Progress
We are stoked to let you know that “Artech Luxus” is now ready-to-occupy!
As per the current work status from our site we are targeted to complete the following works by end of September 2019
- Dadoing of kitchen walls: 13-15 th floor -90% completed.
- Application of putty walls & ceiling :1-18 th floor (98% to be completed).
- First coat painting :2-18 th -100% completed.
- DB Dressing and Switch Fixing :7 th -15 th floor -80% to be completed
- Flooring and skirting :4-17 th floor -100% to be completed.
- HT Electrical work:99% to be completed
- Reticulated gas work-85% to be completed
- Lift Work -100% to be completed
Work status as on 05.09.2019, we have completed the following
- Earthwork Excavations – 99% completed
- Earthwork & Backfilling work – 98% completed
- RCC for structure – completed
- Ceiling Plastering work -Completed
- Block/Brick masonry – Completed
- Dadoing of toilets: 1 st floor -70% completed ,2-7th floor (98% completed),8 th floor (85% completed),9th -98%,10 th-98%,11 th-97%,12th-98%,13 th-85%,14th -95% completed,15 th-95%,16 th -95%,17 th-95%,18-th -95%, completed.
- Dadoing of kitchen walls: 1st floor -65% completed,2-100% completed ,3-6 th -98% completed ,7 th -85% ,8 th -85% ,9-12th floor -98% ,13 th -55% ,14 th -90%,15 th -85% ,16 th -25% ,completed.
- Application of putty walls & ceiling :1-95% ,2-6 th floor (95%completed),7 th -85%,9-12 th -(98%),13 th -75%,14 th – -18 th -(98% completed.)
- First coat painting :2-15 th -98% completed ,16 th -95%,17-18 th 80% completed
- Electrical Chasing :Electrical chasing work completed
- DB Dressing and Switch Fixing :2 nd -50%,2-6 th -90%,7 th -75%,8 th -50%,12 th -25%,15 th -25% completed .
- Door frame fixing – 100% Completed
- Flooring and skirting :1-70% (,2 -7) th -98%,8 th -75%,8-12 th -(98%),13 th -75%,14 th -15 th -98%,16 th -80%,17-18 th -98% completed
- Wall plastering work – completed
- Fixing of door shutters: 1-10%,2-7th -50%,,8-18 -10% completed .
- External Plastering work -completed
- Plumbing work-completed
- Grills and handrails : Handrails completedc ,Grills upto 15th floor completed.balcony handrails : (ss frame fixing )-upto 17 th floor completed
- Common lobby work :85% completed
- Aluminium Fabrication work :1-80% (,2 -11 th )-93%,12 th -13 th -98%,16 th -80%,17-18 th -98% completed .
- HT Electrical work:95% completed
- Reticulated gas work-75 % completed
- Lift Work -2nos completed,1 Nos In progress
- Fire Work-98%completed
Work status as on 05.08.2019, we have completed the following
- Earthwork Excavations – 99% completed
- Earthwork & Backfilling work – 98% completed
- RCC for structure – completed
- Ceiling Plastering work -Completed
- Block/Brick masonry – Completed
- adoing of toilets: 1 st floor -70% completed ,2-6 th floor (95% completed),7th (90%),8 th floor (75% completed),9th -98%,10 th-95%,11 th-95%,12th-95%,13 th-75%,14th -85% completed,15 th-95%,16 th -85%,17 th-90%,18-th -95%, completed.
- Dadoing of kitchen walls: 1st floor -40% completed,2-100% completed ,3-6 th -98% completed ,7 th -85% ,8 th -75% ,9-11 th floor -95% ,13 th -55% ,14 th -70%,15 th -75% completed.
- Application of putty walls & ceiling :1-95% ,2-7 th floor (95%completed),8 th -85%,9-12 th -(95%),13 th -90%,14 th – -18 th -(95% completed.)
- First coat painting :2-12 th -90% completed ,13 th -75%,14th -90%,15-18 th -65% completed.
- DB Dressing and Switch Fixing :2 nd -80%,3rd -6th -90% 7 th floor -75% ,8 th -50%,13 th -25%,15 th -25% completed.
- Door frame fixing – 100% Completed
- Flooring and skirting :1-70% (,2 -6 th)-95%,7-90%,8th 75%,(9 th -12 th) -95%,(13 th,15 th ,18 th ) -95%,16 th -50%,17 th -90% completed.
- Wall plastering work – completed
- Fixing of door shutters: 1-10%,2-7th -50%,7 th -40%,8-18 -10% completed.
