Work status as on 12-12-2024, we have completed the following.
- Civil Works – Ceiling and wall plastering 85% completed,MASONRY WORKS, Block/ brick- Basement 1 floor 100% completed, Basement 2 floor – 100% completed,Ground floor – completed, Party area toilet block work – 100% completed Swmimming pool area toilet & pump room block work 100% completed,Block work for seater in GF landscape area – 100% completed ,GF duct brick work – completed, Inside plastering – Basement 2 inside wall plastering completed,Water tank plastering completed,Party area toilet plastering 100% completed, Swimming pool area toilet plastering – 100% completed 16th Terrace protection plastering 100% completed,Protection plastering GF yard area- 100% Protection plastering Holding tank- 100%,compound wall plastering-25%
- Internal Finishes – Main door – 82 apartments completed,Waterproofing -100% completed,Wall tiling – 81 apartments completed,Flooring – 81 apartments completed ,B1 parking tile – 70% completed ,Putty works – 100% completed ,Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed ,Main stair handrail – 60% completed, Balcony handrails – 90% completed,Parapet GI railing – 100% completed Sliding Doors and Windows -85% completed B2 Parking Tiles: 75% completed TERRACE TILING :90% completed GF Landscape Area Granite Fixing 80% completed
- Electrical, Plumbing ; Firefighting works- Concealed plumbing works – 82 nos. completed,Centralised gas piping system – 81 apartments completed, Fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, gym, association hall, lobby – 100% completed Electrical LT work – wire pulling – 90% completed, GF landscape area – 90% completed, HT work – 72 apartments completed, HVAC work – 32 apartments, lobby, games room, gym completed
- Final Finishes Final Painting 1st coat – 38 Apartments, Final Painting 2nd coat – 5 Apartments Plumbing & Sanitaryware- 8 Apartments,Electrical final fixtures- 8 apartments, Firefighting final fixtures-8 apartments ,AV room -100% , Lobby,games room ,Gym glass work -100% ,Main Door Lock Fixing – 62 Nos
- External Finishes- Windows and sliding doors – 80% completed Duct door – 90% completed External plastering – B2 & B1 floor – 95% completed, External painting – 40% completed ,Texture painting GF – 100% completed Passage SD 90% completed
- Yard Work – Fire fighting work yard area – 95% completed
- Landscape Work- Landscape work – 50% completed, civil work – 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2024.
- Civil works -Compound wall plastering-70%
- Internal Finishes Wall tiling- 1 apartment LFlooring -1 aparments, Apartment Balcony handrail- 100% ,Common Area balcony handrail-100% ,Terrace tiling -100% ,G floor landscape area granite fixing- 100% , SWIMMING POOL TILE WORK-100%
- Electrical, Plumbing & Firefighting works- Elecctrical LT work- landscape area ground floor -100%, HVAC WORK – 2 apartments
- Final Finishes – Final Painting 1st coat – 40 Apartments ,Final Painting 2ND coat – 7 Apartments, Plumbing & Sanitaryware- 10 Apartments
Electrical final fixtures-10 Apartments, Firefighting final fixtures- 10 Apartments , Main Door Lock Fixing – 80 NOS
- External Finishes- Windows and sliding doors – 90% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – 100% to be completed,
- Yard Work – Fire fighting work yard area – 100% to be completed
- Landscape Work- Landscape work – 70% to be completed
Work status as on 08-11-2024, we have completed the following.
- Internal Finishes Main door – 82 apartments completed,Waterproofing – terrace – 95% completed, GF landscape area – 95% completed,Wall tiling – 81 apartments completed Flooring – 81 apartments completed ,B1 parking tile – 70% completed ,Putty works – 100% completed ,Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed ,Main stair handrail – 60% completed, Balcony handrails – 90% completed,Parapet GI railing – 100% completed Sliding Doors and Windows -85% completed B2 Parking Tiles: 60% completed TERRACE TILING :75% completed
- GF Landscape Area Granite Fixing 75% completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 82 nos. completed,Centralised gas piping system – 74 apartments completed, Fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, gym, association hall, lobby – 100% completed Electrical LT work – wire pulling – 82 apartments completed, GF landscape area – 90% completed, HT work – 72 apartments completed, HVAC work – 32 apartments, lobby, games room, gym completed
- Final Finishes Door shutters & ironmongery – 6 apartments completed , Plumbing and Sanitarywares – 8 apartments completed,Electrical final fixtures – 8 apartments completed ,Fire final fixtures – 8 apartments completed ,Lobby and games room – 80% completed, Final painting – 38 Apartments completed Solar Panel completed AV Room completed
- External Finishes Windows and sliding doors – 80% completed Duct door – 75% completed External plastering – B2 & B1 floor – 95% completed, External painting – 40% completed ,Texture painting GF – 100% completed Passage SD 70% completed
- Yard Work Fire fighting work yard area – 85% completed
- Landscape Work Landscape work – 50% completed, civil work – 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2024.
