Work status as on 08-11-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A-ELITE)
- Internal Finishes Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats ,Common Area completed,Tiling – Flats 18C,5C,6C,8C 100%, common area 18 level 100% ,Staircase Handrail – Mainstair and Firestair P3 to level 10 completed,Balcony handrail-7B,3B,1A,1B,7A,1D,9B,7D,16D Completed
- Electrical, Plumbing & Firefighting works Plumbing works – Level 10D,18B,17B,18C,14D,14A concealed works & Ring main work completed. Electrical work – 8A,11A,10A,18B,17B,10D,14D,12A,16C,17C,5C,5B completed. Fire Fighting piping work up to 18th level completed, Centralised Gas piping A,B,C,D flats main riser piping work 100% completed
- External Finishes Sliding Doors and Windows – 7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed BALCONY HANDRAILS -3B,7B,7A,1A,1B,1D 7D,16D,9B,2B,3A,3D,6A,5A,15B completed.PLASTERING: A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed, External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Internal Finishes – Door frame fixtures – 100 Door frame fixtures completed Waterproofing – balconies and flats till 12th floor completed Wall tiling 3A Flat Toilet completed. Balance in progess. Flooring : 3,4 A&B,10A,7A in Progress Putty works & Painting; Flat upto 15th Floor completed Handrails; Main Stair 1 to 8 th floor completed
- External Finishes – AB External Side facing Tower A 100% completed,A Flat External Side facing Water Tank Side, B Flat Facing Swimming Pool works in progress,CD Mbed Side Plastering 100%,C Flat Left Side Mbed 20%, MEP Shaft A&B 60%, MEP Shaft C&D 10%
- Electrical, Plumbing & Firefighting works – Concealed plumbing works : 5th Floor in progress
ARTECH LIFE SPACES (TOWER C-INSPIRE)
- Internal Finishes – Door frame fixtures – (126 flats) 95% completed, Main door fixing – level 3,4,5,6,7,8 9,10 completed Putty and painting works -Level 2 to level 17 – 95% completed, level 17 -40% completed,Waterproofing (level 2 to 17) all toilets in bedrooms & balcony completed, terrace floor 98% completed,OHT – completed, podium level – 40% completed, Wall Tiling – Level 3 – level 12 – 95% completed, Level 2,,16 progressing Floor tiling – level 3 – level 12- 95% completed, Level 2,16 progressing HANDRAILS -Main stair Handrail completed,Fire stair handrail-95%completed
- Electrical, Plumbing & Firefighting works – ELECTRICAL WORKS – Level 2 to level 17 – 90% completed, PLUMBING WORKS- Concealed plumbing works – level 2 – level 17 (90% completed) Ring line 90% completed FIRE FIGHTING WORKS: Level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed,Basement -80% completed
- Final Finishes – Door shutters and iron mongery – Main door shutter & aluminium windows for lvl2, 3,4 ,5,6,7,8,9 ,10& 11 fixed Final painting – First coat painting – level 3,4,5,7,8 .9,10,11 100% completed,2,12,14 in progress ,Plumbing & sanitary ware – vertical duct lines from level 1 to 17 -70% completed ,CP Fixtures 14 flats completed ,Electrical final fixtures – switches and sockets14 flats completed Firefighting final fixtures -14 flats completed
- External Finishes – Sliding doors and windows – level 3,4,5,6,7,8,9,10,11 – 80% completed, External plastering – completed, External painting -south,east,west and north side first coat completed,light well area above lobby first coat painting completed
- Landscape Work Hardscape – planter box – 70% completed
CLUB HOUSE
- Internal Finishes – Waterproofing -100% Completed, Flooring – 90% completed, Wall tiling -100% completed, Putty works & Painting- 95% completed, Door frame fixtures-100% completed,Handrails-95% completed,Corridor Handrails-75% completed
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 98% Completed, wall and floor risers – 98% completed.
- Final Finishes – Fire fighting final fixtures -100% completed,Door shutters & ironmongery – 100%,Plumbing & Sanitaryware – 98%,Electrical final fixtures – 75%,Final Painting – 70%
- External Finishes – External Plastering – 100% completed, External Painting-50% completed, Windows & sliding door-100% completed
- Interior work – Interior ceiling work – 100% completed, Wood work – completed, Furniture -30% completed, painting (PU) – 100% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2024.
ARTECH LIFE SPACES (TOWER A-ELITE)
- Internal Finishes Tiling – 18B ,18C,5C,6C,8C to be completed
- Electrical, Plumbing & Firefighting works PLUMBING 12B,9C,10C,11C ,11B, 16C,17C,15C,12C completion , ELECTRICAL: WIRE PULLING WORKS -12B,11B,11C,15C,12C 100% FIRE: P1 Balance work, P3 – Piping work 100%.
- External Finishes Sliding Doors and Windows – 16D,7D,6B,6D,15B,10 to be completed , Balcony Handrail-2A, 2D,4A,4D,5D,6D,6B, 10B,11A, 14B, 15B 100%. Painting Works – common area painting – 66% to be completed
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Internal Finishes Door frame fixtures – 6 more Door frame fixtures to be completed, Putty and painting work 14-17 floors to be completed, Waterproofing – Remaining to be completed
- External Finishes A Flat External Side facing Water Tank Side, B Flat Facing Swimming pool to be completed
- Electrical, Plumbing & Firefighting works 6,7 & 8th Floor to be completed
ARTECH LIFE SPACES (TOWER C-INSPIRE)
- Internal Finishes Door frame fixtures – 2 doors in progress, Waterproofing -upto 18th floor to be completed Wall Tiling -in progress Floor tiling – 6A,4D,3-7 Floor based on priority HANDRAILS -WIP
- External Finishes Painting – 100 % to be completed
CLUB HOUSE
- Internal Finishes Flooring – 100% to be completed,putty works & Painting- 100% to be Completed
- Electrical, Plumbing & Firefighting works Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes Plumbing & Sanitaryware ,Electrical final fixtures ,Final Painting – 100% to be completed.
- External Finishes External Painting – 90% to be Completed.
- Interior work Furniture – 70% to be completed
- Yard Work External Infrastructure & MEP services & connections – 35% to be completed, feature wall – plastering – 100% to be completed
Work status as on 14-10-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A-ELITE)
- Internal Finishes -Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats ,Common Area completed,Tiling – Flats 4A,4D,11A,14B,17B,12A,7C completed,Staircase Handrail – Mainstair and Firestair P3 to level 7 completed,Balcony handrail-7B,3B,1A,1B,7A,1D,9B,7D,16D Completed
- Electrical, Plumbing & Firefighting works – Plumbing works – Level 10D,18B,17B,18C ,14A,14D concealed works & Ring main work completed Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), 6B,6D,8A,11A,10A,18B,17B,10D,14D,12A completed, Fire Fighting piping work up to 18th level completed, Centralised Gas piping A,B,C,D flats main riser piping work 100% completed
- External Finishes – Sliding Doors and Windows – 7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed -3B,7A,4B,7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed, BALCONY HANDRAILS -3B,7A,4B,7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed, PLASTERING: A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed, External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Civil Works- Ceiling Plastering – level 1 to 15 70% completed,17TH A,B,C,D,E&F, 18TH A,B CompletedMasonry -Block/brick -Level 1 to 18 85% completed,18F on hold. STP Plant Room completed .Inside plastering – level 1 to 15,7D,16th,17th Floor : completed
- Internal Finishes- Door frame fixtures – 100 Door frame fixtures completed, Putty and painting work – 4th to 7th floor ,13th floor completed, Waterproofing – balconies and flats till 9th floor completed
- External Finishes- AB External Side facing Tower A 100% completed,A Flat External Side facing Water Tank Side, B Flat Facing Swimming Pool works in progress
- Electrical, Plumbing & Firefighting works -Concealed plumbing works : 5th Floor in progress
ARTECH LIFE SPACES (TOWER C-INSPIRE)
- Civil Works- Ceiling Plastering – Basement ceiling – 80% completed, Level 1 100% completed, 2nd-17th level – 100% completed Masonry/Block work – level 1 -100% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 95% completed, 2nd – 17th level 100% completed.
- Internal Finishes- Door frame fixtures – (126 flats) 95% completed, Main door fixing – level 3,4,5,6,7,8 9 completed Putty and painting works -Level 2 to level 17 – 95% completed, level 17 -40% completed,Waterproofing (level 2 to 17) all toilets in bedrooms & balcony completed, terrace floor 98% completed,OHT – completed, podium level – 40% completed, Wall Tiling – Level 3 – level 12 – 95% completed, Level 2,12,14,16 progressing Floor tiling – level 3 – level 12- 95% completed, Level 2,12,14,16 progressing HANDRAILS -Main stair Handrail completed,Fire stair handrail-95%completed
- Electrical, Plumbing & Firefighting works- ELECTRICAL WORKS – Level 2 to level 17 – 90% completed, PLUMBING WORKS- Concealed plumbing works – level 2 – level 17 (90% completed) Ring line 85% completed FIRE FIGHTING WORKS: Level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed,Basement -80% completed
- Final Finishes- Door shutters and iron mongery – Main door shutter & aluminium windows for lvl 3,4 ,5,6,7,8,9 & 10 fixed Final painting – First coat painting – level 3,4,5,7,8 .9,10,11 100% completed,Plumbing & sanitary ware – vertical duct lines from level 1 to 17 -70% completed ,CP Fixtures 4 flats completed ,Electrical final fixtures – switches and sockets12 flats completed Firefighting final fixtures -12 flats completed
- External Finishes- Sliding doors and windows – level 3,4,5,6,7,8,9,10,11 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof and 1st coat painting completed
- Landscape Work – Hardscape – planter box – 50% completed
CLUB HOUSE
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed
- Internal Finishes- Waterproofing -100% Completed, Flooring – 90% completed, Wall tiling -100% completed, Putty works & Painting- 95% completed, Door frame fixtures-100% completed,Handrails-90% completed,Corridor Handrails-60% completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes- Fire fighting final fixtures -100% completed,Door shutters & ironmongery – 100%,Plumbing & Sanitaryware – 90%,Electrical final fixtures – 60%,Final Painting – 70%
- External Finishes- External Plastering – 100% completed, External Painting-50% completed, Windows & sliding door-100% completed
- Interior work- Interior ceiling work – 100% completed, Wood work – completed, Furniture -30% completed, painting (PU) – 100% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2024
ARTECH LIFE SPACES (TOWER A-ELITE)
- Internal Finishes- Tiling – 18B ,18C,5C,6C,8C to be completed
- Electrical, Plumbing & Firefighting works- PLUMBING 12B,9C,10C,11C ,11B WORK completion ,ELECTRICAL: WIRE PULLING WORKS – 6C,8C,5C,12B,11B,11C 100% .FIRE: P1 Balance work, P3 – Piping work 100%.
