Progress
As per the current work status from our site we are targeted to complete the following works by end of February 2019
- Ceiling Plastering work – 14th floor (50%to be completed);
- Wall plastering work – 10 th floor (30% to be completed),11th floor (20% to be completed).
- Dadoing of Toilets: 1st &2nd floor(60% tobe completed),3&4th -50% to be completed.
- Application of putty walls & ceiling :5th floor (50% to becompleted)
- Wire pulling : 2nd floor 20% to be completed,3rd &4th 30% to be completed.
- Water proofing and pressure Grouting work: 1-6th floor(80% completed),6 th &7th floor(75% completed)
- Flooring and skirting :1st&2nd floor (30% to be completed)
- Aluminium Windows and Ventilators -1st&2nd floor (30% to be completed)
- Grills &Handrails :2ndfloor(40% to becompleted )and 2nd floor(30% to becompleted)
- DB Dressing & Switch fixing : 1st and 2 nd floor (30% to be completed)
Work status as on 05-02-2019, we have completed the following
- Earth work Excavation – 96% completed
- RCC for Pile cap & Grade beam – 100% completed
- Earth work & Back filling – 95% completed
- RCC for structure – BF to 8th floor (95% completed); 9th to 14th floor (80% completed); 15th floor (30% completed)
- Ceiling Plastering work – BF & GF (80% completed); 1st to7th floor (95% completed);8th to 13th floor (80% completed);
- Block work – 1st to 11th floor (80% completed),12 th floor (40%)
- Door frame fixing -1st &2 ndfloor (95% completed);3rd to10 th floor (80% completed)
- Electrical chasing work – 1st floor to 3rd (95% completed); 4th to 9th floor – 80% completed,10th&11 th floor (70%completed)
- Plumbing work -1st floor – 4th floor (80% completed);5 th floor(70%),6-8th floor -80%completed,9 th floor -50%completed,10 th floor -10%completed.
- Wall plastering work – 1st to 2nd floor (95% completed);3rd(85%completed)-4th floor (80% completed); 5th floor (70% completed);6th floor-8th floor(80% completed),9th floor(50%completed);10 th floor (10%completed).
- Dadoing of Toilets: 1st &2nd floor(50%completed)
- Application of putty walls & ceiling :1-2nd floor (95%completed),3rd -4th floor- 80%completed,6th floor -50%complteted,7th floor-25% completed
- Wire pulling : 1st floor 20% completed.
- Water proofing and pressure Grouting work: 1-6th floor(80% completed),6 th &7th floor( 75% completed)
- Flooring and skirting :2 nd floor (20% completed)
- Aluminium Windows and Ventilators – 2 nd floor( 20% completed)
- Grills &Handrails :BF,GF,1st,3 rd floor(5%completed),2nd floor -20% completed,3rd floor- 30% completed.
- Painting :(1 st coat putty ) -2 nd floor (40% completed)
- DB Dressing & Switch fixing :2 nd floor (10% completed)
As per the current work status from our site we are targeted to complete the following works by end of Janauary 2019
- RCC for structure 9th to 10th floor (95 to becompleted); 15th floor (80% to becompleted)
- Block work – GF to 4th floor -95%to be completed.
- Door frame fixing -1st floor to 4 th floor -95% to be completed
- Dadoing of Toilets:1 st to 3rd floor -60% to be completed
- Application of putty walls & ceiling :5th floor (80% to becompleted),6 th floor- 50% to be completed,7th floor-50%to be completed
- Wire pulling : 1st floor and 2nd floor 40% to be completed.