- External Plastering work -completed
- Plumbing work-completed
- Grills and handrails : Handrails completedc ,Grills upto 14th floor completed.balcony handrails : (ss frame fixing )-upto 14 th floor completed
- Aluminium Fabrication work :1-80% (,2 -10 th )-90%,11 th -80%,12 th -40%,13 th-60%,14 th -55%,15 th -45%,16-17 th -10% completed.
- LT Electrical work: 90% completed
- HT Electrical work:95% completed
- Reticulated gas work-75 % completed
- Lift Work -2nos completed,1 Nos In progress
- Fire Work-95%completed
As per the current work status from our site we are targeted to complete the following works by end of July 2019
- Dadoing of toilets: 1 -18 th floor -98% to be completed
- Dadoing of kitchen walls: 12-17 th floor -90% completed.
- Application of putty walls & ceiling :1-18 th floor (90% to be completed).
- First coat painting :2 nd -13 th floor -95% to be completed
- DB Dressing and Switch Fixing :2 nd -13 th floor -95% to be completed
- Flooring and skirting :4-17 th floor -95% to be completed .
- Aluminium Fabrication work :15-18 th floor -60% to be completed.
- HT Electrical work:75% to be completed
- Reticulated gas work-60% to be completed
- Lift Work -3 nos tobe completed
- Fire Work-70% to be completed
Work status as on 06.07.2019, we have completed the following
- Earthwork Excavations – 99% completed
- Earthwork & Backfilling work – 98% completed
- RCC for structure – completed
- Ceiling Plastering work -Completed
- Block/Brick masonry – Completed
- Dadoing of toilets: 1 st floor -70% completed ,2-6 th floor (95% completed),7-8 th floor (75% completed),9th -98%,10 th-90%,11 th-95%,12th-90%,13 th-75%,14th -85% completed,15 th-95%,16 th -75%,17 th-75%,18-th -95%, completed.
- Dadoing of kitchen walls: 1st floor -40% completed,2-100% completed ,3-6 th -98% completed ,7 th -85% ,8 th -75% ,9-11 th floor -95% ,13 th -25% ,15 th -25% completed.
- Application of putty walls & ceiling :1-10 th floor (85%completed),11,12 th -80%,13 th -90%,15 th -90%,16-18 th -75% completed.
- First coat painting :1-80%,2-7 th -90%,13 th -25% completed .
- DB Dressing and Switch Fixing :2 nd -80%,3rd -7 th -90% 13 th floor -25% completed
- Door frame fixing – 1-18th floor -100% completed,amenity block work on progressing
- Flooring and skirting :1-70% completed,2-95%,3-4 th -98%,5 th-6 th -95%,7-8 th -75%,9-12 th -95% ,13 th -75%,14 th ,15 th -95%,16-17 th -50% ,18 th -95% completed.
- Wall plastering work – completed
- Fixing of door shutters: 1-10%,2-6 th -50%,7 th -40%,8-13 -10% completed .
- External Plastering work -completed
- Plumbing -completed
- Grills and handrails : Handrails completedc ,Grills upto 14th floor completed.balcony handrails : (ss frame fixing )-upto 14 th floor completed
- Aluminium Fabrication work :1-80% ,2 -7-90%,8-10-85%,11-70%,12-35%,13-60%,14-45% completed
- LT Electrical work: 85% completed
- HT Electrical work:90% completed
- Reticulated gas work-55 % completed
- Lift Work -1 nos completed,2 Nos In progress
- Yard Work -40% completed, on progress
- Gatework -50%completed,Block work on progressing
- Fire Work-85%completed
As per the current work status from our site we are targeted to complete the following works by end of June 2019
- Dadoing of toilets: 1 st floor -90% completed ,2-6 th floor (95% completed),7-9 th floor (90% completed),10th -90%,11 th-95%,12 th-50%,13th-90%,15 th-90%,17th -90% to be completed
- Plumbing -80% to be completed
- HandrailsBalcony handrails-up to 10th floor to be completed( ss frame work only )
- Aluminium Fabrication work :1-85% ,2 to 7-95%,8 to 10-80%,11 th -70% ,12 th -50% ,13 th -70% ,14 th -40% to be completed
- HT Electrical work:75% to be completed
- Reticulated gas work-60% to be completed
- Lift Work -3 nos tobe completed
- Fire Work-70% to be completed
Work status as on 06.06.2019, we have completed the following
- Earthwork Excavations – 99% completed
- Earthwork & Backfilling work – 98% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed,second floor -completed,main building (100% completed)
- Block/Brick masonry – (Amenity block)(100% completed ),SF (97% completed),TF (95% completed) (,1st to 18th floor (99% completed)