- Internal Finishes Waterproofing – terrace 100% to be completed, GF landscape area 100% to be completed, Flooring – 1 more apartments to be completed, B1 parking tile – 90% to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 100% to be completed, Main stair handrail – 100% to be completedSliding Doors and Windows -90% to be completed B2 Parking Tiles: 100% to be completed TERRACE TILING :75% to be completed
- Electrical, Plumbing & Firefighting works Centralised gas piping system – 80 apartments to be completed, Electrical LT work – GF lndscape area 100% to be completed, HVAC work – association hall,2 apartments to be completed
- Final Finishes Door shutters & ironmongery – 10 apartments to be completed
- External Finishes Windows and sliding doors – 90% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – 100% to be completed,
- Yard Work Fire fighting work yard area – 85% to be completed
- Landscape Work Landscape work – 70% to be completed
Work status as on 14-10-2024, we have completed the following.
- Civil Works- Ceiling and wall plastering 85% completed,MASONRY WORKS, Block/ brick- Basement 1 floor 100% completed, Basement 2 floor – 100% completed,Ground floor – completed, Party area toilet block work – 100% completed Swmimming pool area toilet & pump room block work 100% completed,Block work for seater in GF landscape area – 100% completed ,GF duct brick work – completed.Inside plastering – Basement 2 inside wall plastering completed,Water tank plastering completed,Party area toilet plastering 100% completed, Swimming pool area toilet plastering – 100% completed 16th Terrace protection plastering 100% completed
- Main door – 82 apartments completed,Waterproofing – terrace – 95% completed, GF landscape area – 95% completed,Wall tiling – 80 apartments completed Flooring – 80 apartments completed ,B1 parking tile – 70% completed ,Putty works – 100% completed ,Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed ,Main stair handrail – 60% completed, Balcony handrails – 90% completed,Parapet GI railing – 100% completed Sliding Doors and Windows -85% completed B2 Parking Tiles: 60% completed TERRACE TILING :45% completed
- Electrical, Plumbing & Firefighting works-Concealed plumbing works – 82 nos. completed,Centralised gas piping system – 74 apartments completed, Fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, gym, association hall, lobby – 100% completedElectrical LT work – wire pulling – 82 apartments completed, GF landscape area – 90% completed, HT work – 72 apartments completed, HVAC work – 30 apartments, lobby, games room, gym completed
- Final Finishes – Door shutters & ironmongery – 6 apartments completed , Plumbing and Sanitarywares – sample flat, 6G, 2D,10B,3G completed,Electrical final fixtures – sample flat, 6G, 2D,10B,3G completed,Fire final fixtures – sample flat, 6G,10B,3G completed ,Lobby and games room – 35% completed, Final painting – 36Apartments completed Solar Panel 70% completed
- External Finishes- Windows and sliding doors – 80% completed Duct door – 75% completed External plastering – B2 & B1 floor – 95% completed, External painting – Primer 100% completed,Emulsion – 40% completed ,Texture painting GF – 100% completed Passage SD 70% completed
- Yard Work – Fire fighting work yard area – 80% completed
- Landscape Work- Landscape work – 50% completed, civil work – 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2024.
