This project is truly a diamond, rare and precious. Diamond Enclave is a super-luxury apartment project that aims to revamp the architectural landscape in Trivandrum. It is an exclusive haven for the select few. Located in Vellayambalam, this residence is one that you will be proud to call your home.

Categories: ,

Quick Enquire

Take your first few steps towards finding the ultimate happiness of the Perfect Home.


Amenities

Specification

Concept Images

PROGRESS

As per the current work status from our site we are targeted to complete the following works by end of May 2018

  • Pile cap work – 100% to be completed
  • BF column work – 100% to be completed
  • Roof slab work – 6th floor – 10% to be completed

Work status as on 05-05-2018, we have completed the following.

  • Piling work – 100% completed
  • Pile chipping work – 100% completed
  • Pile cap work – 33 nos completed (out of 35)
  • BF column work – 64 nos completed (out of 66)
  • Roof slab work – BF (100% completed) ;GF& 1st floor to 4th floor(70% completed); 5th floor(70% completed); 6th floor (60% completed)

As per the current work status from our site we are targeted to complete the following works by end of April 2018

  • Pile chipping work – 211 nos to be completed (out of 211)
  • Pile cap work – 35 nos to be completed (out of 35)
  • BF column work – 66 nos to be completed (out of 66)
  • Roof slab work – 5th floor roof slab – 70% to be completed;

Work status as on 16-04-2018, we have completed the following.

  • Piling work – 100% completed
  • Pile chipping work – 207nos completed (out of 211)
  • Pile cap work – 33 nos completed (out of 35)
  • BF column work – 62 nos completed (out of 66)
  • Roof slab work – BF (100% completed) ;GF& 1st floor to 4th floor(70% completed);5th floor(60% completed)

As per the current work status from our site we are targeted to complete the following works by end of July 2018

  • Roof slab work – 3rd floor (100% to be completed); 7th floor (70% to
    be completed); 8th floor (60% to be completed)

Work status as on 16-07-2018, we have completed the following.

  • Piling work – 100% completed
  • Pile chipping work – 100% completed
  • Pile cap work – 100% completed
  • BF column work – 100% completed
  • Roof slab work – BF to 1st floor (100% completed); 2nd floor (90%
    completed); 3rd to 6th floor (70%completed); 7th floor (50% completed)