completed.
- BLOCK WORK: 9th floor- 100% to be completed.
- Plumbing Wall Chasing: 5th floor-: 100% to be completed.
- FIRST COAT PUTTY: 5th,6th column -100% to be completed
- WATERPROOFING: 4th floor -100% to be completed
As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.
- Retaining wall work – 95% to be completed
- 14th-Floor Slab: 100% to be completed
- 14th column: 100% to be completed
- ELECTRICAL WALL CHASING: 7th-8th floor -100% to be completed
- WALL PLASTERING: 6th floor -100% to be completed.
- CEILING : 11th floor: 100% to be completed.
- BLOCK WORK: 9th floor- 100% to be completed.
- Plumbing Wall Chasing: 4th floor-: 100% to be completed.
Work status as on 09-02-2021, we have completed the following.
- Retaining wall side ground floor slab -85% completed (west side portion )
- GF slab – 13th floor : 100 % completed
- Upto 13th floor column : 100% completed,14th floor -50% completed.
- Front side retaining wall slab& front side GF slab: 80% completed.
- Backside retaining wall area: 100% completed
- ELECTRICAL WALL CHASING: 2nd floor-6th floor -100% completed
- WALL PLASTERING: 1st floor-5th floor -100% completed.
- CEILING: Ground floor -10th floor: 100% completed
- BLOCK WORK: first floor-8th floor: 100% completed.
- Plumbing Wall Chasing: 1st-3rd floor: 100% completed,4th floor -50% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2021
- Retaining wall work – 95% to be completed
- 13th-Floor Slab: 100% to be completed
- 14th column: 100% to be completed
- ELECTRICAL WALL CHASING: 5th-6th floor -100% to be completed
- WALL PLASTERING: 4th floor(CD): 100% to be completed, 5th floor -100% to be completed.
- CEILING : 10th floor: 100% to be completed.
- BLOCK WORK: 8th floor- 100% to be completed.
- Plumbing Wall Chasing: 4th floor-: 100% to be completed.
Work status as on 07-01-2021, we have completed the following.
- Retaining wall side ground floor slab -85% completed (west side portion )
- GF slab – 12th floor : 100 % completed
- Upto 13th floor column : 100% completed
- Front side retaining wall slab& front side GF slab : 80% completed.
- Backside retaining wall area: 100% completed
- ELECTRICAL WALL CHASING: 2nd floor- 4th floor 100% completed, 5th-6th floor -50% completed
- WALL PLASTERING: 1st floor-3rd floor -100% completed, 4th floor(AB): 100% completed.
- CEILING: Ground floor -9th floor : 100% completed
- BLOCK WORK: first floor-7th floor: 100% completed.
- Plumbing Wall Chasing: 1st-3rd floor: 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of July 2020
- Retaining wall work -80% to be completed
- Sixth floor Slab : 100% to be completed
- Seventh floor Slab : 60% to be completed
- Front portion GF slab : 100% to be completed
- Fifth floor: 100% to be completed.
- First floor- 50% to be completed.
Work status as on 11-06-2020, we have completed the following.
- Retaining wall side ground floor slab -85% completed (west side portion )
- GF slab – 4th floor : 100 % completed
- Fifth floor Slab : 100% completed
- Sixth floor Slab : 60% completed
- Back side retaining wall area : 100%
- Fround side retaining wall area slab& front side GF slab : 50% completed.
- Ground floor ceiling plastering : 100% completed
- first floor : 100 % completed
- second floor : 100 %completed
- Third floor: 100% completed.
- Forth floor: 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of March 2020
- Retaining wall work: 100% to be (west side) completed
- Third floor Slab: 100% to be completed
- Fourth floor Slab: 100% to be completed
- Front side retaining wall area slab: 100% to be completed
- CEILING: ground floor & first floor- 100 will be completed
Work status as on 11-03-2020, we have completed the following.
- Retaining wall side ground floor slab -85% completed(west side portion)
- Ground floor slab : 100 % completed
- First floor Slab :100% completed
- Second floor Slab :100% completed
- Third floor Slab : 100% completed
- Fourth floor Slab : 100% completed
- Back side retaining wall area : 100%
- Fround side retaining wall area slab& front side GF slab : 50% to be completed.
- Ground floor ceiling plastering : 100% completed
- first floor : 100 %completed
- second floor : 50 %completed
As per the current work status from our site, we are targeted to complete the following works by the end of February 2020
- Retaining wall work: 100% to be (west side)completed
- Third floor Slab: 100% to be completed
- Fourth floor Slab: 100% to be completed
- Front side retaining wall area slab: 100% to be completed
- CEILING: ground floor & first floor- 100 will be completed
Work status as on 08-02-2020, we have completed the following.
- Retaining wall side ground floor slab -85% completed(west side portion)
- Ground floor slab: 100% completed
- First floor Slab: 100% completed
- Second floor Slab: 100% completed
- Third floor Slab: 60% completed
- Ground floor ceiling plastering : 20% completed
- Back side retaining wall area: 100%
- Front side retaining wall area: 50%
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2020
- Retaining wall work -100% to be (west side )completed
- Second floor Slab :100% to be completed
- Third floor Slab :100% to be completed
Work status as on 10-01-2020, we have completed the following.
- Retaining wall side ground floor slab -85% completed(west side portion )
- Ground floor slab : 100 % completed
- First floor Slab :100% completed
- Second floor Slab :60% completed
As per the current work status from our site we are targeted to complete the following works by end of September 2019
- Retaining wall work -25% to be completed
- Basement floor slab :75 % to be completed
Work status as on 05.09.2019, we have completed the following
- Retaining wall work -5% completed
- Basement floor slab :30 % completed
Work status as on 05.08.2019, we have completed the following
- Retaining wall work -on progressing
- Earth work excavation- on Progressing
- Raft slab work -On progressing