- Water proofing and pressure Grouting work: 3rd floor to5 th floor (80% to be completed),6 th and 7th floor 20% to be completed
- Flooring and skirting : 1st and 2 nd floor (40% to be completed)
- Grills &Handrails :1 st and 2nd floor(60% to becompleted)
- DB Dressing & Switch fixing : 1st and 2 nd floor (30% to be completed)
Work status as on 08-01-2019, we have completed the following
- Earth work Excavation – 96% completed
- RCC for Pile cap & Grade beam – 95% completed
- Earth work & Back filling – 90% completed
- RCC for structure – BF to 7th floor (95% completed); 8th to 13th floor (80% completed); 14th floor (80% completed)
- Ceiling Plastering work – BF & GF (80% completed); 1st to 6th floor (95% completed); 7th to 12th floor (80% completed); 13th floor (75% completed)
- Block work – 1st to 12th floor (80% completed)
- Door frame fixing -1st floor (80% completed); 2nd to7 th floor (40% completed)
- Electrical chasing work – 1st floor to 3rd (95% completed); 4th to 9th floor – 80% completed.
- Plumbing work -1st floor – 4th floor (80% completed);5 th floor(70%)-8th floor -50%completed
- Wall plastering work – 1st to 2nd floor (95% completed);3-4th floor (80% completed); 5th floor (70% completed);6th floor(80% completed),7th floor(75%completed);8 th floor (70%completed),9 th floor-40% completed.
- Dadoing of Toilets: 2nd floor(25%completed)
- Application of putty walls & ceiling :1-4 th floor (80%completed),6 th floor- 10%completed,7th floor-5% completed
- Wire pulling : 1st floor 20% completed.
- Water proofing and pressure Grouting work: 1-2 nd floor(80% completed),3rd floor( 65% completed),4 th floor (60% completed),5 th floor (20% completed)
- Flooring and skirting :2 nd floor (20% completed)
- Aluminium Windows and Ventilators – 2 nd floor( 20% completed)
- Grills &Handrails :BF,GF,1st,3 rd floor(5%completed),2nd floor -20% completed.
- Painting :1 st coat -2 nd floor (40% completed)
- DB Dressing & Switch fixing :2 nd floor (10% completed)
As per the current work status from our site we are targeted to complete the following works by end of December 2019
- Door Frame fixing :9 &12 th -20% to be completed,10&11 -80% to be completed.
- Plumbing work -5th floor – 50% to be completed,6 th floor -30% to be completed.
- Wire pulling : 2nd floor 20% to be completed.
- Water proofing and pressure Grouting wo:,3rd floor( 75% to becompleted),4 th floor (70%to be completed),6th floor (60% completed)
- Grills &Handrails :2nd floor(20% to becompleted)
Work status as on 06-12-2018, we have completed the following
- Earth work Excavation – 96% completed
- RCC for Pile cap & Grade beam – 95% completed
- Earth work & Back filling – 90% completed
- RCC for structure – BF to 7th floor (95% completed); 8th to 13th floor (80% completed); 14th floor (80% completed)
- Ceiling Plastering work – BF & GF (80% completed); 1st to 4th floor (95% completed); 5th to 11th floor (80% completed); 12th floor (20% completed)
- Block work – 1st to 9th floor (80% completed); 10th floor (60% completed); 11th floor (30% completed)
- Door frame fixing -1st floor (80% completed); 2nd & 3rd floor (40% completed); 4th floor (20% completed); 5th floor (40% completed); 7th floor (30% completed),8 th floor(20%)
- Electrical chasing work – 1st floor (95% completed); 2nd to 6th floor – 80% completed; 7th floor (30% completed);8 th floor (20%completed)
- Plumbing work -1st floor – 70% completed; 2nd floor (70% completed; 3rd floor (55% completed); 4th floor (30% completed);5 th floor(30%)
- Wall plastering work – 1st to 2nd floor (95% completed);3-4th floor (80% completed); 5th floor (60% completed);6th floor(80% completed),7th floor(50%completed);8 th floor (30%completed).
- Dadoing of Toilets: 2nd floor(20%completed)
- Application of putty walls & ceiling :1-3rd floor (80%completed),4 th floor- 50%completed.
- Wire pulling : 1st floor 10% completed.