- External Finishes- Sliding Doors and Windows – 16D,7D,6B,6D,15B,10 to be completed, Balcony Handrails- 9B,2B 100% Painting Works – common area painting – 65% to be completed
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Civil Works- Ceiling Plastering -8TH C,D ,E&F to be completed Block work – 100% to be completed, Inside plastering – 100% to be completed
- Internal Finishes- Door frame fixtures – 6 more Door frame fixtures to be completed, Putty and painting work 14-17 floors to be completed, Waterproofing – Remaining to be completed
- External Finishes- A Flat External Side facing Water Tank Side, B Flat Facing Swimming pool to be completed
- Electrical, Plumbing & Firefighting works- 6,7 & 8th Floor to be completed
ARTECH LIFE SPACES (TOWER C-INSPIRE)
- Internal Finishes- Wall Tiling – Level 3 – level 11 – to be completed
CLUB HOUSE
- Internal Finishes- Flooring – 100% to be completed,putty works & Painting- 100% to be Completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes- Plumbing & Sanitaryware ,Electrical final fixtures ,Final Painting – 100% to be completed.
- External Finishes- External Painting – 90% to be Completed.
- Interior work – Furniture – 70% to be completed
- Yard Work- External Infrastructure & MEP services & connections – 35% to be completed, feature wall – plastering – 100% to be completed
Work status as on 12-09-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A-ELITE)
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed,Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C,7D,16D,6B,6D,10B in progress, Flats 4A,4D,11A,14B,5A,5D,6A,common area completed,Staircase Handrail – Mainstair and Firestair P3 to level 7 completed,Balcony handrail-7B,3B,1A,1B,7A,1D,9B,7D,16D Completed
- Electrical, Plumbing & Firefighting works – Plumbing works – Level 10D,18B,17B,18C concealed works & Ring main work completed Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), 6B,6D,8A,11A,10A,18B,17B completed, Fire Fighting piping work up to 18th level completed, Centralised Gas piping A,B,C,D flats main riser piping work 100% completed
- External Finishes – Sliding Doors and Windows – 7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed, BALCONY HANDRAILS -3B,7A,4B,7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed ,PLASTERING: A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed, External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Civil Works- Ceiling Plastering – level 1 to 15 70% completed,17TH A,B,C,D,E&F, 18TH A,B CompletedMasonry -Block/brick -Level 1 to 18 85% completed,18F on hold.,STP Plant Room in P3 to be started.Inside plastering – level 1 to 15,7D,16th,17th Floor : completed
- Internal Finishes- Door frame fixtures – 96 Door frame fixtures completed, Putty and painting work – 4th to 7th floor ,13th floor completed, Waterproofing – balconies and flats till 9th floor completed
- External Finishes- AB External Side facing Tower A 100% completed,A Flat External Side facing Water Tank Side, B Flat Facing Swimming Pool works in progress
- Electrical, Plumbing & Firefighting works -Concealed plumbing works : 3,4,5,6th Floor in progress
ARTECH LIFE SPACES (TOWER C-INSPIRE)
- Internal Finishes- Door frame fixtures – (126 flats) 95% completed, Main door fixing – level 3,4,5,6,7,8 9 completed Putty and painting works -Level 2 to level 17 – 95% completed, level 17 -30% completed,Waterproofing (level 2 to 17) all toilets in bedrooms & balcony completed, terrace floor 98% completed,OHT – completed, podium level – 40% completed, Wall Tiling – Level 3 – level 11 – 95% completed, Level 2,12,14,16 progressing Floor tiling – level 3 – level 11 – 95% completed, Level 2,12,14,16 progressing HANDRAILS -Main stair Handrail completed,Fire stair handrail-50%completed
- Electrical, Plumbing & Firefighting works- ELECTRICAL WORKS – Level 2 to level 17 – 90% completed, PLUMBING WORKS- Concealed plumbing works – level 2 – level 17 (90% completed) FIRE FIGHTING WORKS: Level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed,Basement -80% completed
- Final Finishes- Door shutters and iron mongery – Main door shutter & aluminium windows for lvl 3,4 ,5 & 8 fixed Final painting – First coat painting – level 3,4,5,7,8 90% completed, Plumbing & sanitary ware – vertical duct lines from level 1 to 17 -70% completed ,Electrical final fixtures – switches and sockets12 flats completed Firefighting final fixtures -9 flats completed
- External Finishes- Sliding doors and windows – level 3,4,5,6,7,8 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof and 1st coat painting completed
- Landscape Work – Hardscape – planter box – 50% completed
CLUB HOUSE
- Internal Finishes- Waterproofing -100% Completed, Flooring – 90% completed, Wall tiling -100% completed, Putty works & Painting- 90% completed, Door frame fixtures-100% completed,Handrails-90% completed,Corridor Handrails-60% completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes- Fire fighting final fixtures -100% completed,Door shutters & ironmongery – 100%,Plumbing & Sanitaryware – 90%,Electrical final fixtures – 60%,Final Painting – 70%
- External Finishes- External Plastering – 100% completed, External Painting-50% completed, Windows & sliding door-100% completed
- Interior work- Interior ceiling work – 100% completed, Wood work – completed, Furniture -30% completed, painting (PU) – 100% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2024.
ARTECH LIFE SPACES (TOWER A-ELITE)
- Internal Finishes- Tiling – 17B,18B , 12A,7C,18C to be completed
- Electrical, Plumbing & Firefighting works- PLUMBING 14A,14D WORK completion ,ELECTRICAL: CLIENT CHANGE WORKS – 10D,14D,12A wire pulling.FIRE: P1 – Piping work 100%.
- External Finishes- Sliding Doors and Windows – 16D,7D,6B,6D,15B,10 to be completed, Balcony Handrails- 9B,2B 100% Painting Works – common area painting – 65% to be completed
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Civil Works- Ceiling Plastering -8TH C,D ,E&F to be completed Block work – 100% to be completed, Inside plastering – 100% to be completed
- Internal Finishes- Door frame fixtures – 6 more Door frame fixtures to be completed, Putty and painting work 14-17 floors to be completed, Waterproofing – Remaining to be completed
- External Finishes- A Flat External Side facing Water Tank Side, B Flat Facing Swimming pool to be completed
- Electrical, Plumbing & Firefighting works- 3,4,5,6 & 7th Floor to be completed
ARTECH LIFE SPACES (TOWER C-INSPIRE)
- Internal Finishes- Wall Tiling – Level 3 – level 11 – to be completed
CLUB HOUSE
- Internal Finishes- Flooring – 100% to be completed,putty works & Painting- 100% to be Completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes- Plumbing & Sanitaryware ,Electrical final fixtures ,Final Painting – 100% to be completed.
- External Finishes- External Painting – 90% to be Completed.
- Interior work – Furniture – 70% to be completed
- Yard Work- External Infrastructure & MEP services & connections – 35% to be completed, feature wall – plastering – 100% to be completed
Work status as on 13-08-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A-ELITE)
- Civil Works-Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed,PLASTERING Internal plastering – ceiling and wall – up to 17th level completed, External plastering-Flat B and C rear side external,P1,P2 ,P3 100% Completed ,EXTERNAL PAINTING:98% First coat completed.
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed,Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed,Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C,7D,16D,6B,6D,10B in progress, 5A,5D,6A completed,Staircase Handrail – Mainstair and Firestair P3 to level 7 completed,Balcony handrail – 7B,3B,1A,1B,7A,1D Completed
- Electrical, Plumbing & Firefighting works – Plumbing works – Level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed,Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), 6B,6D Completed,Fire Fighting piping work up to 18th level completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% completed
- External Finishes – Sliding Doors and Windows – 7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed,BALCONY HANDRAILS -3B,7A,4B,7A,4B,1D,1A,1C,1B,3B,2A,2D,2B,9B completed ,PLASTERING: A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed,External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Civil Works- Ceiling Plastering – level 1 to 15 70% completed,17TH A,B,C,D,E&F, 18TH A,B Completed,Masonry -Block/brick – level 1 to 18 85% completed,18F on hold.STP Plant Room in P3 to be started,Inside plastering – level 1 to 15,7D,16th,17th Floor : completed
- Internal Finishes- Door frame fixtures – 90 Door frame fixtures completed, Putty and painting work – 3D, 11(A,C,D,E) ,11F,12(BDEF) completed,12A,12C in progress, Waterproofing – 3,4 (ABEF) completed, 4C,4D -pondingin progress
- External Finishes- AB External Side facing Tower A 90% completed, A Flat External Side facing Water Tank Side, B Flat Facing Swimming Pool works in progress
- Electrical, Plumbing & Firefighting works -Concealed plumbing works : 3AB Completed. 3(CDEF),4 th Floor in progress
ARTECH LIFE SPACES (TOWER C-INSPIRE)
- Civil Works-Ceiling Plastering – Basement ceiling – 80% completed, Level 1 100% completed, 2nd-17th level – 100% completed,Masonry/Block work – level 1 – 100% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 95% completed, 2nd – 17th level 100% completed.
- Internal Finishes- Door frame fixtures – (126 flats) 95% completed, Main door fixing – level 3,4,5,6,7,8 completed,Putty and painting works -Level 2 to level 17 – 95% completed, level 17 -30% completed, Waterproofing (level 2 to 17) all toilets in bedrooms & balcony completed, terrace floor 98% completed,OHT – completed, podium level – 40% completed, Wall Tiling – Level 3 – level 11 – 95% completed, Floor tiling – level 3 – level 12 – 95% completed,HANDRAILS -Main stair Handrail completed,Fire stair handrail-50%completed
- Electrical, Plumbing & Firefighting works- ELECTRICAL WORKS – Level 2 to level 17 – 90% completed,PLUMBING WORKS- Concealed plumbing works – level 2 – level 17 (90% completed)FIRE FIGHTING WORKS: Level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed,Basement -60% completed
- External Finishes- Sliding doors and windows – level 3,4,5,6,7,8 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof and 1st coat painting completed
- Landscape Work – Hardscape – planter box – 50% completed
CLUB HOUSE
- Civil Works- Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes- Waterproofing – 100% Completed, flooring – 90% completed, wall tiling – 100% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed,Handrails-80% completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes- Fire fighting final fixtures -100% completed,Door shutters & ironmongery – 100%,Plumbing & Sanitaryware – 90%,Electrical final fixtures – 50%,Final Painting – 50%
- External Finishes- External Plastering – 100% Completed, External Painting-50% Completed, Windows & sliding door-100% completed
- Interior work-Interior ceiling work – 100% completed, Wood work – completed, Furniture – 30% completed, painting (PU) – 100% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2024.
ARTECH LIFE SPACES (TOWER A-ELITE)
- Internal Finishes- TTiling – Flats 4A,4D,11A,14B,17B,18B , common area 18 level to be completed, Balcony handrail – 9B,7D,16D 100% to be completed
- Electrical, Plumbing & Firefighting works- PLUMBING Level 10D,18B,17B,18C concealed works completion, Ring main work. ELECTRICAL: CLIENT CHANGE WORKS – 8A,11A,10A,18B,17B wire pulling. FIRE: P1 – Piping work 100%.