- Civil Works- Final Painting 1st coat – 38 APARTMENTS ,Plumbing and Sanitaryware- 10E,7A,Electrical final fixtures-10E,7A
Firefighting final fixtures- 10E,7A ,Solar panel -100% to be completed
- Internal Finishes- Waterproofing – terrace 100% to be completed, GF landscape area 100% to be completed, Flooring – 1 more apartments to be completed, B1 parking tile – 90% to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 100% to be completed, Main stair handrail – 100% to be completedSliding Doors and Windows -90% to be completed B2 Parking Tiles: 100% to be completed TERRACE TILING :75% to be completed
- Electrical, Plumbing & Firefighting works – Centralised gas piping system – 80 apartments to be completed, Electrical LT work – GF lndscape area 100% to be completed, HVAC work – association hall,2 apartments to be completed
- Final Finishes – Door shutters & ironmongery – 10 apartments to be completed
- External Finishes – Windows and sliding doors – 90% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – 100% to be completed
- Yard Work – Fire fighting work yard area – 85% to be completed
- Landscape Work – Landscape work – 70% to be completed
Work status as on 12-09-2024, we have completed the following.
- Internal Finishes – Main door – 82 apartments completed,Waterproofing – terrace – 95% completed, GF landscape area – 95% completed,Wall tiling – 79 apartments completed,Flooring – 79 apartments completed ,B1 parking tile – 70% completed ,Putty works – 100% completed ,Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed ,Main stair handrail – 60% completed, Balcony handrails – 85% completed,Parapet GI railing – 100% completed
- Electrical, Plumbing & Firefighting works-Concealed plumbing works – 81 nos. completed,Centralised gas piping system – 74 apartments completed, Fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, gym, association hall, lobby – 100% completedElectrical LT work – wire pulling – 82 apartments completed, GF landscape area – 75% completed, HT work – 72 apartments completed, HVAC work – 28 apartments, lobby, games room, gym completed
- Final Finishes – Door shutters & ironmongery – 6 apartments completed , Plumbing and Sanitarywares – sample flat, 6G, 2D,10B,3G completed,Electrical final fixtures – sample flat, 6G, 2D,10B,3G completed,Fire final fixtures – sample flat, 6G,10B,3G completed ,Lobby and games room – 35% completed, Final painting – 34 Apartments completed
- External Finishes- Windows and sliding doors – 80% completed Duct door – 75% completed External plastering – B2 & B1 floor – 95% completed, External painting – Primer 100% completed,Emulsion – 30% completed ,Texture painting GF – 100% completed
- Yard Work -Fire fighting work yard area – 80% completed
- Landscape Work – Landscape work – 40% completed, civil work – 100% completed
- Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2024.
- Internal Finishes- Waterproofing – terrace 100% to be completed, GF landscape area 100% to be completed, Flooring – 1 more apartments to be completed, B1 parking tile – 90% to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 100% to be completed, Main stair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works – Centralised gas piping system – 80 apartments to be completed, Electrical LT work – GF lndscape area 100% to be completed, HVAC work – association hall,2 apartments to be completed
- Final Finishes – Door shutters & ironmongery – 10 apartments to be completed
- External Finishes – Windows and sliding doors – 90% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – 100% to be completed
- Yard Work – Fire fighting work yard area – 85% to be completed
- Landscape Work – Landscape work – 70% to be completed
Work status as on 13-08-2024, we have completed the following.
- Civil Works- Ceiling and wall plastering 85% completed,MASONRY WORKS ,Block/ brick- Basement 1 floor 100% completed,Basement 2 floor – 100% completed,Ground floor – completed, Party area toilet block work – 100% completed Swmimming pool area toilet & pump room block work 100% completed, Block work for seater in GF landscape area – 100% completed,GF duct brick work – completed,Inside plastering – Basement 2 inside wall plastering completed,Water tank plastering completed ,Party area toilet plastering 100% completed,Swimming pool area toilet plastering – 100% completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 90% completed, GF landscape area – 95% completed,Wall tiling – 78 apartments completed,Flooring – 78 apartments completed,B1 parking tile – 70% completed,Putty works – 100% completed,Door frame fixtures- 100% completed,Handrails – fire stair handrail – 100% Completed,Main stair handrail – 60% completed,Balcony handrails – 85% completed Parapet GI railing – 100% completed
- Electrical, Plumbing & Firefighting works-Concealed plumbing works – 81 nos. completed,Centralised gas piping system – 74 apartments completed,Fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, gym, association hall, lobby – 100% completed, Electrical LT work – wire pulling – 82 apartments completed, GF landscape area – 75% completed, HT work – 72 apartments completed, HVAC work – 27 apartments, lobby, games room, gym completed.
