PROGRESS

As per the current work status from our site we are targeted to complete the following works by end of ​May 2018

  • Pile cap work – 100% to be completed
  • BF column work – 100% to be completed
  • Roof slab work – 6th floor – 10% to be completed

Work status as on ​05-05-2018, we have completed the following.​

  • Piling work – 100% completed
  • Pile chipping work – 100% completed
  • Pile cap work – 33 nos completed (out of 35)
  • BF column work – 64 nos completed (out of 66)
  • Roof slab work – BF (100% completed) ;GF& 1st floor to 4th floor(70% completed); 5th floor(70% completed); 6th floor (60% completed)

As per the current work status from our site we are targeted to complete the following works by end of April 2018

  • Pile chipping work – 211 nos to be completed (out of 211)
  • Pile cap work – 35 nos to be completed (out of 35)
  • BF column work – 66 nos to be completed (out of 66)
  • Roof slab work – 5th floor roof slab – 70% to be completed;

Work status as on 16-04-2018, we have completed the following.

  • Piling work – 100% completed
  • Pile chipping work – 207nos completed (out of 211)
  • Pile cap work – 33 nos completed (out of 35)
  • BF column work – 62 nos completed (out of 66)
  • Roof slab work – BF (100% completed) ;GF& 1st floor to 4th floor(70% completed);5th floor(60% completed)