- External Finishes- Sliding Doors and Windows – 16D,7D,6B,6D,15B,10 to be completed, Balcony Handrails- 9B,2B 100%,Painting Works – common area painting – 65% to be completed
ARTECH LIFE SPACES (TOWER B-FREEDOM)
- Civil Works- Ceiling Plastering -8TH C,D ,E&F to be completed,Block work – 100% to be completed,Inside plastering – 100% to be completed
- Internal Finishes- Door frame fixtures – 14 more Door frame fixtures to be completed, Putty and painting work – 4,5,6,7,13,14,16 floors to be completed, Waterproofing – balconies and flats till 9th floor to be completed
- External Finishes- AB External Side facing Tower A 100% to be completed, A Flat External Side facing Water Tank Side, B Flat Facing Swimming pool 50% to be completed
- Electrical, Plumbing & Firefighting works- 3,4,5,6 & 7th Floor to be completed
CLUB HOUSE
- Internal Finishes- Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes- Plumbing & Sanitaryware ,Electrical final fixtures ,Final Painting – 100% to be completed.
- External Finishes- External Painting – 90% to be Completed.
Work status as on 09-07-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C,7D,16D,6B,6D,10B on progress, Staircase Handrail – Mainstair and firestair P3 to level 2 completed, Balcony handrail – 7B,3B,1A,1B,7A,1D Completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 18th level completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% completed
- External Finishes – Sliding Doors and Windows – 1D,1A,1C,1B,2A,2B,9B,3B,7A,4B completed, A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
- Civil Works- Ceiling Plastering – level 1 to 15 70% completed, Masonry – Block/brick – level 1 to 18 85% completed, Inside plastering – level 1 to 15 75% completed, level 16 on progress
- Internal Finishes- Door frame fixtures – 88 Door frame fixtures completed, putty and painting work – 3D, 11(A,C,D,E) on progress, waterproofing – balconies and flats till 5th floor on progress
- External Finishes- External plastering – AB external side facing tower A 50% on progress, passage external side 100% completed
ARTECH LIFE SPACES (TOWER C)
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 100% completed, 2nd-17th level – 100% completed, Masonry/Block work – level 1 – 100% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 95% completed, 2nd – 17th level 100% completed.
- Internal Finishes- Door frame fixtures – (126 flats) 85% completed, Main door fixing – level 3,4,5,8 completed, putty and painting works – level 2 to level 16 – 95% completed, level 17 -30% completed, Waterproofing (level 3 to 17) all toilets in bedrooms & balcony completed), terrace floor 98% completed, OHT – completed, podium level – 40% completed, wall tiling – Level 3 – level 11 – 95% completed, floor tiling – level 3 – level 12 – 95% completed
- Electrical, Plumbing & Firefighting works- Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 12 (80% completed), level 14,15,16 sunken concreting completed, fire fighting work @ level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed
- Final Finishes- Door shutters and iron mongery – main door shutter & aluminium windows for lvl 3,4 & 5 fixed, Final painting – first coat painting – level 3,4,5 90% completed, plumbing & sanitary ware – vertical duct lines from level 1 to 17 on progress, Electrical final fixtures – switches and sockets for 11A fixed
- External Finishes- Sliding doors and windows – level 3,4,5,6 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof and 1st coat painting completed
- Landscape Work- Hardscape – planter box – 40% completed
CLUB HOUSE
- Structural Works- All sub-structural and structural works-completed
- Civil Works- Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes- Fire fighting final fixtures – 75% completed
- Electrical, Plumbing & Firefighting works- External Plastering – 100% Completed, External Painting-75% Completed, Windows & sliding door-85% completed
- Final Finishes- Interior ceiling work – 90% completed, wood work – completed, furniture – 20% completed, painting (PU) – 90% completed
- External Finishes- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
- Interior work-Interior ceiling work – 93% completed, wood work – completed, furniture – 30% completed, painting (PU) – 93% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2024.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes- Tiling – 5A,5D,11D, Common area 18th level tile work to be completed, Staircase Handrail – Mainstair 2nd to 6th floor 100% to be completed, Balcony handrail – 9B,7D,16D 100% to be completed
- Electrical, Plumbing & Firefighting works-Plumbing works – level 9th sunken floor and concealed work to be completed
- External Finishes- Sliding Doors and Windows – 16D,7D to be completed, Painting Works – common area painting – 30% to be completed
ARTECH LIFE SPACES (TOWER B)
- Civil Works- Ceiling Plastering – 100% to be completed, block work – 100% to be completed, Inside plastering – 100% to be completed
- Internal Finishes- Door frame fixtures – 14 more Door frame fixtures to be completed, putty and painting work – 3D, 11(A,C,D,E,F) to be completed, waterproofing – balconies and flats till 9th floor to be completed
ARTECH LIFE SPACES (TOWER C)
- Structural Works- Footing balance 9+5 to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
CLUB HOUSE
- Internal Finishes- Flooring – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes- Fire fighting final fixtures – 100% to be completed
- External Finishes-External Painting – 90% to be Completed.
- Interior work- Interior ceiling work – 100% to be completed, furniture – 70% to be completed, painting (PU) – 100% to be completed
- Yard Work- External Infrastructure & MEP services & connections – 35% to be completed, feature wall – plastering – 100% to be completed
Work status as on 11-06-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes- Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C,7D,16D,6B,6D on progress, Staircase Handrail – Mainstair and firestair P3 to level 2 completed, Balcony handrail – 7B,3B,1A,1B on progress
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 18th level completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% completed
- External Finishes- Sliding Doors and Windows – 7B,3B,7A,4B completed, A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
- Civil Works- Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed, 13(C,D,E&F), 14(A&B), 7 to 13th A &B lobby plastering completed, 14 (C,D,E &F), 15(A,B,C,D,E&F), 16 (A,B,C,D,E,F), 17 (A,B,C,D,E&F), 18(A,B,C,D) completed, Masonry – Block/brick – 3E, level 4 to 7 (A,B,E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, 4D,10(B,C,D,E&F), 11(A&B),13D Completed, 17(A,B) Completed, 5 (B, C,D),11 (C,D,E&F), 12, 13,( A,B,E&F), 13C, 7(C&D),14,15 (C,D,E,F), 17 (C,D), 18(E,F) on progress, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed, 3D, 9(A,F),10A Completed, 2(A,C&D), 9E,10F,9 (B,C,D),10F,10C,11A,2B,4B,9E,10F,9(B,C,D),10C,11A,11F, 4B, 12th floor, 13th floor, 16th floor, stair case side wall plastering till 7th floor on progress
- Internal Finishes-Door frame fixtures – 84 Door frame fixtures completed, putty and painting work – 4E&F, 3E&F, 7E&F, 8 (A,B,C,D,E&F), 1(A&B) on progress, waterproofing – balconies and flats till 5th floor on progress
- External Finishes- AB external side facing toer A 20% on progress, passage external side 35% completed
ARTECH LIFE SPACES (TOWER C)
- Ceiling Plastering – basement ceiling – 80% completed, level 1 100% completed, 2nd-17th level – 100% completed, Masonry/Block work – level 1 – 100% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 95% completed, 2nd – 17th level 100% completed.
- Internal Finishes – Door frame fixtures – (126 flats) 85% completed, Main door fixing – level 3,4,5 completed, putty and painting works – level 2 to level 16 – 95% completed, level 17 -30% completed, Waterproofing (level 3 to 17) all toilets in bedrooms & balcony completed), terrace floor 98% completed, OHT – completed, podium level – 40% completed, wall tiling – Level 3 – level 12 – 80% completed, floor tiling – level 3 – level 11 – 80% completed.
- Electrical, Plumbing & Firefighting works- Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 12 (80% completed), level 14,15,16 sunken concreting completed, fire fighting work @ level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed
- Final Finishes- Door shutters and iron mongery – main door shutter & aluminium windows for lvl 3,4 & 5 fixed, Final painting – first coat painting – 11A, 3E, 4H,4C completed, plumbing & sanitary ware – vertical duct lines from level 1 started, Electrical final fixtures – switches and sockets for 11A fixed
- External Finishes- Sliding doors and windows – level 3,4,5 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof and 1st coat painting completed
- Landscape Work- Hardscape – planter box – 40% completed
CLUB HOUSE
- Internal Finishes- Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes- Fire fighting final fixtures – 75% completed
- External Finishes- External Plastering – 100% Completed, External Painting-75% Completed, Windows & sliding door-85% completed
- Interior work- Interior ceiling work – 90% completed, wood work – completed, furniture – 20% completed, painting (PU) – 90% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes- Tiling – 10B,11D, Common area 12th level to 17th level tile work to be completed, Staircase Handrail – Mainstair 2nd to 6th floor 100% to be completed, Balcony handrail – 9B,4B,7A,7D,16D 100% to be completed
- Electrical, Plumbing & Firefighting works-Plumbing works – level 9th sunken floor and concealed work to be completed
- External Finishes- Sliding Doors and Windows – 9B,16D,7D,2B to be completed, Painting Works – common area painting – 30% to be completed
ARTECH LIFE SPACES (TOWER B)
- Civil Works- Ceiling Plastering – 18th (E,F,C,D) to be completed, block work – 18(E&F) to be completed, Inside plastering – 16th,17th,18th floor to be completed
- Internal Finishes- Door frame fixtures – 12 more Door frame fixtures to be completed, putty and painting work – 3D, 11(A,C,D,E,F) to be completed, waterproofing – balconies and flats till 9th floor to be completed
ARTECH LIFE SPACES (TOWER C)
- Structural Works- Footing balance 9+5 to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
CLUB HOUSE
- Internal Finishes- Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed, Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes- Fire fighting final fixtures – 100% to be completed
- External Finishes-External Painting – 90% to be Completed.
- Interior work- Interior ceiling work – 100% to be completed, furniture – 70% to be completed, painting (PU) – 100% to be completed
- Yard Work- External Infrastructure & MEP services & connections – 35% to be completed, feature wall – plastering – 100% to be completed.
