Work status as of 07-11-2026, We have completed the following.
- Electrical Works :Wall Chasing : Flat inside completed. Wire Pulling : 60 out of 99 Flats completed. Electrical HT Works : Overall 70% completed
- Plumbing Works : Plumbing : 1st to 25th completed except 25A & B, 26A, Duct works and Ring line works 90% Completed, Suspended line works at UBF in progress
- Waterproofing Works :Waterproofing : 1st to 25th completed except 25A & B, 26A. Terrace floor waterproofing works 90% completed. Ground Floor waterproofing 40% completed.
- Tiling Works : Flooring : 56 out of 99 flats completed, Remaining in Progress. Staircase Tiling works 60% completed.
- Painting Works : Putty & Primer: 1st -23rd putty and primer works in progress.
Ducts and Lift shafts Painting Overall 95% works completed.
External Primer Works : West Side Completed. South Side 50% completed, East side 95% Completed, North Side 20% Completion.
External Putty Works : West side 90% completed, South side 100% completed.
1st Coat Paint : East Side – 50% completed
- Fire Fighting Works :Fire Fighting : GF – 23rd Floor sprinkler line works completed. Remaining Floor sprinkler works in progress. Basement floor works 95% completed
- Grills & Handrails :Staircase, Utility Handrail : Overall 80% completed.
Window Grills : Overall 10% Completed.
Balcony Handrails : Overall 4% Completed..
- Aluminium Fabrication :Fabrication Works : Overall 40% completed, Remaining in Progress
- Doors :Main Door : 51 out of 99 Flats Completed.
Internal Doors : 20 out of 99 Flats Completed..
- Elevators: Service Lift : 100% Works Completed.
Lift 2 : Works in Progress.
As per the current site work status, we are targeting to complete the following work by the end of NOV 2026.
- Tiling Works :Staircase Tiling works 100% completion, Rest of the Flats Tiling works completion.
- Painting Works : External Primer : North Side Completion.
1st Coat Paint : East side 95% Completion planned.
Work status as of 07-10-2026, We have completed the following.
- Electrical works: WALL CHASING-Flat inside completed. WIRE PULLING- 56 out of 99 Flats completed.Electrical HT works -50% completed.
- Plumbing Works: 1st to 25th completed,(25A&B, 26A Pending), Duct works and Ring line works 90% Completed.Suspended line works at UBF in progress.
- Waterproofing Works: 1st to 25th completed,(25A&B, 26A Pending). Terrace floor waterproofing works 90% completed.Ground floor waterproofing 30% completed.
- Tiling Works: 56 out of 99 flats completed, Remaining in Progress.Stair case Tiling works 30% completed.
- Painting Works: 1st -23rd putty and primer in progress, Ducts and Lift shafts Painting works 85% completed.External primer works – West Side Completed,South side 50% completed,East side in progress.External Putty works-West side 80% Completed,South side 50% completed.
- Fire Fighting Works: GF – 23rd Floor sprinkler line works completed. Remaining Floor sprinkler works in progress. Basement floor works 95% completed.
- Grills & Handrails: Stair case & Utility handrail-60% completed, Window grills-10% completed,Balcony handrail-4% completed.
- Aluminium Fabrication works: 40% completed, Remaining in Progress
- Door works: Main door – 51/99 Flats completed .Internal doors – 16/99 Completed.
- Elevator works: Lift 2 works in progress.Service Lift works completed.
As per the current site work status, we are targeting to complete the following work by the end of OCT 2026.
- Painting Works : External primer/putty works-West & South Side Completion.
Work status as of 09-09-2026, We have completed the following.
- Civil Works – Block work -Lower Basement Floor,Upper Basement Floor,Ground Floor in progress, 1st -25th floor completed Ceiling plastering – Lower Basement Floor,Upper Basement Floor- in progress,GF-25th floor completed. Terrace Floor Completed. Plastering Inside : First to 25th floor completed. GF &UBF Plastering 95% completed. External plastering : North Side 100% completed. South Side- 100% completed, West Side – 100% Completed, East Side – 95% Completed.
- Electrical works – WALL CHASING-First to 25th floor completed. WIRE PULLING- 55 out of 99 Flats completed. Electrical HT works in progres
- Plumbing Works – 1st to 25th completed,(25A&B, 26A Pending), Duct works and Ring line works 90% Completed.Suspended line works at UBF in progress.
- Waterproofing Works – 1st to 25th completed,(25A&B, 26A Pending). Terrace floor waterproofing works 80% completed.Ground floor waterproofing in progress.
- Tiling Works – 55 out of 99 flats completed, Remaining in Progress
- Painting Works – 1st -23rd putty and primer in progress, Ducts and Lift shafts Painting works 75% completed. External primer works – West Side Completed. External Putty works-West side 75% Completed.