- Final Finishes – Door shutters & ironmongery – 6 apartments completed,Plumbing and Sanitarywares – sample flat, 6G, 2D,10B completed,Electrical final fixtures – sample flat, 6G, 2D,10B completed,Fire final fixtures – sample flat, 6G,10B completed,Lobby and games room – 35% completed,Final painting – 32 Apartments completed
- External Finishes- Windows and sliding doors – 80% completed,Duct door – 75% completed,External plastering – B2 & B1 floor – 95% completed,External painting – Primer 95% completed,Emulsion – 20% completed,Texture painting GF – 90% completed
- Yard Work – Fire fighting work yard area – 70% completed
- Landscape Work -Landscape work – 15% completed, civil work – 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2024.
- Civil Works – Ceiling and wall plastering – 100% to be completed
- Internal Finishes- Waterproofing – terrace 100% to be completed, GF landscape area 100% to be completed, Flooring – 1 more apartments to be completed, B1 parking tile – 90% to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 100% to be completed, Main stair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works -Centralised gas piping system – 80 apartments to be completed, Electrical LT work – GF lndscape area 100% to be completed, HVAC work – association hall to be completed
- Final Finishes – Door shutters & ironmongery – 10 apartments to be completed
- External Finishes – Windows and sliding doors – 90% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – primer 100% to be completed, texture painting GF – 100% to be completed
- Yard Work – Fire fighting work yard area – 85% to be completed
- Landscape Work – Landscape work – 20% to be completed
Work status as on 09-07-2024, we have completed the following.
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 90% completed, GF landscape area – 95% completed, wall tiling – 78 apartments completed, flooring – 78 apartments completed, B1 parking tile – 70% completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 80% completed, parapet GI railing – 100% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 81 nos: completed, Centralised gas piping system – 74 apartments completed, fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, gym, association hall, lobby – 100% completed, Electrical LT work – wire pulling – 82 apartments completed, GF landscape area – 50% completed, HT work – 72 apartments completed, HVAC work – 27 apartments, lobby, games room, gym completed
- Final Finishes – Door shutters & ironmongery – 6 apartments completed, Plumbing and Sanitarywares – sample flat, 6G, 2D,10B completed, Electrical final fixtures – sample flat, 6G, 2D,10B completed, fire final fixtures – sample flat, 6G,10B completed, lobby and games room – 35% completed, final painting – 24 Apartments completed
- External Finishes – Windows and sliding doors – 80% completed, duct door – 75% completed, External plastering – B2 & B1 floor – 90% completed, External painting – primer 95% completed, painting – 20% completed, texture painting GF – 90% completed
- Yard Work – Fire fighting work yard area – 70% completed
- Landscape Work – Landscape work – 15% completed, civil work – 100% completed
- Mockup – Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2024.
- Internal Finishes – Waterproofing – terrace 100% to be completed, GF landscape area 100% to be completed, Flooring – 1 more apartments to be completed, B1 parking tile – 90% to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 100% to be completed, Main stair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works – Centralised gas piping system – 80 apartments to be completed, Electrical LT work – GF lndscape area 100% to be completed, HVAC work – association hall to be completed
- Final Finishes – Door shutters & ironmongery – 10 apartments to be completed
- External Finishes – Windows and sliding doors – 90% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – primer 100% to be completed, texture painting GF – 100% to be completed
- Yard Work – Fire fighting work yard area – 85% to be completed
- Landscape Work – Landscape work – 20% to be completed
Work status as on 11-06-2024, we have completed the following.
