Progress
As per the current work status from our site we are targeted to complete the following works by end of February 2019
- Earthwork Excavations – 99% to be completed
- Earthwork & Backfilling work – 98% to be completed
- Door frame fixing – amenity block(BF ,FF) -100% to becompleted
- Wall plastering work – 18th floor – 100% to be completed
- External Plastering work-South side (90% to be completed)
- Tiling Work – 11 th &12th floor -50% to be completed
- Putty work -14th floor – 90% to be completed
- Handrails:Main stair work -100% to be completed
- Aluminium Fabrication work -60% to be completed
- LT Electrical work: 85% to be completed
- HT Electrical work-50% to be completed
- Reticulated gas work-10% to be completed
- Fire Work-60% to be completed
Work status as on 05-02-2019, we have completed the following
- Earthwork Excavations – 97% completed
- Earthwork & Backfilling work – 95% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed,second floor -completed
- Block/Brick masonry – BF ,FF(Amenity block)(95% completed ),1st to 18th floor (99% completed)
- Door frame fixing – 1-18 th floor -99% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (98% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (93% completed), South sideside (35% completed),
- Tiling Work – dadoing of toilets-1st floor -50%,2-7 th floor-85%,9 th floor -85%,10th floor on progressing
- Putty work – 1st to 10th floor (100% completed) ;11th floor ,12 th,13 th floor -(95%),14th floor-on progressing
- Plumbing -1-3 rd floor -100% completed,4 th to 12 th floor -99%completed,13 th to 14 th floor -98% completed,15 th floor -100% completed,16 th ,17 th floor 90% completed ,118 th floor -95% completed
- Handrails:upto terrace fire stair completed,main stair work -80%completed
- Aluminium Fabrication work :Upto 7 th floor completed(30%completed)
- LT Electrical work: 75% completed
- HT Electrical work-45% completed
- Reticulated gas work-on progressing
- Fire Work-55%completed
As per the current work status from our site we are targeted to complete the following works by end of January 2019
- Earthwork Excavations – 99% to be completed
- Earthwork & Backfilling work – 98% to be completed
- Ceiling Plastering work – Amenity Block(second floor) -100% to be completed
- Door frame fixing – 1-18 th floor -100% to becompleted
- Wall plastering work – 18th floor – 100% to be completed
- External Plastering work-East side (90% to be completed)
- flooring and skirting :10th floor – 50% to be completed
- Putty work – 11th-13th floor – 90% to be completed
- LT Electrical work: 80% to be completed
- HT Electrical work-50% to be completed
- Fire Work-55% to be completed
Work status as on 08-01-2019, we have completed the following
- Earthwork Excavations – 97% completed
- Earthwork & Backfilling work – 95% completed
- RCC for structure – completed
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor – completed
- Block/Brick masonry – 1st to 18th floor (99% completed)
- Door frame fixing – 1-18 th floor -98% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (90% completed); 18th floor (95% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (85% completed)
- Tiling Work – dadoing of toilets-1st floor -50%,2-7 th floor-85%,9 th floor -started
- flooring and skirting :1st floor -50%,2 nd to 7th floor -85%,9 th floor – on progress
- Putty work – 1st to 10th floor (100% completed) ;11th floor ,12 th,13 th floor -(75%)
- Plumbing -1-3 rd floor -100% completed,4 th to 12 th floor -99%completed,13 th to 14 th floor -98% completed,15 th floor -100% completed,16 th ,17 th floor 90% completed ,118 th floor -95% completed
- Handrails:upto terrace fire stair completed
- LT Electrical work: 70% completed
- HT Electrical work-40% completed
- Reticulated gas work-On progress
- Fire Work-50%completed
As per the current work status from our site we are targeted to complete the following works by end of December 2019
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- RCC for structure – water tank work – 100%to be completed.
- First floor -50% to be completed
- Wall plastering work – 18th floor – 100% to be completed
- Putty work – 10th floor – 100% to be completed
- Plumbing -70% to be completed
- LT Electrical work: 65% to be completed
- Fire Work-55% to be completed
Work status as on 06-12-2018, we have completed the following
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 90% completed
- RCC for structure – water tank work – 92%completed.
- Ceiling Plastering work – Amenity Block (BF) – 100% completed,First floor -50% completed
- Block/Brick masonry – 1st to 18th floor (99% completed)
- Door frame fixing – 97% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (50% completed); 18th floor (90% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (70% completed)
- Tiling Work – 1st floor (50% completed); 2nd floor to 7 th floor(70% completed).
- Putty work – 1st to 9th floor (100% completed) ; 10th floor (50%)
- Plumbing -60% completed
- LT Electrical work: 55% completed
- HT Electrical work-30% completed
- Reticulated gas work-On progress
- Fire Work-45%completed
As per the current work status from our site we are targeted to complete the following works by end of November 2018
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Wall plastering work – 18th floor – 100% to be completed
- Putty work – 10th floor – 100% to be completed
Work status as on 16-11-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – water tank work – progressing
- Ceiling Plastering work – Amenity Block (BF) – 100% completed
- Block/Brick masonry – 1st to 18th floor (99% completed)
- Door frame fixing – 85% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (99% completed); 13th floor (98% completed); 14th floor (98% completed); 15th floor (100% completed); 16th & 17th floor (50% completed); 18th floor (30% completed)
- External Plastering work – North side (100% completed); West side (100% completed); East side (50% completed)
- Tiling Work – 1st floor (50% completed); 2nd floor (70% completed); 3rd & 4th floor (55% completed); 5th & 6th floor (50% completed)
- Putty work – 1st to 9th floor (100% completed) ; 10th floor (progrssing)
As per the current work status from our site we are targeted to complete the following works by end of July 2018
- Earthwork Excavations – 100% to be completed.