- Water proofing and pressure Grouting work: 1-2 nd floor(80% completed),3rd floor( 65% completed),4 th floor (60% completed),5 th floor (20% completed)
- Flooring and skirting :2 nd floor (20% completed)
- Aluminium Windows and Ventilators – 2 nd floor( 20% completed)
- Grills &Handrails :BF-3 rd floor(5%completed)
- Painting :1 st coat -2 nd floor (40% completed)
- DB Dressing & Switch fixing :2 nd floor (10% completed)
As per the current work status from our site we are targeted to complete the following works by end of November 2018
- Earth work Excavation – 100% to be completed
- RCC for Pile cap & Grade beam – 100% to be completed
- Earth work & Back filling – 100% to be completed
- RCC for Structure – 14th floor – 100% to be completed
- Ceiling Plastering work – 12th floor – 100% to be completed
- Block work – 9th to 11th floor – 100% to be completed
- Door frame fixing – 6th floor – 100% to be completed
- Electrical chasing work – 6th & 7th floor – 80% to be completed
- Plumbing work -4th & 5th floor – 100% to be completed
- Wall plastering work – 5th and 6th floor – 100% to be completed
Work status as on 16 -11-2018, we have completed.
- Earth work Excavation – 95% completed
- RCC for Pile cap & Grade beam – 95% completed
- Earth work & Back filling – 90% completed
- RCC for structure – BF to 7th floor (95% completed); 8th to 13th floor (80% completed); 14th floor (40% completed)
- Ceiling Plastering work – BF & GF (80% completed); 1st to 4th floor (95% completed); 5th to 10th floor (80% completed); 11th floor (60% completed)
- Block work – 1st to 8th floor (80% completed); 9th floor (50% completed); 10th floor (5% completed)
- Door frame fixing -1st floor (80% completed); 2nd & 3rd floor (40% completed); 4th floor (20% completed); 5th floor (40% completed); 6th floor (5% completed)
- Electrical chasing work – 1st floor (95% completed); 2nd to 5th floor – 80% completed; 6th floor (40% completed)
- Plumbing work -1st floor – 10% completed; 2nd floor (70% completed; 3rd floor (55% completed); 4th floor (60% completed)
- Wall plastering work – 1st to 3rd floor (80% completed); 4th floor (60% completed); 5th & 6th floor (50% completed)
- Earth work Excavation – 95% completed
- RCC for Pile cap & Grade beam – 95% completed
- Earth work & Back filling – 90% completed
- RCC for structure – BF to 2nd floor (95% completed); 3rd to 9th floor (80% completed); 10nth floor (40% completed)
- Ceiling Plastering work – BF to 6th floor – 80% completed
- Block work – 1st to 3rd floor (80% completed); 4th floor (50% completed)
- Door frame fixing -1st floor – 70% completed
- Electrical chasing work – 1st to 3rd floor – 80% completed
- Plumbing work -1st floor – 10% completed
- Wall plastering work – 1st floor (65% completed); 2nd floor (25% completed)
As per the current work status from our site we are targeted to complete the following works by end of June 2018
- Earth work Excavation – 100% to be completed
- RCC for Pile cap & Grade beam – 100% to be completed
- Earth work & Back filling – 100% to be completed
- RCC for Structure – 10nth floor – 100% to be completed
- Ceiling Plastering work – 6th floor -100% to be completed
- Block work – 4th floor – 100% to be completed
- Door frame fixing – 1st floor – 100% to be completed
- Electrical chasing work – 3rd floor – 100% to be completed
- Plumbing work – 100% to be completed
- Wall plastering work – 1st floor -100% to be completed
As per the current work status from our site we are targeted to complete the following works by end of April 2018
- Earth work Excavation – 100% to be completed
- RCC for Pile cap & Grade beam – 100% to be completed
- Earth work & Back filling – 100% to be completed
- RCC for Structure – 100% to be completed
- Ceiling Plastering work – 1st & 2nd floor -100% to be completed
- Block work – 100% to be completed
- Door frame fixing – 100% to be completed
- Electrical chasing work – 100% to be completed
- Plumbing work -100% to be completed
- Wall plastering work – 1st floor -100% to be completed
Work status as on 1 9 -0 4-2018, we have completed.