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 90% completed, GF landscape area – 95% completed, wall tiling – 77 apartments completed, flooring – 77 apartments completed, B1 parking tile – 60% completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 75% completed, parapet GI railing – 90% completed
- Electrical, Plumbing & Firefighting works -Firefighting works Concealed plumbing works – 81 nos: completed, Centralised gas piping system – 74 apartments completed, fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, Electrical LT work – wire pulling – 82 apartments completed, HT work – 72 apartments completed, HVAC work – 24 apartments completed
- Final Finishes – Door shutters & ironmongery – 6 apartments completed, Plumbing and Sanitarywares – sample flat, 6G, 2D,10B completed, Electrical final fixtures – sample flat, 6G, 2D,10B completed, fire final fixtures – sample flat, 6G,10B completed, lobby and games room – 35% completed, final painting – 18 Apartments completed
- External Finishes- Windows and sliding doors – 80% completed, duct door – 75% completed, External plastering – B2 & B1 floor – 90% completed, External painting – primer 95% completed, painting – 20% completed, texture painting GF – 75% completed
- Yard Work – Fire fighting work yard area – 50% completed
- Landscape Work -Landscape work – 10% completed, civil work – 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
- Internal Finishes – Waterproofing – terrace 100% to be completed, GF landscape area 100% to be completed, Flooring – 1 more apartments to be completed, B1 parking tile – 90% to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 80% to be completed, Main stair handrail – 100% to be completed, parapet GI railing – 100% to be completed
- Electrical, Plumbing & Firefighting works – Centralised gas piping system – 80 apartments to be completed, Electrical LT work – wire pulling gym, association hall to be completed, HVAC work – lobby, gym, association hall to be completed
- Final Finishes – Door shutters & ironmongery – 10 apartments to be completed
- External Finishes- Windows and sliding doors – 90% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – primer 100% to be completed, texture painting GF – 100% to be completed
- Yard Work – Fire fighting work yard area – 70% to be completed
- Landscape Work -Landscape work – 20% to be completed
Work status as on 09-04-2024, we have completed the following.
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 90% completed, GF landscape area – 70% completed, wall tiling – 76 apartments completed, flooring – 76 apartments completed, B1 parking tile – 30% completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 75% completed, parapet GI railing – 85% completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 81 nos: completed, Centralised gas piping system – 58 apartments completed, fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 100% Completed, Electrical LT work – wire pulling – 80 apartments completed, HT work – 72 apartments completed, HVAC work – 21 apartments completed
- Final Finishes – Door shutters & ironmongery – 6 apartments completed, Plumbing and Sanitarywares – sample flat, 6G, 2D,10B completed, Electrical final fixtures – sample flat, 6G, 2D,10B completed, fire final fixtures – sample flat, 6G,10B completed, lobby and games room – 35% completed, final painting – 5 Apartments completed
- External Finishes – Windows and sliding doors – 75% completed, duct door – 75% completed, External plastering – B2 & B1 floor – 90% completed, External painting – primer 95% completed, texture painting GF – 50% completed
- Yard Work – Fire fighting work yard area – 20% completed
- Landscape Work – Landscape work – 10% completed, civil work – 90% completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2024.
- Internal Finishes – Waterproofing – terrace 100% to be completed, GF landscape area 90% to be completed, Flooring – 1 more apartments to be completed, B1 parking tile – 60% to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 80% to be completed, Main stair handrail – 100% to be completed, parapet GI railing – 100% to be completed
- Electrical, Plumbing & Firefighting works – Centralised gas piping system – 60 apartments to be completed, Electrical LT work – wire pulling 1 more apartments to be completed, HVAC work – 23 more apartments to be completed
- Final Finishes – Door shutters & ironmongery – 10 apartments to be completed
- External Finishes Windows and sliding doors – 85% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – primer 100% to be completed, texture painting GF – 70% to be completed
- Yard Work – Fire fighting work yard area – 50% to be completed
- Landscape Work – Landscape work – 20% to be completed, Civil work – 100% to be completed
Work status as on 09-03-2024, we have completed the following.
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 90% completed, GF landscape area – 70% completed, wall tiling – 75 apartments completed, flooring – 75 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 75% completed, parapet GI railing – 85% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 81 nos: completed, Centralised gas piping system – 58 apartments completed, fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 90% Completed, Electrical LT work – wire pulling – 80 apartments completed, HT work – 72 apartments completed, HVAC work – 21 apartments completed
- Final Finishes – Door shutters & ironmongery – 6 apartments completed, Plumbing and Sanitarywares – sample flat, 6G, 2D completed, Electrical final fixtures – sample flat, 6G, 2D completed, fire final fixtures – sample flat, 6G completed, lobby and games room – 35% completed.
- External Finishes Windows and sliding doors – 75% completed, duct door – 75% completed, External plastering – B2 & B1 floor – 90% completed, External painting – primer 95% completed, texture painting GF – 25% completed
- Landscape Work – Landscape work – 10% completed, civil work – 80% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2024.