- Dadoing of toilets: 1 st floor -70% completed ,2-6 th floor (95% completed),7-9 th floor (75% completed),10th -65%,11 th-95%,12 th-50%,13th-50%,14,15 th-75%,17th -40% completed
- Dadoing of kitchen walls: 1st floor -40% completed,2-6 th floor -90% completed,7th-80%,8-11 th -75%,13th-25%,15th-25% completed
- Application of putty walls & ceiling :1-18 th floor (75%completed)
- Door frame fixing – 1-18 th floor -100% completed,amenity block work on progressing
- Flooring and skirting :1-70%,2-6 th -95%,7th-9th -75%completed,10 th-65% completed,11 th-95%,12-13-50% completed,15 th-75%,17 th-40% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (98% completed),amenity block plastering completed
- Fixing of door shutters: 1-13th -10% completed(main doors)
- External Plastering work – 95% completed
- Putty work – 75% completed
- Plumbing -70% completed
- Handrails:Staircase handrails(100% completed),Balcony handrails-up to 7th floor completed(ss frame work only )
- Aluminium Fabrication work :1-75% ,2 to 7-90%,8 to 10-75%,11 th -60% ,12 th -25% ,13 th -50% ,14 th -25%
- LT Electrical work: 85% completed
- HT Electrical work:70% completed
- Reticulated gas work-55 % completed
- Lift Work -2 nos completed,1 Nos In progress
- Yard Work -40% completed
- Gatework -50%completed,Block work on progressing
- Fire Work-65%completed
As per the current work status from our site we are targeted to complete the following works by end of May 2019
- Dadoing of toilets: 1 st floor -90% completed ,2-6 th floor (95% completed),7-9 th floor (90% completed),10th -90%,11 th-95%,12 th-50%,13th-90%,15 th-90%,17th -90% to be completed
- Plumbing -80% to be completed
- HandrailsBalcony handrails-up to 10th floor to be completed( ss frame work only )
- Aluminium Fabrication work :1-65% ,2-7th -75%,8-10th-65%,11-14 th-65% to be completed
- HT Electrical work:75% to be completed
- Reticulated gas work-50 % to be completed
- Lift Work -3 nos tobe completed
- Fire Work-70% to be completed
Work status as on 06.05.2019, we have completed the following
- Earthwork Excavations – 99% completed
- Earthwork & Backfilling work – 98% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed,second floor -completed,main building (100% completed)
- Block/Brick masonry – (Amenity block)(100% completed ),SF (97% completed),TF (95% completed) (,1st to 18th floor (99% completed)
- Dadoing of toilets: 1 st floor -70% completed ,2-6 th floor (95% completed),7-9 th floor (75% completed),10th -65%,11 th-95%,12 th-50%,13th-50%,15 th-75%,17th -40% completed
- Dadoing of kitchen walls: 1st floor -40% completed,2-6 th floor -90% completed,7th-80%,8-11 th -75%,13th-25%,15th-25% completed
- Application of putty walls & ceiling :1-13 th floor (75%completed),14th floor -50%complteted,15th-16th-75%,17 th-50%,18th-75 % completed.
- Door frame fixing – 1-18 th floor -100% completed,amenity block work on progressing
- Flooring and skirting :1-70%,2-6 th -95%,7th-9th -75%completed,10 th-65% completed,11 th-95%,12-13-50% completed,15 th-75%,17 th-40% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (98% completed),amenity block plastering completed
- Fixing of door shutters: 1-10th -10% completed(main door s
- External Plastering work – 95% completed
- Putty work – 75% completed
- Plumbing -70% completed
- Handrails:Staircase handrails(100% completed),Balcony handrails-up to 7th floor completed(ss frame work only )
- Aluminium Fabrication work :1-50% ,2-7th -75%,8-10th-50%,11-14 th-25% completed
- LT Electrical work: 85% completed
- HT Electrical work:70% completed
- Reticulated gas work-25 % completed
- Lift Work -2 nos completed,1 Nos In progress
- Yard Work -40% completed
- Gatework -50%completed
- Fire Work-65%completed
As per the current work status from our site we are targeted to complete the following works by end of April 2019
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Ceiling Plastering work (-amenity block)Third floor -100 % to be completed
- Block/Brick masonry – BF ,FF(Amenity block)(100% completed ),SF (100 to be completed),TF (100% to be completed) (,1st to 18th floor 100% to be completed)
- Door frame fixing – amenity block(BF ,FF) -100% to becompleted
- Wall plastering work – 18th floor – 100% to be completed
- External Plastering work-100% to be completed
- Tiling Work -85 % to be completed.
