Work status as on 10-10-2023, we have completed the following.
- Structural Works – All sub-structural and structural works – Completed
- Civil Works – Ceiling plastering and wall plastering, Masonry – Block/ brick, Screeding – Completed
- Internal Finishes – Main door – 99% completed, Waterproofing – 99.5% Completed, Wall tiling – 99% Completed, Flooring – 100% Completed, putty works & Painting – 95% Completed , Door frame fixtures – 100% Completed, Handrails – 100% Completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% Completed, Wall and floor services, Risers – 99% Completed, Centralised Gas piping system – 99% Completed
- Final Finishes – Door shutters & ironmongery – 95% Completed, Plumbing and Sanitary wares – 40% completed, Electrical final fixtures – 40% completed, Firefighting final fixtures – 99.5% Completed
- External Finishes – Windows & Sliding doors – 98% Completed, External Plastering – 100% Completed, External Painting – 99% Completed, Louvers/ Façade/ Wall cladding – 99% Completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2023.
- Internal Finishes – Main Door – 100% to be completed, Water Proofing – 100% to be completed, Wall tiling – 100% to be completed, Flooring – 100% to be completed, putty works and painting – 100% to be completed, Handrails – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas Piping System – 100% to be completed
- Final Finishes – Firefighting final fixtures – 100% to be completed
- External Finishes – Windows & Sliding door – 100% to be completed, External Painting – 100% to be completed, Louvres/ Façade/ Wall cladding – 100% to be completed
- Mockup – Interior work 100% to be Completed.
Work status as on 13-09-2023, we have completed the following.
- Structural Works – All sub-structural and structural works – Completed
- Civil Works – Ceiling plastering and wall plastering, Masonry – Block/ brick, Screeding – Completed
- Internal Finishes – Main door – 99% completed, Waterproofing – 99% Completed, Wall tiling – 99% Completed, Flooring – 99% Completed, putty works & Painting – 95% Completed , Door frame fixtures – 100% Completed, Handrails – 99% Completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 99% Completed, Wall and floor services, Risers – 99% Completed, Centralised Gas piping system – 99% Completed
- Final Finishes – Door shutters & ironmongery – 90% Completed, Plumbing and Sanitary wares – 35% completed, Electrical final fixtures – 30% completed, Firefighting final fixtures – 99% Completed
- External Finishes – Windows & Sliding doors – 98% Completed, External Plastering – 100% Completed, External Painting – 99% Completed, Louvers/ Façade/ Wall cladding – 99% Completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
- Internal Finishes – Main Door – 100% to be completed, Water Proofing – 100% to be completed, Wall tiling – 100% to be completed, Flooring – 100% to be completed, putty works and painting – 100% to be completed, Handrails – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas Piping System – 100% to be completed
- Final Finishes – Firefighting final fixtures – 100% to be completed
- External Finishes – Windows & Sliding door – 100% to be completed, External Painting – 100% to be completed, Louvres/ Façade/ Wall cladding – 100% to be completed
- Mockup – Interior work 100% to be Completed.
Work status as on 12-08-2023, we have completed the following.
- Structural Works – All sub-structural and structural works – Completed
- Civil Works – Ceiling plastering and wall plastering, Masonry – Block/ brick, Screeding – Completed
- Internal Finishes – Main door – 99% completed, Waterproofing – 99% Completed, Wall tiling – 99% Completed, Flooring – 99% Completed, putty works & Painting – 95% Completed , Door frame fixtures – 100% Completed, Handrails – 99% Completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 99% Completed, Wall and floor services, Risers – 99% Completed, Centralised Gas piping system – 99% Completed
- Final Finishes – Door shutters & ironmongery – 85% Completed, Firefighting final fixtures – 99% Completed
- External Finishes – Windows & Sliding doors – 98% Completed, External Plastering – 100% Completed, External Painting – 99% Completed, Louvers/ Façade/ Wall cladding – 99% Completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
- Internal Finishes – Main Door – 100% to be completed, Water Proofing – 100% to be completed, Wall tiling – 100% to be completed, Flooring – 100% to be completed, putty works and painting – 100% to be completed, Handrails – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas Piping System – 100% to be completed
- Final Finishes – Firefighting final fixtures – 100% to be completed
- External Finishes – Windows & Sliding door – 100% to be completed, External Painting – 100% to be completed, Louvres/ Façade/ Wall cladding – 100% to be completed
- Mockup – Interior work 100% to be Completed.
Work status as on 12-07-2023, we have completed the following.