- Earth work Excavation – 95% completed
- RCC for Pile cap & Grade beam – 95% completed
- Earth work & Back filling – 90% completed
- RCC for structure – BF & GF (95% completed); 1st to 8th floor(80% completed);9th floor (10% completed)
- Ceiling Plastering work – 1st & 2nd floor (90% completed);BF,GF,3rd, 4th & 5th floor (80% completed)
- Block work – 1st floor (80% completed);2nd floor (75% completed); 3rd floor (70% completed)
- Door frame fixing -1st floor (55% completed)
- Electrical chasing work – 1st floor (65% completed); 2nd floor (20% completed)
- Plumbing work -1st floor (10% completed)
- Wall plastering work – 1st floor (35% completed)
As per the current work status from our site we are targeted to complete the following works by end of March 2018
- Earth work Excavation – 100% to be completed
- RCC for Pile cap & Grade beam – 100% to be completed
- Earth work & Back filling – 100% to be completed
- RCC for Structure – 100% to be completed
- Block work – 100% to be completed
- Ceiling Plastering work – 1st & 2nd floor -100% to be completed
- Wall plastering work – 1st floor -100% to be completed
- Electrical chasing work – 100% to be completed
- Door frame fixing -1st floor – 100% to be completed
- Plumbing work -1st floor -100% to be completed
Work status as on 1 3 -0 3 -2018, we have completed.
- Earth work Excavation – 95% completed
- RCC for Pile cap & Grade beam – 95% completed
- Earth work & Back filling – 90% completed
- RCC for structure – BF to 7th floor(80% completed)
- Block work – 1st floor (80% completed);2nd,3rd floor (65% completed)
- Ceiling Plastering work – 1st & 2nd floor (90% completed);BF,GF,3rd & 4th floor (80% completed)
- Wall plastering work – 1st floor (20% completed)
- Electrical chasing work – 1st floor (30% completed)
- Door frame fixing -1st floor (40% completed)
- Plumbing work -1st floor (10% completed)
As per the current work status from our site we are targeted to complete the following works by end of February 2018.
- Earth work Excavation – 100% to be completed
- RCC for Pile cap & Grade beam – 100% to be completed
- Earth work & Back filling – 100% to be completed
- RCC for Structure – 100% to be completed
- Ceiling Plastering work – 1st & 2nd floor -100% to be completed
- Block work – 100% to be completed
- Door frame fixing -1st floor – 100% to be completed
- Electrical chasing work – 100% to be completed
Work status as on 10-0 2 -2018, we have completed.
- Earth work Excavation – 90% completed
- RCC for Pile cap & Grade beam – 90% completed
- Earth work & Back filling – 80% completed
- RCC for structure – BF & GF(80% completed);1st,2nd & 3rd floor (75% completed);4th& 5th floor(70% completed);6th floor(40% completed)
- Ceiling Plastering work – 1st & 2nd floor (90% completed);3rd floor (20% completed)
- Block work – 1st floor (70% completed);2nd floor (20% completed)
- Door frame fixing -1st floor – 16% completed
- Electrical chasing work – 1st floor (25% completed)
Work status as on 10-8-2017, we have completed the following.
- Piling work – completed
- Pile cap work – progressing
- BF – column work – progressing
- GF column work – progressing
Work status as on 9-6-2017, we have completed the following.
- Pile cap work -progressing
- BF – column work – progressing
Work status as on 10-5-2017, we have completed the following.
- Piling work – completed
- Pile cap work – progressing
Work status as on 8-3-2017, we have completed the following.
- Piling work – completed
- Pile cap work – progressing
- BF – column work -progressing
As per the current work status from our site we are targeted to complete the following works by end of March, 2017.