- Putty work -85% to be completed
- Plumbing -85% to be completed
- Handrails:Main stair work -100% to be completed,balcony handrails(60% to be completed)
- Aluminium Fabrication work -60% to be completed
- LT Electrical work: 95% to be completed
- HT Electrical work-70% to be completed
- Reticulated gas work-50% to be completed
- Fire Work-75% to be completed
Work status as on 05.04.2019, we have completed the following
- Earthwork Excavations – 99% completed
- Earthwork & Backfilling work – 98% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed,second floor -completed,main building (100% completed)
- Block/Brick masonry – BF ,FF(Amenity block)(100% completed ),SF (97% completed),TF (95% completed) (,1st to 18th floor (99% completed)
- Door frame fixing – 1-18 th floor -99% completed,amenity block work on progressing
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (98% completed)
- External Plastering work – 95% completed
- Tiling Work – 1-12 th floor (75% completed),13 th floor on progressing
- Putty work – 75% completed
- Plumbing -70% completed
- Handrails:Staircase handrails(85% completed),Balcony handrails635%)
- Aluminium Fabrication work :40% completed
- LT Electrical work: 85% completed
- HT Electrical work:60% completed
- Reticulated gas work-25 % completed
- Fire Work-65%completed
As per the current work status from our site we are targeted to complete the following works by end of March 2019
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Door frame fixing – amenity block(BF ,FF) -100% to be completed
- Wall plastering work – 18th floor – 100% to be completed
- External Plastering work-South side (100% to be completed)
- Tiling Work -85 % to be completed.
- Putty work -80% to be completed
- Plumbing -75% to be completed
- Handrails:Main stair work -100% to be completed,balcony handrails(60% to be completed)
- Aluminium Fabrication work -60% to be completed
- LT Electrical work: 95% to be completed
- HT Electrical work-65% to be completed
- Reticulated gas work-10% to be completed
- Firework-70% to be completed
Work status as on 06-03-2019, we have completed the following
- Earthwork Excavations – 99% completed
- Earthwork & Backfilling work – 98% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed,second floor -completed
- Block/Brick masonry – BF ,FF(Amenity block)(95% completed ),1st to 18th floor (99% completed)
- Door frame fixing – 1-18 th floor -99% completed,amenity block work on progressing
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (98% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (100% completed), South side side (70% completed),
- Tiling Work – 1-11th floor (65% completed),12th floor on progressing
- Putty work – 70% completed
- Plumbing -65% completed
- Handrails:Staircase handrails(75% completed),Balcony handrails(25%)
- Aluminium Fabrication work :40% completed
- LT Electrical work: 85% completed
- HT Electrical work 55% completed
- Reticulated gas work-on progressing
- Firework-60%completed
As per the current work status from our site we are targeted to complete the following works by end of February 2019
- Earthwork Excavations – 99% to be completed
- Earthwork & Backfilling work – 98% to be completed
- Door frame fixing – amenity block(BF ,FF) -100% to be completed
- Wall plastering work – 18th floor – 100% to be completed
- External Plastering work-South side (90% to be completed)
- Tiling Work – 11 th &12th floor -50% to be completed
- Putty work -14th floor – 90% to be completed
- Handrails:Main stair work -100% to be completed
- Aluminium Fabrication work -60% to be completed
- LT Electrical work: 85% to be completed
- HT Electrical work-50% to be completed
- Reticulated gas work-10% to be completed
- Fire Work-60% to be completed
Work status as on 05-02-2019, we have completed the following
- Earthwork Excavations – 97% completed
- Earthwork & Backfilling work – 95% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed,second floor -completed
- Block/Brick masonry – BF ,FF(Amenity block)(95% completed ),1st to 18th floor (99% completed)
- Door frame fixing – 1-18 th floor -99% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (98% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (93% completed), South sideside (35% completed),
- Tiling Work – dadoing of toilets-1st floor -50%,2-7 th floor-85%,9 th floor -85%,10th floor on progressing
- Putty work – 1st to 10th floor (100% completed) ;11th floor ,12 th,13 th floor -(95%),14th floor-on progressing
- Plumbing -1-3 rd floor -100% completed,4 th to 12 th floor -99%completed,13 th to 14 th floor -98% completed,15 th floor -100% completed,16 th ,17 th floor 90% completed ,118 th floor -95% completed