Work status as on 09-05-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes- Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C,7D,16D on progress, Staircase Handrail – Mainstair and firestair P3 to 1st level completed, Balcony handrail – 7B,3B,1A,1B on progress
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 16th level completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% completed
- External Finishes- Sliding Doors and Windows – 7B,3B completed, A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER A)
- Civil Works- Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed, 13(C,D,E&F), 14(A&B), 7 to 13th A &B lobby plastering completed, 14 (C,D,E &F), 15(A,B,C,D,E&F), 16 (A,B,C,D,E,F), 17 (A,B,C,D,E&F), 18(A,B,C,D) completed, Masonry – Block/brick – 3E, level 4 to 7 (A,B,E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, 4D,10(B,C,D,E&F), 11(A&B),13D Completed, 17(A,B) Completed, 5 (B, C,D),11 (C,D,E&F), 12, 13,( A,B,E&F), 13C, 7(C&D),14,15 (C,D,E,F), 17 (C,D) on progress, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed, 3D, 9(A,F),10A Completed, 2(A,C&D), 9E,10F,9 (B,C,D),10F,10C,11A,2B,4B,9E,10F,9(B,C,D),10C,11A,11F, 4B, 12th floor, 13th floor, stair case side wall plastering till 7th floor on progress
- Internal Finishes-Door frame fixtures – 84 Door frame fixtures completed, putty and painting work – 4E&F, 3E&F, 7E&F, 8 (A,B,C,D,E&F), 1(A&B) on progress
- External Finishes- External plastering – AB external side facing toer A 20% on progress
ARTECH LIFE SPACES (TOWER C)
- Internal Finishes-Door frame fixtures – (126 flats) 85% completed, Main door fixing – level 3,4,5 completed, putty and painting works – level 2 to level 16 – 95% completed, level 17 -30% completed, Waterproofing (level 3 to 17) all toilets in bedrooms & balcony completed), terrace floor 98% completed, OHT – completed, podium level – 40% completed, wall tiling – Level 3 – level 11 – 80% completed, floor tiling – level 3 – level 11 – 80% completed
- Electrical, Plumbing & Firefighting works- Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 12 (80% completed), level 14,15,16 sunken concreting completed, fire fighting work @ level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed
- Final Finishes- Door shutters and iron mongery – main door shutter & aluminium windows for lvl 3,4 & 5 fixed, Final painting – first coat painting – 11A, 3E, 4H,4C completed, plumbing & sanitary ware – vertical duct lines from level 1 started, Electrical final fixtures – switches and sockets for 11A fixed
- External Finishes-Sliding doors and windows – level 3,4,5 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof and 1st coat painting completed
- Landscape Work- Hardscape – planter box – 40% completed
CLUB HOUSE
- Internal Finishes- Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes- Concealed Plumbing works- Fire fighting final fixtures – 75% completed
- External Finishes- External Plastering – 100% Completed, External Painting-75% Completed, Windows & sliding door-85% completed
- Interior work- Interior ceiling work – 90% completed, wood work – completed, furniture – 20% completed, painting (PU) – 90% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes- Tiling – 6 (A,B,C,D) toilets, floor tile work to be completed, Staircase Handrail – Mainstair 2nd to 6th floor 100% to be completed, Balcony handrail – 9B,4B,7A,7D,16D 100% to be completed
- Electrical, Plumbing & Firefighting works-Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work inside flat work 17th to 18th floor 100% to be completed
- External Finishes-Sliding Doors and Windows – 7A,4B,9B to be completed, Painting Works – common area painting – 30% to be completed
ARTECH LIFE SPACES (TOWER B)
- Civil Works- Ceiling Plastering – 18th (E,F) to be completed, block work – 18(E&F) to be completed, Inside plastering – level 2A,14th, 15th 12th,13th floor to be completed
- Internal Finishes- Door frame fixtures – 12 more Door frame fixtures to be completed, putty and painting work – 1A, 9(A,B,C,D,E&F), 10(A,C,D,E,F) to be completed
ARTECH LIFE SPACES (TOWER C)
- Structural Works- Footing balance 9+5 to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
CLUB HOUSE
- Internal Finishes- Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed, Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works-Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes- Fire fighting final fixtures – 100% to be completed
- External Finishes-External Painting – 90% to be Completed.
- Interior work- Interior ceiling work – 100% to be completed, furniture – 70% to be completed, painting (PU) – 100% to be completed
- Yard Work- External Infrastructure & MEP services & connections – 35% to be completed, feature wall – plastering – 100% to be completed
Work status as on 09-05-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes- Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C,7D,16D on progress, Staircase Handrail – Mainstair and firestair P3 to 1st level completed, Balcony handrail – 7B,3B,1A,1B on progress
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 16th level completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% completed
- External Finishes- Sliding Doors and Windows – 7B,3B completed, A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER A)
- Civil Works- Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed, 13(C,D,E&F), 14(A&B), 7 to 13th A &B lobby plastering completed, 14 (C,D,E &F), 15(A,B,C,D,E&F), 16 (A,B,C,D,E,F), 17 (A,B,C,D,E&F), 18(A,B,C,D) completed, Masonry – Block/brick – 3E, level 4 to 7 (A,B,E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, 4D,10(B,C,D,E&F), 11(A&B),13D Completed, 17(A,B) Completed, 5 (B, C,D),11 (C,D,E&F), 12, 13,( A,B,E&F), 13C, 7(C&D),14,15 (C,D,E,F), 17 (C,D) on progress, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed, 3D, 9(A,F),10A Completed, 2(A,C&D), 9E,10F,9 (B,C,D),10F,10C,11A,2B,4B,9E,10F,9(B,C,D),10C,11A,11F, 4B, 12th floor, 13th floor, stair case side wall plastering till 7th floor on progress
- Internal Finishes-Door frame fixtures – 84 Door frame fixtures completed, putty and painting work – 4E&F, 3E&F, 7E&F, 8 (A,B,C,D,E&F), 1(A&B) on progress
- External Finishes- External plastering – AB external side facing toer A 20% on progress
ARTECH LIFE SPACES (TOWER C)
- Internal Finishes-Door frame fixtures – (126 flats) 85% completed, Main door fixing – level 3,4,5 completed, putty and painting works – level 2 to level 16 – 95% completed, level 17 -30% completed, Waterproofing (level 3 to 17) all toilets in bedrooms & balcony completed), terrace floor 98% completed, OHT – completed, podium level – 40% completed, wall tiling – Level 3 – level 11 – 80% completed, floor tiling – level 3 – level 11 – 80% completed
- Electrical, Plumbing & Firefighting works- Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 12 (80% completed), level 14,15,16 sunken concreting completed, fire fighting work @ level 1 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed
- Final Finishes- Door shutters and iron mongery – main door shutter & aluminium windows for lvl 3,4 & 5 fixed, Final painting – first coat painting – 11A, 3E, 4H,4C completed, plumbing & sanitary ware – vertical duct lines from level 1 started, Electrical final fixtures – switches and sockets for 11A fixed
- External Finishes-Sliding doors and windows – level 3,4,5 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof and 1st coat painting completed
- Landscape Work- Hardscape – planter box – 40% completed
CLUB HOUSE
- Internal Finishes- Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works- Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes- Concealed Plumbing works- Fire fighting final fixtures – 75% completed
- External Finishes- External Plastering – 100% Completed, External Painting-75% Completed, Windows & sliding door-85% completed
- Interior work- Interior ceiling work – 90% completed, wood work – completed, furniture – 20% completed, painting (PU) – 90% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
- Yard Work- External Infrastructure & MEP services & connections – 20% completed, feature wall – structural work 100% completed, plastering – 50% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
ARTECH LIFE SPACES (TOWER A)
- Internal Finishes- Tiling – 6 (A,B,C,D) toilets, floor tile work to be completed, Staircase Handrail – Mainstair 2nd to 6th floor 100% to be completed, Balcony handrail – 9B,4B,7A,7D,16D 100% to be completed
- Electrical, Plumbing & Firefighting works-Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work inside flat work 17th to 18th floor 100% to be completed
- External Finishes-Sliding Doors and Windows – 7A,4B,9B to be completed, Painting Works – common area painting – 30% to be completed
ARTECH LIFE SPACES (TOWER B)
- Civil Works- Ceiling Plastering – 18th (E,F) to be completed, block work – 18(E&F) to be completed, Inside plastering – level 2A,14th, 15th 12th,13th floor to be completed
- Internal Finishes- Door frame fixtures – 12 more Door frame fixtures to be completed, putty and painting work – 1A, 9(A,B,C,D,E&F), 10(A,C,D,E,F) to be completed
ARTECH LIFE SPACES (TOWER C)
- Structural Works- Footing balance 9+5 to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
CLUB HOUSE
-
- Internal Finishes- Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed, Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works-Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes- Fire fighting final fixtures – 100% to be completed
- External Finishes-External Painting – 90% to be Completed.
- Interior work- Interior ceiling work – 100% to be completed, furniture – 70% to be completed, painting (PU) – 100% to be completed
- Yard Work- External Infrastructure & MEP services & connections – 35% to be completed, feature wall – plastering – 100% to be completed
Work status as on 09-04-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Tiling/flooring – 4B completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C completed, Staircase Handrail – Mainstair and firestair P3 to 1st level completed, Balcony handrail – 7B,3B,1A,1B 100% completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 11th level completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% completed
- External Finishes Sliding Doors and Windows – 7B,3B completed, A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Civil Works Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed, 13(C,D,E&F), 14(A&B), 7 to 13th A &B lobby plastering completed, 14 (C,D,E &F), 15( A,B,C,D,E&F), 16 (A,B,C,D,E,F) completed, Masonry – Block/brick – 3E, level 4 to 7 (A,B,E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, 4D,10(B,C,D,E&F), 11(A&B),13D Completed, 5 (B, C,D),11 (C,D,E&F), 12, 13,( A,B,E&F), 13C, 7(C&D),14,15 (C,D,E,F) on progress, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed, 3D, 9(A,F),10A Completed, 2(A,C&D), 9E,10F,9 (B,C,D),10F,10C,11A,2B,4B,9E,10F,9(B,C,D),10C,11A,11F, 4B, 12th floor, 13th floor, stair case side wall plastering till 7th floor on progress
- Internal Finishes – Door frame fixtures – 72 Door frame fixtures completed, putty and painting work – 4E&F, 3E&F on progress
ARTECH LIFE SPACES (TOWER C)
-
-
- Internal Finishes – Door frame fixtures – (126 flats) 85% completed, Main door fixing – level 3,4,5 completed, putty and painting works – level 2 to level 16 – 95% completed, Waterproofing (level 3 to 17) all toilets in bedrooms & balcony completed), terrace floor 98% completed, OHT – completed, wall tiling – Level 3 – level 11 – 80% completed, floor tiling – level 3 – level 11 – 80% completed, putty and painting – level 2 to level 16 – 95% completed
- Electrical, Plumbing & Firefighting works – Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 12 (80% completed), fire fighting work @ level 3 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed
- Final Finishes – Door shutters and iron mongery – main door shutter for lvl 3,4 & 5 fixed, Final painting – first coat painting – 11A, 3E, 4H,4C completed
- External Finishes Sliding doors and windows – level 3,4,5 – 80% completed, External plastering – completed, External painting – south, east, west & north side, light well area above lobby first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof completed
CLUB HOUSE
-
-
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed, Windows & sliding door-85% completed
- Interior work – Interior ceiling work – 90% completed, wood work – 80% completed, furniture – 20% completed, painting (PU) – 25% completed
- Yard Work External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2024.