- Internal Finishes – Waterproofing – terrace 100% to be completed, GF landscape area 90% to be completed, Flooring – 1 more apartments to be completed, Wall tiling – 1 more apartments to be completed, Balcony handrail – 80% to be completed, Main stair handrail – 100% to be completed, parapet GI railing – 100% to be completed
- Electrical, Plumbing & Firefighting works – Centralised gas piping system – 60 apartments to be completed, fire fighting work – BF 1 100% to be completed, Electrical LT work – wire pulling 1 more apartments to be completed, HVAC work – 23 more apartments to be completed
- Final Finishes – Door shutters & ironmongery – 10 apartments to be completed, Plumbing and Sanitarywares – 10B to be completed, Electrical final fixtures – 10B to be completed , fire final fixtures – 10B to be completed, lobby and games room – 60% to be completed.
- External Finishes – Windows and sliding doors – 85% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – primer 100% to be completed, texture painting GF – 70% to be completed
- Landscape Work Landscape work – 20% to be completed, Civil work – 100% to be completed
Work status as on 10-02-2024, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet -completed, Ground floor parapet – completed, GF Landscape structure work – 60% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 100% completed, Ground floor – completed, GF duct brick work – completed, Inside plastering – Basement 2 inside wall plastering completed, water tank plastering completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 90% completed, GF landscape area – 50% completed, wall tiling – 74 apartments completed, flooring – 74 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 75% completed, parapet GI railing – 85% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 81 nos: completed, Centralised gas piping system – 58 apartments completed, fire fighting work – 1st to 12th floor – 100% completed, BF 1 – 60% Completed, Electrical LT work – wire pulling – 79 apartments completed, HT work – 72 apartments completed, HVAC work – 21 apartments completed
- Final Finishes – Door shutters & ironmongery – 6 apartments completed, Plumbing and Sanitary wares – sample flat, 6G, 2D completed, Electrical final fixtures – sample flat, 6G, 2D completed, fire final fixtures – sample flat, 6G, 2D completed
- External Finishes – Windows and sliding doors – 75% completed, duct door – 75% completed, External plastering – B2 & B1 floor – 90% completed. External painting – primer 95% completed
- Landscape Work – Landscape work – 10% completed
- Mockup – Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2024.
- Structural Works – Ground floor Landscape structure work – 75% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, GF landscape area 70% to be completed, Flooring – 2 more apartments to be completed, Wall tiling – 2 more apartments to be completed, Balcony handrail – 80% to be completed, Main stair handrail – 100% to be completed, parapet GI railing – 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 1 no more to be completed, Centralised gas piping system – 60 apartments to be completed, fire fighting work – BF 1 100% to be completed, Electrical LT work – wire pulling 2 more apartments to be completed, HVAC work – 23 more apartments to be completed
- Final Finishes – Plumbing and Sanitary wares – 10B to be completed, Electrical final fixtures – 10B to be completed , fire final fixtures – 10B to be completed
- External Finishes – Windows and sliding doors – 85% to be completed, Duct door – 100% to be completed, External plastering B2 & B1 floor – 100% to be completed, Painting – primer 100% to be completed
- Landscape Work – Landscape work – 20% to be completed
Work status as on 13-01-2024, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet -completed, Ground floor parapet – completed, GF Landscape structure work – 50% completed
- Civil Works Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 99% completed, Ground floor – completed, GF duct brick work – completed, Inside plastering – Basement 2 inside wall plastering completed, water tank plastering completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, GF landscape area – 40% completed, wall tiling – 72 apartments completed, flooring – 72 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 70% completed, parapet GI railing – 50% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 81 nos: completed, Centralised gas piping system – 58 apartments completed, fire fighting work – 1st to 12th floor – 100% completed, Electrical LT work – wire pulling – 79 apartments completed, HT work – 72 apartments completed, HVAC work – 19 apartments completed
- Final Finishes – Door shutters & ironmongery – sample flat, 6G completed, Plumbing and Sanitary wares – sample flat, 6G, 2D completed, Electrical final fixtures – sample flat, 6G, 2D completed
- External Finishes – Windows and sliding doors – 75% completed, duct door – 66% completed, External plastering – B2 & B1 floor – 60% completed. External painting – primer 95% completed
- Mockup Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2024.