- Handrails:upto terrace fire stair completed,main stair work -80%completed
- Aluminium Fabrication work :Upto 7 th floor completed(30%completed)
- LT Electrical work: 75% completed
- HT Electrical work-45% completed
- Reticulated gas work-on progressing
- Fire Work-55%completed
As per the current work status from our site we are targeted to complete the following works by end of January 2019
- Earthwork Excavations – 99% to be completed
- Earthwork & Backfilling work – 98% to be completed
- Ceiling Plastering work – Amenity Block(second floor) -100% to be completed
- Door frame fixing – 1-18 th floor -100% to becompleted
- Wall plastering work – 18th floor – 100% to be completed
- External Plastering work-East side (90% to be completed)
- flooring and skirting :10th floor – 50% to be completed
- Putty work – 11th-13th floor – 90% to be completed
- LT Electrical work: 80% to be completed
- HT Electrical work-50% to be completed
- Fire Work-55% to be completed
Work status as on 08-01-2019, we have completed the following
- Earthwork Excavations – 97% completed
- Earthwork & Backfilling work – 95% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed
- Block/Brick masonry – 1st to 18th floor (99% completed)
- Door frame fixing – 1-18 th floor -98% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (95% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (85% completed)
- Tiling Work – dadoing of toilets-1st floor -50%,2-7 th floor-85%,9 th floor -started
- flooring and skirting :1st floor -50%,2 nd to 7th floor -85%,9 th floor – on progress
- Putty work – 1st to 10th floor (100% completed) ;11th floor ,12 th,13 th floor -(75%)
- Plumbing -1-3 rd floor -100% completed,4 th to 12 th floor -99%completed,13 th to 14 th floor -98% completed,15 th floor -100% completed,16 th ,17 th floor 90% completed ,118 th floor -95% completed
- Handrails:upto terrace fire stair completed
- LT Electrical work: 70% completed
- HT Electrical work-40% completed
- Reticulated gas work-On progress
- Fire Work-50%completed
As per the current work status from our site we are targeted to complete the following works by end of December 2019
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- RCC for structure – water tank work – 100%to be completed.
- First floor -50% to be completed
- Wall plastering work – 18th floor – 100% to be completed
- Putty work – 10th floor – 100% to be completed
- Plumbing -70% to be completed
- LT Electrical work: 65% to be completed
- Fire Work-55% to be completed
Work status as on 06-12-2018, we have completed the following
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 90% completed
- RCC for structure – water tank work – 92%completed.
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor -50% completed
- Block/Brick masonry – 1st to 18th floor (99% completed)
- Door frame fixing – 97% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (50% completed); 18th floor (90% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (70% completed)
- Tiling Work – 1st floor (50% completed); 2nd floor to 7 th floor(70% completed).
- Putty work – 1st to 9th floor (100% completed) ; 10th floor (50%)
- Plumbing -60% completed
- LT Electrical work: 55% completed
- HT Electrical work-30% completed
- Reticulated gas work-On progress
- Fire Work-45%completed
As per the current work status from our site we are targeted to complete the following works by end of November 2018
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Wall plastering work – 18th floor – 100% to be completed
- Putty work – 10th floor – 100% to be completed
Work status as on 16-11-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – water tank work – progressing
- Ceiling Plastering work – Amenity Block (BF) – 100% completed
- Block/Brick masonry – 1st to 18th floor (99% completed)
- Door frame fixing – 85% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (50% completed); 18th floor (30% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (50% completed)
- Tiling Work – 1st floor (50% completed); 2nd floor (70% completed); 3rd & 4th floor (55% completed); 5th & 6th floor (50% completed)
- Putty work – 1st to 9th floor (100% completed) ; 10th floor (progrssing)
As per the current work status from our site we are targeted to complete the following works by end of July 2018
- Earthwork Excavations – 100% to be completed.
- Earthwork & Backfilling work – 100% to be completed.
- Block/Brick masonry – 17th & 18th floor – 100% to be completed.
- Door frame fixing – 17th floor – 100% to be completed.
- Wall plastering work – 12th & 13th floor – 100% to be completed.
- Putty work – 5th floor – 100% to be completed.