ARTECH LIFE SPACES (TOWER A)
-
-
- Internal Finishes – Tiling – 2A,2B,2C,2D,16D,7D toilets, floor tile work to be completed, Staircase Handrail – Mainstair 2nd to 6th floor 100% to be completed, Balcony handrail – 9B,4B,7A,7D 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work inside flat work 12th to 17th floor 100% to be completed
- External Finishes – Sliding Doors and Windows – 7A,4B,9B to be completed, Painting Works – common area painting – 30% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Civil Works Ceiling Plastering – 17th, 18th (A,B,C,D,E,F) to be completed, block work – 7 (C,D), 13 (C), 15 (C,D,E,F), 16 & 17 to be completed, Inside plastering – level 2A,14th, 15th 12th,13th floor to be completed
- Internal Finishes Door frame fixtures – 24 more Door frame fixtures to be completed, putty and painting work – 7 (E&F), 8 A,B,C,D,E,F to be completed
CLUB HOUSE
-
-
- Internal Finishes – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed, Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 100% to be completed, wood work – 100% to be completed furniture – 70% to be completed, painting (PU) – 75% to be completed
- Yard Work External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 09-03-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup, 1D,7B,7A,3B,4B,9B,1A,1B,1C completed, Staircase Handrail – Mainstair and firestair P3 to 1st level completed, Balcony handrail – 7B,3B,1A,1B 100% completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 10th level completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% completed
- External Finishes – Sliding Doors and Windows – 7B,3B completed, A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Civil Works Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed, 13(C,D,E&F), 14(A&B), 7 to 13th A &B lobby plastering completed, 14 (C,D,E &F), 15( A,B,C,D,E&F), 16 (A,B,C,D,E,F) completed, Masonry – Block/brick – 3E, level 4 to 7 (E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, 4D,10(B,C,D,E&F), 11(A&B) Completed, 5 (B, C,D),11 (C,D,E&F), 12, 13,( A,B,E&F), 13 (C&D), 7A,14,15 (A,B,E,F) on progress, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed, 3D, 9 (A,F),10A Completed, 2(C&D), 9E,10F,9 (B,C,D),10F,10C,11A,2B,4B,9E,10F,9(B,C,D),10C,11A,11F, stair case side wall plastering till 7th floor on progress
- Internal Finishes Door frame fixtures – 66 Door frame fixtures completed, putty and painting work – 4E&F, 3E&F on progress
ARTECH LIFE SPACES (TOWER C)
-
-
- Civil Works Ceiling Plastering – basement ceiling – 80% completed, level 1 90% completed, 2nd-17th level – 100% completed, Masonry/Block work – level 1 – 100% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 90% completed, 2nd – 17th level 100% completed.
- Internal Finishes Door frame fixtures – (126 flats) 85% completed, Main door fixing – level 3,4,5 completed, putty and painting works – level 2 to level 16 – 95% completed, Waterproofing (level 3 to 17) all toilets in bedrooms & balcony completed), Level 16 all toilets completed, terrace floor 85% completed, OHT – completed, wall tiling – Level 3 – level 7 – 80% completed, level 8,9,10 on progress, floor tiling – level 3 – level 7 – 80% completed , level 8,9,10 on progress, putty and painting – level 2 to level 16 – 95% completed
- Electrical, Plumbing & Firefighting works Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 12 (80% completed), fire fighting work @ level 3 to level 17 fittings and pipe installation completed, vertical lines up to level 17 completed
- External Finishes Sliding doors and windows – level 3 – 70% completed, External plastering – completed, External painting – south side first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof completed
CLUB HOUSE
-
-
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.Windows & sliding door-85% completed
- Interior work – Interior ceiling work – 90% completed, wood work – 80% completed, furniture – 20% completed, painting (PU) – 25% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2024.
ARTECH LIFE SPACES (TOWER A)
-
-
- Internal Finishes – Tiling – 2A,2B,2C,2D,16D toilets tile work to be completed, Staircase Handrail – Mainstair 1st to 6th floor 100% to be completed, Balcony handrail – 9B,4B,7A 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work inside flat work 11th to 17th floor 100% to be completed
- External Finishes – Sliding Doors and Windows – 7A,4B,9B to be completed, Painting Works – common area painting – 30% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Civil Works – Ceiling Plastering – 17th, 18th (A,B,C,D) to be completed, block work – 7 (A,B,C,D), 13 (C,D), 15 (C,D,E,F), 16 & 17 to be completed, Inside plastering – level 2A,4B,12th,13th floor to be completed
- Internal Finishes – Door frame fixtures – 36 more Door frame fixtures to be completed, putty and painting work – 5 (E,F),6 (E,F), 7 (E&F) , 8 A,B,C,D,E,F to be completed
CLUB HOUSE
-
-
- Internal Finishes – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 100% to be completed, wood work – 100% to be completed furniture – 70% to be completed, painting (PU) – 75% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 10-02-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Earthwork and rock breaking – 98% completed, Retaining wall work (8m) 100% completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed.
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Sump tank completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup, 1D,7B,7A,3B,4B completed, Staircase Handrail – Mainstair and firestair P3 to 1st level completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 9th level completed, Centralised Gas piping – 1st level internal 90% completed
- External Finishes – Sliding Doors and Windows – 7B,3B completed, A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Grade slab completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Podium slab 90% completed, Roof slab – Reflective pool wall up to base of reflective pool and sitting area in reflective pool completed, Level 1 to 18 – Type A, B, C & D flats completed, Level 5 to 11 & 13,14,15,16,17 Flat ( E & F) completed
- Civil Works – Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed, 13(C,D,E&F), 14(A&B), 7 to 13th A &B lobby plastering completed, 14 C,D,E &F, 15 A,B,C,D,E&F, 16 A,B,C,D on progress, Masonry – Block/brick – 3E, level 4 to 7 (E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, 4D,10(B,C,D,E&F), 11(A&B) Completed, 5B,11 C,D,E&F, 12, 13, A,B,E&F, 13 C&D on progress, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed, 3D, 9 A,F,10A Completed, 2C&D, 9E,10F,9 B,C,D,10F,10C,11A on progress
- Internal Finishes – Door frame fixtures – 44 Door frame fixtures completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 80% completed, 2nd-17th level – 100% completed, Masonry/Block work – level 1 – 95% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 85% completed, 2nd – 17th level 100% completed.
- Internal Finishes – Door frame fixtures – (126 flats) 85% completed, Main door fixing – level 3 completed, putty and painting works – level 2 to level 15 – 95% completed, Waterproofing (level 3 to 15) all toilets in bedrooms & balcony completed), Level 16 all toilets completed, terrace floor 85% completed, OHT – completed, wall tiling – Level 3 – 95% completed, level 4 – 95% completed, level 5 – 95% completed, level 6 – 70% completed, level 7 – 40% completed, floor tiling – level 3 – 95% completed, level 4 – 95% completed, level 5 – 95% completed, level 6 – 85% completed, level 7 – 60% completed
- Electrical, Plumbing & Firefighting works – Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 11 (80% completed), fire fighting work @ level 3 to level 15 fittings and pipe installation completed, vertical lines up to level 17 completed
- External Finishes – External plastering – completed, External painting – south side first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Electrical, Plumbing & Firefighting works Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.Windows & sliding door-85% completed
- Interior work – Interior ceiling work – 80% completed, wood work – 80% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2024.
ARTECH LIFE SPACES (TOWER A)
-
-
- Internal Finishes – Tiling – 1A,1B, 1C, 2A, 7B, 2B,2C,2D,9B,16D toilets tile work to be completed, Staircase Handrail – Mainstair 1st to 6th floor 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – main riser duct piping work 9th to 17th level 100% to be completed, Centralised Gas piping – A,B,C,D flats main riser piping work 100% to be completed
- External Finishes – Sliding Doors and Windows – 7A,4B to be completed, Painting Works – 100% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 18 flat (E&F) to be completed
- Civil Works – Ceiling Plastering – 16E&F, 17th, 18th (A,B,C,D) to be completed, block work – 5 B,C,D, 7 A,B,C,D, 14,15 A,B,C,D,E&F to be completed, Inside plastering – 2A&B, 4(A,B,C,D) to be completed
- Internal Finishes – Door frame fixtures – 28 more Door frame fixtures to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footing balance 9+5 to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
CLUB HOUSE
-
-
- Internal Finishes – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 90% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 13-01-2024, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Earthwork and rock breaking – 98% completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed.
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed, Staircase Handrail – Mainstair P3 to 1st level completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed (LT), fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – first coat 98% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Podium slab pool area except STP area – 90% pool deck completed, Roof slab – Reflective pool wall up to base of reflective pool and sitting area in reflective pool completed, Level 1 to 17 – Type A, B, C & D flats completed, Level 5 to 11 & 13,14,15,16,17 Flat ( E & F) completed
- Civil Works – Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed, 13(C,D,E&F), 14(A&B), 7 to 13th A &B lobby plastering completed, Masonry – Block/brick – 3E, level 4 to 7 (E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, 4D,10(B,C,D,E&F), 11(A&B) Completed, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed, 3D, 9 A,F,10A Completed
- Internal Finishes – Door frame fixtures – 26 Door frame fixtures completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 80% completed, 2nd-17th level – 100% completed, Masonry/Block work – level 1 – 90% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 75% completed, 2nd – 17th level 100% completed.
- Internal Finishes – Door frame fixtures – (110 flats) 75% completed, Main door fixing – level 3 completed, putty and painting works – level 2 to level 15 – 95% completed, Waterproofing (level 3 to 15) all toilets in bedrooms & balcony completed), Level 16 all toilets completed, terrace floor 85% completed, OHT – completed, wall tiling – Level 3 – 95% completed, level 4 – 80% completed, level 5 – 95% completed, level 6 – 70% completed, level 7 – 40% completed, floor tiling – level 3 – 95% completed, level 4 – 95% completed, level 5 – 95% completed, level 6 – 85% completed, level 7 – 60% completed
- Electrical, Plumbing & Firefighting works – Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 11 (80% completed), fire fighting work @ level 3 to level 15 fittings and pipe installation completed, vertical lines up to level 17 completed
- External Finishes – External plastering – completed, External painting – south side first coat painting completed, east side primer and putty – 50% completed, west side primer & putty work completed, light well damp proof completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works Concealed Plumbing works- 90% Completed, wall and floor risers – 95% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.Windows & sliding door-50% completed
- Interior work – Interior ceiling work – 80% completed, wood work – 80% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2024.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Retaining wall work (8m) 100% to be completed
- Internal Finishes – Painting Works – balcony inside putty, primer work 100% to be completed, Tiling – 1A,1B, 1C, 2A, 7B to be completed, Staircase Handrail – Fire stair handrail P3 to level 1 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – main riser duct piping work 9th to 17th level 100% to be completed
- External Finishes – Painting Works – 100% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Swimming pool deck level wall and slab to be completed, podium slab pool area over STP area- concrete with pool deck wall to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, Level 18 flats (A,B,C &D) to be completed, level 18 flat (E&F) to be completed
- Civil Works – Ceiling Plastering – 14th level (C,D,E &F), 15th (A,B,C,D,E &F) plastering to be completed, block work – 5,7 (A,B,C,D), 11 (C,D,E&F), 12,13 (A,B,C,D,E&F) to be completed, Inside plastering – Level 9E,10F,9B,C,D,10F to be completed
- Internal Finishes – Door frame fixtures – 18 more Door frame fixtures to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footing balance 9+5 to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
CLUB HOUSE
-
-
- Internal Finishes – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% to be completed, wall and floor risers – 100% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 90% to be completed
- Yard Work -External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 08-12-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Earthwork and rock breaking – 98% completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed.