- Fire Fighting Works – GF – 23rd Floor sprinkler line works completed. Remaining Floor sprinkler works in progress. Basement floor works 95% completed.
- Aluminium Fabrication works – 30% completed, Remaining in Progress
- Door works – Main door – 43/99 Flats completed .Internal doors – 16/99 Completed.
- Elevator works – Lift 2 works in progress.
As per the current site work status, we are targeting to complete the following work by the end of SEP 2026.
- Painting Works – External primer works-West Side Completion.
- Door works – Main door-51 Flats completion ,Internal door-30 Flats completion.
Work status as on 10-08-2026, we have completed the following.
- Civil Works – Block work -Lower Basement Floor,Upper Basement Floor,Ground Floor in progress, 1st -25th floor completed,Ceiling plastering – Lower Basement Floor,Upper Basement Floor- in progress,GF-25th floor completed. Terrace Floor Completed , Plastering Inside : First to 25th floor completed. GF &UBF Plastering in progress. , External plastering : North Side 100% completed. South Side- 100% completed, West Side – 100% Completed, East Side – 95% Completed. Remaining in Progress
- Electrical works – WALL CHASING-First to 25th floor completed. WIRE PULLING- 50 out of 99 Flats completed. Electrical HT works in progress
- Plumbing Works – 1st to 25th completed,(25A&B, 26A Pending), Duct works and Ring line works 80% Completed.
- Waterproofing Works – 1st to 25th completed,(25A&B, 26A Pending). Terrace floor waterproofing works 80% completed.Ground floor waterproofing in progress.
- Tiling Works – 50 out of 99 flats completed, Remaining in Progress
- Painting Works – 1st -23rd putty and primer in progress, Ducts and Lift shafts Painting works 60% completed,External primer works – West Side Completed External, Putty works-West side in progress.
- Fire Fighting Works – GF – 23rd Floor sprinkler line works completed, Remaining Floor sprinkler works in progress. Basement floor works 90% completed.
- Aluminium Fabrication works – 20% completed, Remaining in Progress
- Door works – Main door – 36/99 Flats completed Internal doors – 7/99 Completed.
- Elevator works – Service Lift works in Progress
As per the current work status from our site, we are targeted to complete the following works by the end of Aug 2026.
- Sub Structural Works – UBF Parapet 100% completion
- Civil Works – GF & UBF Plastering completion
- Door works – Main door-43 Flats completion ,Internal door-20 Flats completion.
- Elevator works – Service lift works completion,Lift 2 installation works to be commenced.
Work status as of 08-07-2026, We have completed the following.
- Electrical works : WIRE PULLING- 38 out of 99 Flats completed. Electrical HT works in progress
- Plumbing Works : Duct works in Progress,Ring line works started.
- Waterproofing Works : Terrace floor waterproofing in Progress
- Tiling Works : 37 out of 99 flats completed, Remaining in Progress
- Painting Works : 1st -23rd putty and primer in progress, Ducts and Lift shafts Painting works 70% completed External primer works – West Side 80% Completed
- Fire Fighting Works : Ground Floor – 23rd Floor sprinkler line works completed. Remaining Floor sprinkler works in progress. Basement floor works 90% completed.
- Aluminium Fabrication works : 15 out of 99 flats completed, Remaining in Progress
- Door works : Main door – 22/99 Flats completed Internal doors – 4/99 Completed.
- Elevator works : Service Lift works in Progress
As per the current site work status, we are targeted to complete the following work by the end of July 2026.
- Electrical works – Wire pulling- 45 flat completion.
- Painting Works – External primer works – West Side Completion
- Elevator works – Service lift works completion
Work status as of 09-06-2026, We have completed the following.
- Electrical works : WIRE PULLING- 30 out of 99 Flats completed. Electrical HT works in progress
- Plumbing Works : 1st to 25th completed,(25A&B, 26A Pending), Duct works in Progress
- Waterproofing Works : 1st to 25th completed,(25A&B, 26A Pending). Terrace floor waterproofing in Progress
- Tiling Works : 30 out of 99 flats completed, Remaining in Progress
- Painting Works : 1st -23rd putty and primer in progress, Ducts and Lift shafts Painting works 60% completed External primer works – West Side 80% Completed
- Fire Fighting Works : Ground Floor – 23rd Floor sprinkler line works completed. Remaining Floor sprinkler works in progress. Basement floor works in Progress
- Aluminium Fabrication works : 8 out of 99 flats completed, Remaining in Progress
- Door works : Main door – 22/99 Flats completed Internal doors – 4/99 Completed.
- Elevator works : Service Lift works in Progress
As per the current site work status, we are targeted to complete the following work by the end of June 2026.