- Earthwork & Backfilling work – 100% to be completed.
- Block/Brick masonry – 17th & 18th floor – 100% to be completed.
- Door frame fixing – 17th floor – 100% to be completed.
- Wall plastering work – 12th & 13th floor – 100% to be completed.
- Putty work – 5th floor – 100% to be completed.
Work status as on 05-06-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor -100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 18th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor (99% completed);17th floor (75% completed); 18th floor (50% completed)
- Door frame fixing -1st to 16th floor – 100% completed
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 12th floor (95% completed); 13th floor (75% completed)
- External Plastering work – 2nd to 15th floor (10% completed); 16th, 17th & 18th floor (35% completed)
- Putty work – 1st & 2nd floor (50% completed); 4th floor (50% completed); 5th floor (75% completed)
As per the current work status from our site we are targeted to complete the following works by end of May 2018
- Earthwork & Backfilling work – 100% to be completed
- Ceiling plastering work – 100% to be completed
- Block/Brick masonry – 17th & 18th floor – 100% to be completed
- Door frame fixing – 16th floor – 100% to be completed
- Wall plastering work – 11th & 12th floor – 100% to be completed
- External Plastering work – 9th to 17th floor- 20% to be completed
- Putty work – 2nd floor -100% to be completed
Work status as on 05-05-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor -100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 17th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor ( 99% completed);17th floor (75% completed)
- Door frame fixing -1st to 15th floor (100% completed); 16th floor (60% completed)
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 11th floor(95% completed)
- External Plastering work – 9th to 17th floor (10% completed); 18th floor (20%)
Putty work – 1st floor – 40% completed
As per the current work status from our site we are targeted to complete the following works by end of April 2018
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Ceiling plastering work – 100% to be completed
- Block/Brick masonry – 100% to be completed
- Door frame fixing – 14th floor – 100% to be completed
- Electrical chasing work – 100% to be completed
- Wall plastering work – 4th to 9th floor – 100% to be completed
- Putty work – 1st floor -100% to be completed
- Water Proofing work – 100% to be completed
- Wire pulling work – 1st floor- 100% to be completed
- Plumbing work -1st floor- 100% to be completed
Work status as on 16-04-2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor -100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 17th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor ( 99% completed);17th floor (50% completed)
- Door frame fixing -1st to 14th floor – 100% completed
- Electrical chasing work – 1st to 14th floor(100% completed)
- Wall plastering work – 1st to 3rd floor (100% completed); 4th to 10th floor(95% completed)
- Putty work – 1st floor -20% completed
- Water Proofing work – 1st floor to 5th floor (100% completed)
- Wire pulling work – 1st floor- 25% completed
- Plumbing work -1st floor-75% completed
As per the current work status from our site we are targeted to complete the following works by end of March -2018
- Earthwork Excavations – 100% to be completed
- Earthwork & Backfilling work – 100% to be completed
- Ceiling plastering work – 100% to be completed
- Block/Brick masonry – 100% to be completed
- Wall plastering work – 4th to 9th floor – 100% to be completed
- Putty work – 1st floor -100% to be completed
- Electrical chasing work – 12th floor – 100% to be completed
- Wire pulling work – 1st floor- 100% to be completed
- Door frame fixing – 14th floor – 100% to be completed
- Water Proofing work – 2nd & 3rd floor – 100% to be completed
- Plumbing work -1st floor- 100% to be completed
Work status as on 1 3 -0 3 -2018, we have completed the following.
- Earthwork Excavations – 96% completed
- Earthwork & Backfilling work – 81% completed
- RCC for structure – GF to 18th floor 100% completed
- Ceiling Plastering work – GF (80% completed); 1st to 17th floor (100% completed)
- Block/Brick masonry – 1st to 16th floor( 99% completed)
- Wall plastering work – 1st to 3rd floor (100% completed);4th to 9th floor(95% completed)
- Putty work – 1st floor -20% completed
- Electrical chasing work – 1st to 10th floor(100% completed);11th floor (100% completed);12th floor (75% completed);13th floor(25% completed)
- Wire pulling work – 1st floor- 25% completed
- Door frame fixing -1st to 13th floor – 100% completed
- Water Proofing work – 1st floor (95% completed); 2nd & 3rd floor (50% completed)
- Plumbing work -1st floor-75% completed
Work status as on 9-5-2017, we have completed
- Earthwork & Backfilling work – progressing
- RCC for structure – 12th floor progressing
- Ceiling Plastering work -progressing
- Block/Brick masonry – progressing
- Wall plastering work – 1st floor – progressing
Work status as on 8-3-2017, we have completed
- RCC for structure – 11th floor – progressing
- Ceiling Plastering work – progressing
- Block/Brick masonry -progressing
Work status as on 8-2-2017, we have completed
- Earthwork Excavations – progressing
- RCC for structure – 10th floor – progressing
- Ceiling Plastering work – progressing
As per the current work status from our site we are targeted to complete the following works by end of February, 2017.
Work status as on 06-5-2016, we have completed
- Earthwork Excavations – completed
- RCC for structure – 3rd floor – completed
Work status as on 06-03-2015, we have completed
27 nos of Piling works out of 101 and expected to complete 20 nos more out 101 by next month.