- Structural Works – Ground floor Landscape structure work – 75% to be completed
- Civil Works Masonry – Block/Brick – basement 2 floor – 100% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, GF landscape area 60% to be completed, Flooring – 2 more apartments to be completed, Wall tiling – 2 more apartments to be completed, Balcony handrail – 80% to be completed, Main stair handrail – 100% to be completed, parapet GI railing – 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 1 no more to be completed, Centralised gas piping system – 60 apartments to be completed, Electrical LT work – wire pulling 2 more apartments to be completed
- External Finishes – Windows and sliding doors – 85% to be completed, Duct door – 75% to be completed, External plastering B2 & B1 floor – 80% to be completed, Painting – primer 100% to be completed
Work status as on 08-12-2023, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet -completed, Ground floor parapet – completed, GF Landscape structure work – 50% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 99% completed, Ground floor – completed, GF duct brick work – 20% completed, Inside plastering – Basement 2 inside wall plastering completed, water tank plastering completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, wall tiling – 72 apartments completed, flooring – 72 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 60% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 79 nos: completed, Centralised gas piping system – 46 apartments completed, fire fighting work – 1st to 11th floor – 100% completed, Electrical LT work – wire pulling – 79 apartments completed, HT work – 72 apartments completed, HVAC work – 14 apartments completed
- Final Finishes – Door shutters & ironmongery – sample flat, 6G completed, Plumbing and Sanitary wares – sample flat, 6G, 2D completed, Electrical final fixtures – sample flat, 6G, 2D completed
- External Finishes – Windows and sliding doors – 75% completed, duct door – 66% completed, External plastering – B2 & B1 floor – 40% completed. External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
- Structural Works – Ground floor Landscape structure work – 75% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, GF duct brick work – 100% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 2 more apartments to be completed, Wall tiling – 2 more apartments to be completed, Balcony handrail – 75% to be completed, Main stair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 2 nos more to be completed, Centralised gas piping system – 60 apartments to be completed, fire fighting work – 12th floor to be completed, Electrical LT work – wire pulling 2 more apartments to be completed
- External Finishes – Windows and sliding doors – 85% to be completed, Duct door – 75% to be completed, External plastering B2 & B1 floor – 80% to be completed, Painting – primer 100% to be completed
Work status as on 10-11-2023, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet – 100% completed, Ground floor parapet – completed, GF Landscape structure work – 25% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 99% completed, Ground floor – completed, Basement 2 inside wall plastering completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, wall tiling – 63 apartments completed, flooring – 62 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Main stair handrail – 60% completed, Balcony handrails – 40% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 76 nos: completed, , Centralised gas piping system – 17 apartments completed, fire fighting work – 1st to 11th floor – 100% completed, Electrical LT work – wire pulling – 68 apartments completed, HT work – 72 apartments completed, HVAC work – 14 apartments completed
- External Finishes – Windows and sliding doors – 65% completed, duct door – 66% completed, External plastering – B2 & B1 floor – 40% completed. External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2023.
- Structural Works – Ground floor Landscape structure work – 75% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed.
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 2 more apartments to be completed, Wall tiling – 2 more apartments to be completed, Balcony handrail – 60% to be completed. Main stair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 4 nos more to be completed, fire fighting work – 12th floor to be completed, Electrical LT work – wire pulling 2 more apartments to be completed
- External Finishes – Windows and sliding doors – 75% to be completed, Duct door – 75% to be completed, External plastering B2 & B1 floor – 60% to be completed. Painting – primer 100% to be completed
Work status as on 10-10-2023, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet – 100% completed, Ground floor parapet – 75% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 95% completed, Ground floor – completed, water tank plastering – 100% completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – completed, OHT – Completed, wall tiling – 62 apartments completed, flooring – 62 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Balcony handrails – 40% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 76 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 1st to 11th floor – 100% completed, Electrical LT work – wire pulling – 68 apartments completed, HT work – 72 apartments completed, HVAC work – 14 apartments completed
- External Finishes – Windows and sliding doors – 65% completed, duct door – 66% completed, External plastering – B2 & B1 floor – 25% completed. External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2023.