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed, Staircase Handrail – Mainstair P3 to 1st level completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, Machine room electrical work completed(LT), fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side completed External Painting – 90% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Podium slab pool area except STP area – 90% pool deck completed, Roof slab – Reflective pool wall up to base of reflective pool and sitting area in reflective pool completion, Level 1 to 15 – Type A, B, C & D flats completed, Level 5 to 11 & 13,14,15 Flat ( E & F) completed, Level 16 – A,B,C,D completed
- Civil Works – Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 13 (E & F) Completed 7 to 13th A &B lobby plastering completed, Masonry – Block/brick – 3E, level 4 to 7 (E & F) Completed, level 8,9 (A,B,C,D,E &F),10A completed, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed, 3C, 8 (A,B,C,D) & 7,8(E&F) completed
- Internal Finishes – Door frame fixtures – 26 Door frame fixtures completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 50% completed, 2nd-17th level – 100% completed, level 16 – 90% completed, Masonry/Block work – level 1 – 80% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 45% completed, 2nd – 17th level 100% completed.
- Internal Finishes – Door frame fixtures – (110 flats) 75% completed, Main door fixing – level 3 completed, putty and painting works – level 2 to level 14 – 95% completed, Waterproofing (level 3 to 15) all toilets in bedrooms & balcony completed), terrace floor 85% completed, OHT – 20% completed, wall tiling – Level 3 – 95% completed, level 4 – 80% completed, level 5 – 95% completed, level 6 – 50% completed, floor tiling – level 3 – 95% completed, level 4 – 95% completed, level 5 – 95% completed, level 6 – 50% completed
- Electrical, Plumbing & Firefighting works – Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 10 (80% completed), fire fighting work @ level 3 to level 12 fittings and pipe installation completed, vertical lines up to level 12 completed
- External Finishes – External plastering – completed, External painting – south side, west side primer & putty work completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed, Door frame fixtures-100% completed
- Electrical, Plumbing & Firefighting works Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.Windows & sliding door-50% completed
- Interior work – Interior ceiling work – 70% completed, wood work – 70% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Retaining wall work (8m) 100% to be completed
- Internal Finishes – Painting Works – balcony inside putty, primer work 100% to be completed, Tiling – 1A,1B, 1C, 2A, 7B to be completed, Staircase Handrail – Fire stair handrail P3 to level 1 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – main riser duct piping work 9th to 17th level 100% to be completed
- External Finishes – Painting Works – 100% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Swimming pool deck level wall and slab to be completed, podium slab pool area over STP area- concrete with pool deck wall to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, Level 17,18 flats (A,B,C &D) to be completed, level 16,17 & 18 flat (E&F) to be completed
- Civil Works Ceiling Plastering – 13th level (C,D,E &F), 14th (A,B,C,D,E &F) plastering to be completed, block work – 4D, 5,7 (A,B,C,D), 10 (B,C,D,E&F), 11,12 (A,B,C,D,E&F) to be completed, Inside plastering – Level 3D, 9,10 (A,B,C,D,E & F) to be completed
- Internal Finishes – Door frame fixtures – 18 more Door frame fixtures to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footing balance 9+5 to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
- External Finishes – External plastering – passage light well area plastering to be completed, External painting – east side damp proof coating to be completed
CLUB HOUSE
-
-
- Internal Finishes – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% to be completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 80% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 10-11-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Earthwork and rock breaking – 98% completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed.
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – 50% completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed, Staircase Handrail – Mainstair P3 to 1st level completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, fire fighting piping work up to 9th level completed.Machine room electrical work completed(LT)
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side – 95% completed External Painting – 70% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Podium slab pool area except STP area – 90% pool deck completed, Roof slab – Reflective pool wall up to base of reflective pool and sitting area in reflective pool completion, Level 1 to 15 – Type A, B, C & D flats completed, Level 5 to 11 Flat ( E & F) completed, Level 16 – A & B completed
- Civil Works – Ceiling Plastering – level 1 to 11 (A,B,C,D) and 1 to 9 (E & F) Completed 7 to 11 lobby completed, Masonry – Block/brick – 3E, level 4 to 7 (E & F) Completed, level 8 (A,B,C,D,E &F) completed, Inside plastering – level 1 (A,B,C & D) & Level 3 to 6 (E & F) completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 45% completed, 2nd-17th level – 100% completed, level 16 – 90% completed, Masonary/Block work – level 1 – 80% completed, 2nd – 17th level – 100% completed, Inside Plastering- level 1 – 25% completed, 2nd – 17th level 100% completed.
- Internal Finishes – Door frame fixtures – (110 flats) 75% completed, putty and painting works – level 2 to level 14 – 95% completed, Waterproofing (level 3 to 15) all toilets in bedrooms & balcony completed), terrace floor 85% completed, wall tiling – Level 3 – 95% completed, level 4 – 80% completed, level 5 – 65% completed, floor tiling – level 3 – 95% completed, level 4 – 80% completed, level 5 – 65% completed
- Electrical, Plumbing & Firefighting works – Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 9 (80% completed), fire fighting work @ level 3 to level 12 fittings and pipe installation completed, vertical lines up to level 12 completed
- External Finishes – External plastering – completed, External painting – south side, west side primer & putty work completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed,Door frame fixtures-100% completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes External Plastering – 100% Completed, External Painting-75% Completed. Windows & sliding door-50% completed
- Interior work – Interior ceiling work – 70% completed, wood work – 70% completed
- Yard Work -External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2023.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Sump tank of Tower A up to cover slab level wall casting to be completed
- Civil Works – Flat BC rear side 100% plastering to be completed.
- Internal Finishes – Waterproofing – Terrace level – 100% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed, Tiling – 1A,1B & 1C 2A to be completed, Staircase Handrail – Fire stair handrail P3 to level 1 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – 10th level piping, duct piping work 1st to 10th 100% to be completed,Rectification work 1st to 9th floor 100% to be completed.
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Swimming pool deck level wall and slab to be completed, podium slab pool area over STP area- concrete with pool deck wall to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 16 (C & D), level 17 flat (A&B) to be completed, Level 13 to 15 flat (E and F) to be completed, Reflective pool base and wall to be completed
- Civil Works – Ceiling Plastering – level 10 to 13 (E & F) to be completed, Level 12th,13th (A,B,C, &D) lobby plastering to be completed, block work level 9 to 11 (A,B,C,D,E & F) to be completed, Inside plastering – Level 3C & 3D, to be completed, level 8,9 (A,B,C & D) & level 7 to 9 (E &F) to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footing balance 9+5 to be completed.Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
CLUB HOUSE
-
-
- Internal Finishes – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.Hand rail works-50% to be completed
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 80% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 10-10-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Earthwork and rock breaking – 98% completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed.
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – 50% completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, fire fighting piping work up to 9th level completed.Machine room electrical work completed(LT).
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side – 95% completed External Painting – 70% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed,Podium slab pool area except STP area – 90% pool deck completed,Roof slab-Reflective pool wall up to base of reflective pool and sitting area in reflective pool completion Podium slab pool area over STP area completed, Level 1 to 14 – Type A, B, C & D flats completed, Level 5,6,7,8,9,10 Flat E & F completed, Level 15 – A & B completed ,Level-9,10 Flat E&F completed
- Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7,8,9,10,11 (A,B,C,D) and 1,2,3,4,5,6,7,8 (E & F) Completed 7,8,9 lobby completed, Masonry – Block/brick – level 2,3,6 (A,B,C,D),2E&F,3F completed, Level 4,5,6 E&F on progress ,Level 1 A,B.C,D completed level 4 D, 7 A&B on progress, Inside plastering – 3A & 3B on progress,Wall plastering 1,2 E&F completed,1A plastering on progress
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-16th level – 100% completed, level 16 – 90% completed, Masonary/Block work – level 1 – 80% completed, 2nd – 17th level-100% completed, Inside Plastering- level 1 – 25% completed, 2nd – 16th level 100% completed.
- Internal Finishes – Door frame fixtures – (110 flats) 75% completed, putty and painting works – level 2 to level 14- 95% completed, level 13-75% completed, Waterproofing (level 3,4,5,6,7,8,9,10,11,12,13,14) all toilets in bedrooms & balcony completed), terrace floor 85% completed, stair room slab and LMR slab completed, wall tiling-3H,3B completed, floor tiling – mockup completed,3B on going
- Electrical, Plumbing & Firefighting works – Electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 9 (80% completed), fire fighting work @ level 3 to level 12 fittings and pipe installation completed, vertical lines up to level 10 completed
- External Finishes – External plastering – south side completed, west side completed, East side completed, North side & light well area 50% completed, External painting – south side 2 coat damp proof and primer completed, west side – damp proof completed, primer & putty work on progress
- Yard Work – External infrastructure &MEP services & connections
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed,Door frame fixtures-100% completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes External Plastering – 100% Completed, External Painting-75% Completed.Windows & sliding door-50% completed
- Interior work – Interior ceiling work – 70% completed, wood work – 70% completed
- Yard Work -External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2023.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Sump tank of Tower A up to cover slab level wall casting to be completed
- Civil Works – Flat BC rear side 100% plastering to be completed.
- Internal Finishes – Waterproofing – Terrace level – 100% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed, Tiling – 1A,1B & 1C 2A to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – 10th level piping, duct piping work 1st to 10th 100% to be completed,Rectification work 1st to 9th floor 100% to be completed.
- External Finishes – External Plastering – Flat B & C rear side plastering 100% to be completed, Painting Works – 80% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Swimming pool deck level wall and slab to be completed, podium slab pool area over STP area- concrete with pool deck wall to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 15 C,D,level 16 flat A&B to be completed, Level 11,12 & 13 flat E and F to be completed .Reflective pool base and wall to be completed .Roof slab on level11,12&13 to be completed. Balance swimming pool deck level wall&slab completetion except STP area to be completed.
- Civil Works – Ceiling Plastering – level 12,13A,B,C,D E & F 10,11,12,13 th lobby plastering to be completed, block work for level 3E,4,5,6,7(E&F)8(A,B,C,D,E,F) (A,B,C,D) to be completed, Inside plastering -Level 3(A&B),level1(A,B,CD),level3,4,5( E&F) to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footing balance 9+5 to be completed.Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed.
- Civil Works – Ceiling Plastering- level 17 – 100% to be completed, Masonry – block/brick – level 17th 100% to be completed
CLUB HOUSE
-
-
- Internal Finishes – Flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.Hand rail works-50% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 80% to be completed, wood work – 70% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 13-09-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Earthwork and rock breaking – 90% completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed
- Internal Finishes – Waterproofing- up to 17th level completed, Terrace level – 30% completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, B & C rear side – 85% completed External Painting – 65% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed,Podium slab pool area except STP area – 90% pool deck completed, Podium slab pool area over STP area completed, Level 1 to 14 – Type A, B, C & D flats completed, Level 5,6,7,8,9,10 Flat E & F completed, Level 15 – A & B completed
- Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7,8,9,10,11 (A,B,C,D) and 1,2,3,4 (E & F) Completed, Masonry – Block/brick – level 2,3,6 (A,B,C,D) Completed, level 4 Flat A,B,C completed, Level 4D, 7 A&B on progress, Inside plastering – 3A & 3B on progress
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-15th level – 100% completed, level 16 – 90% completed, Masonary/Block work – level 1 80% completed, 2nd – 13th level-100% completed, level 14th to 16th – 100% completed, level 17 – 90% completed, Inside Plastering- level 1 – 25% completed, 2nd – 14th level 100% completed, Level 15 – 65% completed
- Internal Finishes – Door frame fixtures – (110 flats) 75% completed, putty and painting works – level 2 (75% completed), level 3 to level 12 (100% completed), level 13 – 75% completed, Waterproofing – (level 3,4,5,6,7,8,9,10,11,12 all toilets in bedrooms & balcony completed), terrace floor 55% completed, stair room slab and LMR slab completed, wall tiling – mockup completed, floor tiling – mockup completed
- Electrical, Plumbing & Firefighting works – electrical works – level 2 to level 17 – 90% completed, concealed plumbing works – level 3 – level 9 (80% completed), fire fighting work @ level 3 to level 10 fittings and pipe installation completed, vertical lines up to level 10 completed
- External Finishes – External plastering – south side completed, west side completed, East side completed, North side & light well area 10% completed, External painting – south side 2 coat damp proof and primer completed, west side – damp proof completed, primer work on progress
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
- Electrical, Plumbing & Firefighting works Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes External Plastering – 100% Completed, External Painting-75% Completed.