Work status as on 05-06-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor -100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 18th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor (99% completed);17th floor (75% completed); 18th floor (50% completed)
- Door frame fixing -1st to 16th floor – 100% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (95% completed); 13th floor (75% completed)
- External Plastering work – 2nd to 15th floor (10% completed); 16th, 17th & 18th floor (35% completed)
- Putty work – 1st & 2nd floor (50% completed); 4th floor (50% completed); 5th floor (75% completed)
As per the current work status from our site we are targeted to complete the following works by end of May 2018
- Earthwork & Backfilling work – 100% to be completed
- Ceiling plastering work – 100% to be completed
- Block/Brick masonry – 17th & 18th floor – 100% to be completed
- Door frame fixing – 16th floor – 100% to be completed
- Wall plastering work – 11th & 12th floor – 100% to be completed
- External Plastering work – 9th to 17th floor- 20% to be completed
- Putty work – 2nd floor -100% to be completed
Work status as on 05-05-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor -100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 17th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor ( 99% completed);17th floor (75% completed)
- Door frame fixing -1st to 15th floor (100% completed); 16th floor (60% completed)
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 11th floor(95% completed)
- External Plastering work – 9th to 17th floor (10% completed); 18th floor (20%)
Putty work – 1st floor – 40% completed
As per the current work status from our site we are targeted to complete the following works by end of April 2018
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Ceiling plastering work – 100% to be completed
- Block/Brick masonry – 100% to be completed
- Door frame fixing – 14th floor – 100% to be completed
- Electrical chasing work – 100% to be completed
- Wall plastering work – 4th to 9th floor – 100% to be completed
- Putty work – 1st floor -100% to be completed
- Water Proofing work – 100% to be completed
- Wire pulling work – 1st floor- 100% to be completed
- Plumbing work -1st floor- 100% to be completed
Work status as on 16-04-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor -100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 17th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor ( 99% completed);17th floor (50% completed)
- Door frame fixing -1st to 14th floor – 100% completed
- Electrical chasing work – 1st to 14th floor(100% completed)
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 10th floor(95% completed)
- Putty work – 1st floor -20% completed
- Water Proofing work – 1st floor to 5th floor (100% completed)
- Wire pulling work – 1st floor- 25% completed
- Plumbing work -1st floor-75% completed
As per the current work status from our site we are targeted to complete the following works by end of March -2018
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Ceiling plastering work – 100% to be completed
- Block/Brick masonry – 100% to be completed
- Wall plastering work – 4th to 9th floor – 100% to be completed
- Putty work – 1st floor -100% to be completed
- Electrical chasing work – 12th floor – 100% to be completed
- Wire pulling work – 1st floor- 100% to be completed
- Door frame fixing – 14th floor – 100% to be completed
- Water Proofing work – 2nd & 3rd floor – 100% to be completed
- Plumbing work -1st floor- 100% to be completed
Work status as on 1 3 -0 3 -2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor 100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 17th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor( 99% completed)
- Wall plastering work – 1st to 3rd floor (100% completed);4th to 9th floor(95% completed)
- Putty work – 1st floor -20% completed
- Electrical chasing work – 1st to 10th floor(100% completed);11th floor (100% completed);12th floor (75% completed);13th floor(25% completed)
- Wire pulling work – 1st floor- 25% completed
- Door frame fixing -1st to 13th floor – 100% completed
- Water Proofing work – 1st floor (95% completed); 2nd & 3rd floor (50% completed)
- Plumbing work -1st floor-75% completed
Work status as on 9-5-2017, we have completed
- Earthwork & Backfilling work – progressing
- RCC for structure – 12th floor progressing
- Ceiling Plastering work -progressing
- Block/Brick masonry – progressing
- Wall plastering work – 1st floor – progressing
Work status as on 8-3-2017, we have completed
- RCC for structure – 11th floor – progressing
- Ceiling Plastering work – progressing
- Block/Brick masonry -progressing
Work status as on 8-2-2017, we have completed
- Earthwork Excavations – progressing
- RCC for structure – 10th floor – progressing
- Ceiling Plastering work – progressing
As per the current work status from our site we are targeted to complete the following works by end of February, 2017.
Work status as on 06-5-2016, we have completed
- Earthwork Excavations – completed
- RCC for structure – 3rd floor – completed
Work status as on 06-03-2015, we have completed
27 nos of Piling works out of 101 and expected to complete 20 nos more out 101 by next month.
You must be logged in to post a comment.