- Structural Works – Ground floor parapet – 100% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed. Basement 2 inside wall plastering 100% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 4 more apartments to be completed, Wall tiling – 4 more apartments to be completed, Balcony handrail – 60% to be completed. Main stair handrail – 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 4 nos more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 12th floor to be completed, Electrical LT work – wire pulling 5 more apartments to be completed
- External Finishes – Windows and sliding doors – 75% to be completed, Duct door – 75% to be completed, External plastering B2 & B1 floor – 50% to be completed. Painting – primer 100% to be completed
Work status as on 13-09-2023, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet – 99% completed, Ground floor parapet – 50% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 85% completed, Ground floor – completed, water tank plastering – 100% completed
- Internal Finishes – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – completed, OHT – Completed, wall tiling – 57 apartments completed, flooring – 56 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Balcony handrails – 25% completed
- Electrical, Plumbing & Firefighting works – Main door – 82 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – completed, OHT – Completed, wall tiling – 57 apartments completed, flooring – 56 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Balcony handrails – 25% completed
- External Finishes – Windows and sliding doors – 50% completed, duct door – 66% completed, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor parapet – 75% to be completed
- Civil Works – basement 2 level parapet – 100% to be completed, Ground floor parapet – 75% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 4 more apartments to be completed, Wall tiling – 4 more apartments to be completed, Balcony handrail – 35% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 12th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 7 more apartments to be completed
- External Finishes – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 12th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 7 more apartments to be completed
Work status as on 12-08-2023, we have completed the following.
- Structural Works – Swimming pool wall – completed, basement 2 level parapet – 95% completed, Ground floor parapet – 35% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 95% completed, water tank plastering – 100% completed
- Internal Finishes – Main door – 80 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – completed, OHT – Completed, wall tiling – 53 apartments completed, flooring – 51 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed, Balcony handrails – 15% completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 1st to 10th floor – 100% completed, Electrical LT work – wire pulling – 60 apartments completed, HT work – 66 apartments completed, HVAC work – 14 apartments completed
- External Finishes – Windows and sliding doors – 40% completed, duct door – 65% completed, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor parapet – 50% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 4 more apartments to be completed, Wall tiling – 4 more apartments to be completed, Balcony handrail – 25% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 11th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 7 more apartments to be completed
- External Finishes – Windows and sliding doors – 50% to be completed, Duct door – 75% to be completedExternal plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 12-07-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 90% completed
- Internal Finishes – Main door – 80 apartments completed, Waterproofing – terrace – 85% completed, Sump tank – 100% completed, OHT – Completed, wall tiling – 43 apartments completed, flooring – 40 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 47 apartments completed, HT work – 34 apartments completed, HVAC work – 4th floor completed
- External Finishes – Windows and sliding doors – mockup only, duct door – 50% completed, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
- Structural Works – basement 2 level parapet – 100% to be completed
- Civil Works – Masonry – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Waterproofing – terrace 100% to be completed, Flooring – 5 more apartments to be completed, Wall tiling – 7 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, fire fighting work – 11th floor to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, HVAC work – 5th floor to be completed
- External Finishes – Duct door – 75% to be completedExternal plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 06-06-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 90% completed
- Internal Finishes – Main door – 80 apartments completed, Waterproofing – terrace – 75% completed, Sump tank – 100% completed, OHT – 75% Completed, wall tiling – 43 apartments completed, flooring – 40 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 45 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
- Structural Works – basement 2 level parapet – 100% to be completed,
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Maindoor – 3 more numbers to be fixed, Waterproofing – OHT Tank – 100% to be completed, terrace 85% to be completed, Flooring – 5 more apartments to be completed, Wall tiling – 7 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Corridor handrail works – 100% to be completed, Electrical LT work – wire pulling 7 more apartments to be completed
- External Finishes – External plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 05-05-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – 90% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 80% completed
- Internal Finishes – Main door – 63 apartments completed, Waterproofing – terrace – 40% completed, Sump tank – 100% completed, wall tiling – 43 apartments completed, flooring – 37 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 40 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 95% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Maindoor – 11 more numbers to be fixed, Waterproofing – OHT Tank – 75% to be completed, terrace 75% to be completed, Flooring – 5 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6 nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed
- External Finishes – External plastering – 100% to be completed, Painting – primer 100% to be completed
Work status as on 08-04-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – 90% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 75% completed
- Internal Finishes – Main door – 56 apartments completed, Waterproofing – 15th floor – 75% completed, terrace – 40% completed, Sump tank – 75% completed, wall tiling – 43 apartments completed, flooring – 35 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 100% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 95% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 35 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 90% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Maindoor – 18 more numbers to be fixed, Waterproofing – sump tank – 100% to be completed, terrace 75% to be completed, Flooring – 5 more apartments to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed
- External Finishes – External plastering – 100% to be completed, Painting – primer 95% to be completed