- Interior work – Interior ceiling work – 50% completed, wood work – 50% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – sump tank of Tower A up to cover slab level wall casting to be completed
- Internal Finishes – Waterproofing – Terrace level – 50% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed, Tiling – 1A,1B & 1C to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – 10th level piping, duct piping work 1st to 10th 100% to be completed, Electrical works lift machine room electrical work to be completed
- External Finishes – External Plastering – Flat B & C rear side plastering 100% to be completed, Painting Works – 75% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Swimming pool deck level wall and slab to be completed, podium slab pool area over STP area- concrete with pool deck wall to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 15 C,D to be completed, Level 11,12 & 13 flat E and F to be completed
- Civil Works – Ceiling Plastering – level 5,6,7,8 & 9 (E & F) to be completed, block work for level 2,3,4 (E&F), 1 (A,B,C,D) to be completed, 5,6,7 (E &F) to be completed, Inside plastering – 3 (A,B,C & D) to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed
- Civil Works Ceiling Plastering- level 17 – 100% to be completed, Masonry – block/brick – level 17th 100% to be completed
CLUB HOUSE
-
-
- Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 70% to be completed, wood work – 70% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 12-08-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Earthwork and rock breaking – 70% completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed
- Internal Finishes – Waterproofing- up to 17th level completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed except Bed 1 Toilet
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, External Painting – 60% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed,Stilt 1 – roof slab 90% completed,Podium slab pool area except STP area – 90% pool deck completed, Podium slab pool area over STP area completed, Level 1 to 14 – Type A, B, C & D flats completed, Level 5,6,7,8 Flat E & F completed
- Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7,8 (A,B,C,D) and 1 (E & F) Completed, Masonry – Block/brick – level 2,3,6 (A,B,C,D) Completed, level 4 Flat A,B,C completed, Level 4D, 7 A&B on progress
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-15th level – 100% completed, level 16 – 90% completed, Masonary/Block work – level 1 80% completed, 2nd – 13th level-100% completed, level 14th to 16th – 100% completed, level 17 – 65% completed, Inside Plastering- level 1 – 25% completed, 2nd – 12th level 100%, level 13 – 100% completed, level 14 – 45% completed
- Internal Finishes – Door frame fixtures – (106 flats) 70% completed, putty and painting works – level 2 (75% completed), level 3 to level 10 (100% completed), level 11 – 100% completed, level 12 – 100% completed, Water proofing – (level 3,4,5,6,7,8,9,10,11,12 all toilets in bedrooms & balcony completed) 95% completed, terrace floor 55% completed, stair room slab and LMR slab completed, wall tiling – mockup completed, floor tiling – mockup completed
- Electrical, Plumbing & Firefighting works – electrical works – level 2 to level 15 – 98% completed, concealed plumbing works – level 3 – level 9 (80% completed), fire fighting work @ level 3 to level 10 fittings and pipe installation completed, vertical lines up to level 10 completed
- Internal Finishes – Door frame fixtures – (106 flats) 70% completed, putty and painting works – level 2 (75% completed), level 3 to level 10 (100% completed), level 11 – 100% completed, level 12 – 100% completed, Water proofing – (level 3,4,5,6,7,8,9,10,11,12 all toilets in bedrooms & balcony completed) 95% completed, terrace floor 55% completed, stair room slab and LMR slab completed, wall tiling – mockup completed, floor tiling – mockup completed
- Electrical, Plumbing & Firefighting works – electrical works – level 2 to level 15 – 98% completed, concealed plumbing works – level 3 – level 9 (80% completed), fire fighting work @ level 3 to level 10 fittings and pipe installation completed, vertical lines up to level 10 completed
- External Finishes – External plastering – south side completed, west side completed, East side up to level 8 completed, External painting – south side 2 coat damp proof and primer completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
- Electrical, Plumbing & Firefighting works Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes External Plastering – 100% Completed, External Painting-75% Completed.
- Interior work – Interior ceiling work – 50% completed, wood work – 25% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Retaining wall 15 mtr, sump tank of Tower A up to coverslab level wall casting to be completed
- Internal Finishes – Waterproofing – 17th level 100% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – 10th level piping, duct piping work 1st to 10th 100% to be completed, Electrical works – Passenger lift and lift machine room electrical work to be completed
- External Finishes – External Plastering – Flat B & C rear side plastering 100% to be completed, Painting Works – 70% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Swimming pool deck level wall and slab to be completed, podium slab pool area over STP area- concrete with pool deck wall to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 15 A,B,C,D to be completed, Level 9,10 & 11 flat E and F to be completed
- Civil Works – Ceiling Plastering – level 2 & 3 E & F and 9 A,B,C,D to be completed, block work for level 4,5 & 7 A,B,C,D to be completed, 2E to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed
- Civil Works Ceiling Plastering- level 16 – 100% to be completed,Masonry – block/brick – level 17th 100% to be completed
CLUB HOUSE
-
-
- Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 70% to be completed, wood work – 40% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 12-07-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – completed, all slab completed – (98% of overall completed), Treated water tank of Tank A & B completed
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed, Passenger lift 2Nos: completed
- Internal Finishes – Waterproofing- up to 16th level completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed except Bed 1 Toilet
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion, M bed side, fire stair side completed, External Painting – 55% completed (putty and primer)
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Roof slab podium – 80% completed, Podium slab pool area except STP area – wall of pool deck completed, Level 1 to 13 – Type A, B, C & D flats completed, Level 5,6,7 Flat E & F completed
- Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7,8 (A,B,C,D) Completed, Masonry – Block/brick – level 2,3,6 (A ,B,C,D) Completed, level 4 Flat A,B,C completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-15th level – 100% completed, level 16 – 90% completed, Masonary/Block work – level 1 35% completed, 2nd – 13th level-100% completed, level 14th to 16th – 90% completed, level 17 – 45% completed, Inside Plastering- level 1 – 25% completed, 2nd – 12th level 100%, level 13 – 100% completed, level 14 – 35% completed
- Internal Finishes – Door frame fixtures – (106 flats) 70% completed, putty and painting works – level 2 (75% completed), level 3 to level 10 (100% completed), level 11 – 100% completed, level 12 – 75% completed, Water proofing – (level 3,4,5,6,7,8,9,10,11,12 all toilets in bedrooms & balcony completed) 95% completed, terrace floor 25% completed, stair room slab and LMR slab completed, wall tiling – mockup completed, floor tiling – mockup completed
- Electrical, Plumbing & Firefighting works – electrical works – level 2 to level 15 – 98% completed, concealed plumbing works – level 3 – level 9 (80% completed), fire fighting work @ level 3 to level 10 fittings and pipe installation completed, vertical lines up to level 10 completed
- External Finishes – External plastering – south side completed, west side 95% completed, External painting – south side 2 coat damp proof completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
- Interior work – Interior ceiling work – 50% completed, wood work – 25% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
ARTECH LIFE SPACES (TOWER A)
-
-
- Internal Finishes – Waterproofing – 17th level 100% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 9th sunken floor and concealed work to be completed, Fire fighting Work piping work – 10th level piping, duct piping work 1st to 10th 100% to be completed, Electrical works – Passenger lift and lift machine room electrical work to be completed
- External Finishes – External Plastering – Flat A,B inside parapet wall plastering, p3 columns plastering, Painting Works – 65% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Swimming pool deck level wall and slab to be completed, podium slab pool area over STP area- concrete with pool deck wall to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 14 A,B,C,D to be completed, Level 8, 9 & 10 flat E and F to be completed
- Civil Works – Ceiling Plastering – level 1,2 & 3 E & F to be completed, block work for level 4,5 & 7 A,B,C,D to be completed, 2E to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed
- Civil Works – Ceiling Plastering- level 16 – 100% to be completed,Masonry – block/brick – level 14th – 16th 100% to be completed, level 17 – 50% to be completed
CLUB HOUSE
-
-
- Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 70% to be completed, wood work – 40% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 06-06-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works- Footings – completed, all slab completed – (98% of overall completed)
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed except client change apartments, Passenger lift 2Nos: completed
- Internal Finishes – Waterproofing- up to 15th level completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed except Bed 1 Toilet
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th sunken floor work completed, concealed work of toilets – up to 8th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift, one passenger lift well electrical work completed, fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side plastering completed, B flat front portion, C flat front portion completed, External Painting – 35% completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 95% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Roof slab podium – 80% completed, Level 1 to 13 – Type A, B, C & D flats completed, Level 3,4 Flat E & F completed, STP – walls and base slab completed, cover slab – 95% completed
- Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7 (A,B,C,D) Completed, Masonry – Block/brick – level 2,3,6 (A ,B,C,D) Completed, level 4 Flat A,B,C completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 85% completed, slab completed – up to 18th level (roof slab – terrace) – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-15th level – 100% completed, level 16 – 90% completed, Masonary/Block work – level 1 35% completed, 2nd – 13th level-100% completed, level 14th to 16th – 75% completed, level 17 – 45% completed, Inside Plastering- level 1 – 25% completed, 2nd – 12th level 100%, level 13 – 100% completed, level 14 – 35% completed
- Internal Finishes – Door frame fixtures – (100 flats) 70% completed, putty and painting works – level 2 (75% completed), level 3 to level 10 (100% completed), level 11 – 90% completed, level 12 – 35% completed, Water proofing – (level 3,4,5,6,7,8,9,10,11,12 all toilets in bedrooms & balcony completed) 95% completed, terrace floor – stair room slab and LMR slab completed, wall tiling – mockup completed, floor tiling – mockup completed
- Electrical, Plumbing & Firefighting works – electrical works – level 2 to level 15 – 98% completed, concealed plumbing works – level 3 – level 8 (80% completed), fire fighting work @ level 3 to level 10 fittings and pipe installation completed, vertical lines up to level 10 completed
- External Finishes – External plastering – Flat B and C balcony area plastering completed, South side – Flat H completed, Flat A and staircase side completed, Flat A west side completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
- Interior work – Interior ceiling work – 50% completed, wood work – 25% completed
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
ARTECH LIFE SPACES (TOWER A)
-
-
- Internal Finishes – Waterproofing – 16th level 100% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 11th piping to be completed, Fire fighting Work piping work – 10th level piping, duct piping work 1st to 10th 100% to be completed, Electrical works – Passenger lift and lift machine room electrical work to be completed
- External Finishes – External Plastering – Flat A,B side design work plastering, fire stair outside etc to be completed, Painting Works – 55% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Raft slab – 100% to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 14 A,B,C,D to be completed, Level 5,6 & 7 flat E and F to be completed
- Civil Works – Ceiling Plastering – level 8th,9th level to be completed, block work for level 5,7 to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 90% to be completed
- Civil Works – Ceiling Plastering- level 16 – 100% to be completed,Masonry – block/brick – level 14th – 16th 100% to be completed, level 17 – 50% to be completed
CLUB HOUSE
-
-
- Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Interior work – Interior ceiling work – 70% to be completed, wood work – 40% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 05-05-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER-D)
-
-
- Structural Works- All sub-structural and structural works-100% completed
- Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
- Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 99% completed, Flooring – 99% completed, Putty works & Painting – 91% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 95% completed
- Final Finishes – Door shutters – 100% completed, Final Painting – 90% completed, CP & Sanitaryware – (82 flats) 60% completed, Electrical final fixtures – 88% completed, Fire fighting final fixtures – 100% completed
- External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 92% completed, Louvers/façade/wall cladding – 96% completed
- Yard Work – External Infrastructure & MEP services & connections – 96% completed
- Landscape – Hardscape – 95% completed, Landscape area – 95% completed
- Mockup – Completed.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – 100 % completed, all slab completed – (98% of overall completed), RCC of treated water tank cover slab, Fire and drinking water tank wall and cover slab, Main stair cover slab and beams, terrace parapet 100% completed , rear side RCC retaining wall (35m) completed, Tower B Sump base slab completed.