- Structural Works – All sub-structural and structural works – Completed
- Civil Works – Ceiling plastering and wall plastering, Masonry – Block/ brick, Screeding – Completed
- Internal Finishes – Main door – 99% completed, Waterproofing – 99% Completed, Wall tiling – 99% Completed, Flooring – 99% Completed, putty works & Painting – 95% Completed , Door frame fixtures – 100% Completed, Handrails – 99% Completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 99% Completed, Wall and floor services, Risers – 99% Completed, Centralised Gas piping system – 99% Completed
- Final Finishes – Door shutters & ironmongery – 85% Completed, Firefighting final fixtures – 99% Completed
- External Finishes – Windows & Sliding doors – 98% Completed, External Plastering – 100% Completed, External Painting – 99% Completed, Louvers/ Façade/ Wall cladding – 99% Completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
- Internal Finishes – Main Door – 100% to be completed, Water Proofing – 100% to be completed, Wall tiling – 100% to be completed, Flooring – 100% to be completed, putty works and painting – 100% to be completed, Handrails – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas Piping System – 100% to be completed
- Final Finishes – Firefighting final fixtures – 100% to be completed
- External Finishes – Windows & Sliding door – 100% to be completed, External Painting – 100% to be completed, Louvres/ Façade/ Wall cladding – 100% to be completed
- Mockup – Interior work 100% to be Completed.
Work status as on 06-06-2023, we have completed the following.
- Structural Works – All sub-structural and structural works – Completed
- Civil Works – Ceiling plastering and wall plastering, Masonry – Block/ brick, Screeding – Completed
- Internal Finishes – Main door – 99% completed, Waterproofing – 99% Completed, Wall tiling – 99% Completed, Flooring – 99% Completed, putty works & Painting – 95% Completed , Door frame fixtures – 100% Completed, Handrails – 99% Completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 99% Completed, Wall and floor services, Risers – 98% Completed, Centralised Gas piping system – 99% Completed
- Final Finishes – Door shutters & ironmongery – 83% Completed, Firefighting final fixtures – 99% Completed
- External Finishes – Windows & Sliding doors – 97% Completed, External Plastering – 100% Completed, External Painting – 98% Completed, Louvers/ Façade/ Wall cladding – 99% Completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
- Internal Finishes – Main Door – 100% to be completed, Water Proofing – 100% to be completed, Wall tiling – 100% to be completed, Flooring – 100% to be completed, putty works and painting – 100% to be completed, Handrails – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas Piping System – 100% to be completed
- Final Finishes – Firefighting final fixtures – 100% to be completed
- External Finishes – Windows & Sliding door – 100% to be completed, External Painting – 100% to be completed, Louvres/ Façade/ Wall cladding – 100% to be completed
- Mockup – Interior work 100% to be Completed.
Work status as on 05-05-2023, we have completed the following.
- Structural Works – All sub-structural and structural works – Completed
- Civil Works – Ceiling plastering and wall plastering, Masonry – Block/ brick, Screeding – Completed
- Internal Finishes – Main door – 99% completed, Waterproofing – 99% Completed, Wall tiling – 99% Completed, Flooring – 99% Completed, putty works & Painting – 95% Completed , Door frame fixtures – 100% Completed, Handrails – 99% Completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 99% Completed, Wall and floor services, Risers – 98% Completed, Centralised Gas piping system – 99% Completed
- Final Finishes – Door shutters & ironmongery – 80% Completed, Firefighting final fixtures – 99% Completed
- External Finishes – Windows & Sliding doors – 97% Completed, External Plastering – 100% Completed, External Painting – 97% Completed, Louvers/ Façade/ Wall cladding – 98% Completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
- Internal Finishes – Main Door – 100% to be completed, Water Proofing – 100% to be completed, Wall tiling – 100% to be completed, Flooring – 100% to be completed, putty works and painting – 100% to be completed, Handrails – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas Piping System – 100% to be completed
- Final Finishes – Firefighting final fixtures – 100% to be completed
- External Finishes – Windows & Sliding door – 100% to be completed, External Painting – 100% to be completed, Louvres/ Façade/ Wall cladding – 100% to be completed
- Mockup – Interior work 100% to be Completed.
Work status as on 08-04-2023, we have completed the following.
- Structural Works – All sub-structural and structural works – Completed
- Civil Works – Ceiling plastering and wall plastering, Masonry – Block/ brick, Screeding – Completed
- Internal Finishes – Main door – 99% completed, Waterproofing – 99% Completed, Wall tiling – 99% Completed, Flooring – 99% Completed, putty works & Painting – 95% Completed , Door frame fixtures – 100% Completed, Handrails – 99% Completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 99% Completed, Wall and floor services, Risers – 98% Completed, Centralised Gas piping system – 99% Completed
- Final Finishes – Door shutters & ironmongery – 75% Completed, Firefighting final fixtures – 99% Completed
- External Finishes – Windows & Sliding doors – 96% Completed, External Plastering – 100% Completed, External Painting – 96% Completed, Louvers/ Façade/ Wall cladding – 95% Completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
- Internal Finishes – Main Door – 100% to be completed, Water Proofing – 100% to be completed, Wall tiling – 100% to be completed, Flooring – 100% to be completed, putty works and painting – 100% to be completed, Handrails – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas Piping System – 100% to be completed
- Final Finishes – Firefighting final fixtures – 100% to be completed
- External Finishes – Windows & Sliding door – 100% to be completed, External Painting – 100% to be completed, Louvres/ Façade/ Wall cladding – 97% to be completed
- Mockup – Interior work 100% to be Completed.
Click here to see the previous work progress updates.