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed except client change apartments, Passenger lift 1No: completed
- Internal Finishes – Waterproofing- up to 14th level completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed, Tiling – Mockup completed except Bed 1 Toilet
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th flats sunken floor work completed, concealed work of toilets – up to 7th floor completed, Electrical work – box fixing & piping upto 17th level completed, Service lift well electrical work completed, fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side palstering completed, External Painting – 15% completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 90% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Roof slab podium – 80% completed, Level 1 to 12 – Type A, B, C & D flats completed, Level 13 Flat A & B completed, Level 2 Flat E & F completed, STP – walls and base slab completed
- Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7 (A,B,C,D) Completed, Masonry – Block/brick – level 2,3,6 (A ,B,C,D) Completed, level 4 Flat A,B,C completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 75% completed, sub structural works – 75% completed, slab completed – up to 17th level 100% Completed, 18th level (roof slab – terrace) – completed, Stair case roof slab, LMR base slab, Water Tank base slab – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-15th level, level 16 – 90% completed, Masonary/Block work – level 1 35% completed, 2nd – 13th level-100% completed, level 14th to 16th – 75% completed, level 17 – 45% completed, Inside Plastering- level 1 – 25% completed, 2nd – 12th level 100%, level 13 – 90% completed, level 14 – 20% completed
- Internal Finishes – Door frame fixtures – (100 flats) 70% completed, putty and painting works – level 2 (75% completed), level 3 to level 10 (100% completed), level 11 – 90% completed, level 12 – 10% completed, Water proofing – (level 3,4,5,6,7,8,9,10,11,12 all toilets in bedrooms & balcony completed) 95% completed, wall tiling – mockup completed, floor tiling – mockup completed
- Electrical, Plumbing & Firefighting works – electrical works – level 2 to level 15 – 98% completed, concealed plumbing works – level 3 – level 8 (80% completed), fire fighting work @ level 3 to level 10 fittings and pipe installation completed
- External Finishes – External plastering – Flat B and C balcony area plastering done from level 12 to level 1 completed, South side – (Flat H, level 1 to 17), Flat A and staircase side – level 18 – level 5 completed, Flat A west side level 17 to level 11 completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
ARTECH LIFE SPACES (TOWER-D)
-
-
- Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
- Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 97% to be completed.
- Final Finishes – Final Painting – 94% to be completed, CP and Sanitary ware – 65% to be completed, Electrical final fixtures – 100% to be completed
- External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 96% to be completed, Louvers/façade/wall cladding – 98% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 98% to be completed
- Landscape – Hardscape – 100% to be completed, Specialist works in landscape area – 100% to be completed
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Tower B – sump walls, retaining wall 10m, treated water tank A & B Sump to be completed
- Internal Finishes – Waterproofing – 15th level (A,B,C,D) 100% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 11th piping to be completed, Fire fighting Work piping work – 10th level piping, duct piping work 1st to 10th 100% to be completed, Electrical works – Passenger lift and lift machine room electrical work to be completed
- External Finishes – External Plastering – A Flat rear side 7th to 1st level, B Flat side area parapet to 1st level 100% to be completed, Painting Works – 30% to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – STP cover slab to be completed, Raft slab – 100% to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1, level 13 – C,D to be completed, Level 3, 4 Flat E & F to be completed, level 14 Flat A & B to be completed
- Civil Works – Ceiling Plastering – level 8th,9th level to be completed, block work for level 5,7 to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 80% to be completed, sub structural works – 80% to be completed
- Civil Works – Ceiling Plastering- level 16 – 100% to be completed,Masonry – block/brick – level 14th – 16th 100% to be completed, level 17 – 50% to be completed, Inside plastering – level 13th – 100% to be completed.
CLUB HOUSE
-
-
- Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes – External Painting – 90% to be Completed.
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Work status as on 08-04-2023, we have completed the following.
ARTECH LIFE SPACES (TOWER-D)
-
-
- Structural Works- All sub-structural and structural works-100% completed
- Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
- Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 99% completed, Flooring – 99% completed, Putty works & Painting – 91% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 95% completed
- Final Finishes – Door shutters – 100% completed, Final Painting – 90% completed, CP & Sanitaryware – (82 flats) 60% completed, Electrical final fixtures – 88% completed, Fire fighting final fixtures – 100% completed
- External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 92% completed, Louvers/façade/wall cladding – 96% completed
- Yard Work – External Infrastructure & MEP services & connections – 96% completed
- Landscape – Hardscape – 95% completed, Landscape area – 95% completed
- Mockup – Completed.
ARTECH LIFE SPACES (TOWER A)
-
-
- Structural Works – Footings – 100 % completed, all slab completed – (98% of overall completed), RCC of treated water tank cover slab, Fire and drinking water tank wall and cover slab, Main stair cover slab and beams, terrace parapet 100% completed , rear side RCC retaining wall (35m) completed.
- Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed except client change apartments.
- Internal Finishes – Waterproofing- up to 14th level completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats, 16th level B,C,D flats completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 8th flats sunken floor work completed, concealed work of toilets – up to 6th floor completed, Electrical work – box fixing & piping upto 17th level completed, fire fighting piping work up to 9th level completed.
- External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side m bed external plastering completed, D Flat rear side palstering completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – Footings – 95 nos completed out of 95 including lift, Raft slab completed – 90% completed, Roof slab – Stilt 2 level roof slab 90 % completed, Stilt 1 – roof slab 90% completed, Roof slab podium – 80% completed, Level 1 to 12 – Type A, B, C & D flats completed
- Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7 (A,B,C,D) Completed, Masonry – Block/brick – level 2 (A ,B,C,D) Completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Footings – 122 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 75% completed, sub structural works – 75% completed, slab completed – up to 17th level 100% Completed, 18th level (roof slab – terrace) – completed, Stair case roof slab, LMR base slab, Water Tank base slab – completed
- Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-15th level, level 16 – 90% completed, Masonary/Block work-level 1 35% completed, 2nd – 13th level-100% completed, level 14th to 16th – 75% completed, level 17 – 25% completed, Inside Plastering- level 1 – 25% completed, 2nd – 12th level 100%, level 13 – 65% completed
- Internal Finishes – Door frame fixtures – (94 flats) 70% completed, putty and painting works – level 2 (75% completed), level 3 to level 10 (100% completed), level 11 – 65% completed, Water proofing – (level 3,4,5,6,7 & 8 all toilets in bedrooms & balcony completed) 95% completed
- Electrical, Plumbing & Firefighting works – (electrical works – level 2 to level 13 – 98% completed), concealed plumbing works – level 3 – level 8 (80% completed), fire fighting work @ level 3 to level 10 fittings and pipe installation completed
- External Finishes – External plastering – Flat B and C balcony area plastering done from level 12 to level 1 completed, South side – (Flat H, level 1 to 17), Flat A and staircase side – level 18 – level 5 completed
CLUB HOUSE
-
-
- Structural Works – All sub-structural and structural works-completed
- Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
- Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
- Final Finishes – Fire fighting final fixtures – 75% completed
- External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
- Yard Work – External Infrastructure & MEP services & connections – 20% completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
ARTECH LIFE SPACES (TOWER-D)
-
-
- Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
- Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 97% to be completed.
- Final Finishes – Final Painting – 94% to be completed, CP and Sanitary ware – 65% to be completed, Electrical final fixtures – 100% to be completed
- External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 96% to be completed, Louvers/façade/wall cladding – 98% to be completed
- Yard Work – External Infrastructure & MEP services & connections – 98% to be completed
- Landscape – Hardscape – 100% to be completed, Specialist works in landscape area – 100% to be completed
ARTECH LIFE SPACES (TOWER A)
-
-
- Civil Works – Passenger lift inside plastering – 1 No: 100% to be completed
- Internal Finishes – Waterproofing – 15th level (A,B,C,D) 100% to be completed, Painting Works – balcony inside putty, primer work 100% to be completed
- Electrical, Plumbing & Firefighting works – Plumbing works – level 11th piping to be completed, Fire fighting Work piping work – duct piping work 1st to 10th 100% to be completed
- External Finishes – External Plastering – A Flat rear side 7th to 1st level, A Flat left side area parapet to 1st level 100% to be completed, Painting Works – A & D flats external putty, primer etc to be completed
ARTECH LIFE SPACES (TOWER B)
-
-
- Structural Works – STP cover slab to be completed, Raft slab – 100% to be completed, Roof slab – 100 % to be completed in stilt level 2, Roof slab – 100 % to be completed in stilt 1,level 13 – A,B,C,D to be completed, Level 2,3 E & F to be completed
- Civil Works – Ceiling Plastering – level 8th,9th level to be completed, block work for level 3,4,5,7 (A,B,C,D) to be completed
ARTECH LIFE SPACES (TOWER C)
-
-
- Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 80% to be completed, sub structural works – 80% to be completed
- Civil Works – Ceiling Plastering- level 16 – 100% to be completed,Masonry – block/brick – level 14th – 16th 100% to be completed, Inside plastering – level 13th – 100% to be completed.
CLUB HOUSE
-
-
- Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
- Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
- Final Finishes – Fire fighting final fixtures – 100% to be completed
- External Finishes –
- Yard Work – External Infrastructure & MEP services & connections – 35% to be completed
Click here to see the previous work progress updates.