- Civil Works – External plastering : East side 75% completion, North side 100% completion
- Painting Works – External primer works – West Side Completion
- Elevator works – Service lift works completion
Work status as of 07-05-2026, We have completed the following.
- Electrical works : WALL CHASING-First to 25th floor completed. WIRE PULLING- 26 out of 99 Flats completed. Electrical HT works in progress
- Plumbing Works : 1st to 25th completed,(25A&B, 26A Pending), Duct works in Progress
- Waterproofing Works : 1st to 25th completed,(25A&B, 26A Pending). Terrace floor waterproofing in Progress
- Tiling Works : 26 out of 99 flats completed, Remaining in Progress
- Painting Works : 1st -22th putty and primer in progress,Ducts and Lift shafts. Painting works in Progress. External primer works – West Side 80% Completed
- Fire Fighting Works : GF – 20th Floor sprinkler line works completed. 21st – 23rd floor Floor sprinkler works in progress.
- Aluminium Fabrication works : A Flat series in progress
- Door works : Main door – 22/99 Flats completed Internal doors – 4/99 Completed.
- Elevator works : Service Lift works in Progress
As per the current site work status, we are targeted to complete the following work by the end of May 2026.
- Painting Works – External primer works – West Side Completion
- Fire Fighting Works – 21 to 23rd floor completion. Basement floor works to be started
- Elevator works – Service lift works completion
Work status as on 11-04-2026, we have completed the following.
- Civil Works -Block work -LBF,UBF,GF in progress, 1st -25th floor completed
- Ceiling plastering- LBF ,UBF in progress,GF-25th floor completed. Terrace floor completed.
- Plastering Inside : First to 25th floor completed (25A&B, 26A Pending).
- External plastering : North Side 60% completed. South Side – 100% completed, West Side – 100% Completed, East Side – 40% Completed. Remaining in Progress
- Electrical Works – WALL CHASING-First to 25th floor completed (25A&B in Progress) WIRE PULLING- 20 out of 99 Flats completed. Electrical HT works in progress
- Plumbing Works – 1st to 24th completed,25th in progress, Duct works in Progress
- Waterproofing Works – 1st-24th floors completed, 25th floor in Progress. Terrace floor waterproofing started
- Tiling Works – Ground Floor – 20 out of 99 flats completed, Remaining in Progress
- Painting Works – 1st -20th putty and primer in progress,Ducts and Lift shafts Painting works in Progress External primer works – West Side 80% Completed
- Fire Fighting Works – GF – 13th Floor sprinkler line works completed. 14th – 16th floor Floor sprinkler works in progress
- Elevator Works – Service Lift works in Progress
As per the current site work status, we are targeted to complete the following works by the end of April 2026.
- Civil Works – External plastering : East side 50% completion, North side 80% completion
- Plumbing Works – 25th floor completion
- Waterproofing Works – 25th floor completion
- Painting Works – External primer works – West Side Completion
Work status as on 07-03-2026, we have completed the following.
- Civil Works -Block work -Lower Basement Floor,Upper Basement Floor,Ground Floor in progress, 1st -25th floor completed
- Ceiling plastering Lower Basement Floor ,Upper Basement Floor in progress,Ground Floor-25th floor completed. Terrace Floor Completed
- Plastering Inside : First to 25th floor completed.(25A & B, 26A Pending)
- External plastering : North Side 60% completed. South Side – 100% completed, West Side – 95% Completed, East Side – 20% Completed. Remaining in Progress
- Electrical Works – WALL CHASING-First to 25th floor completed (25A&B pending) WIRE PULLING- 16 out of 99 Flats completed. Electrical HT works started
- Plumbing Works – 1st to 24th completed,25th in progress, Duct works in Progress
- Waterproofing Works- 1st-23rd floors completed, 24th floor in Progress.
- Tiling Works – Ground Floor – 16 out of 99 flats completed, Remaining in Progress
- Painting Works – 1st -20th putty and primer in progress, Ducts and Lift shafts Painting works in Progress ,External primer works – West Side 50% Completed
- Fire Fighting Works – GF – 13th Floor sprinkler line works completed. Pressure testing in progress
- Elevator Works – Service Lift works in Progress
As per the current site work status, we are targeted to complete the following works by the end of March 2026.
- Sub Structural Works – Terrace Elevation Design works completion
- Civil Works – External plastering :West Side completion, East side 40% completion
- Plumbing Works – 25th floor completion
- Waterproofing Works – 24th floor completion
- Painting Works – External primer works – West Side Completion
Work status as on 06-02-2026, we have completed the following.
- Plumbing Works – 1st to 23rd completed,24th in progress, Duct works in Progress
- Waterproofing Works – 1st-22nd floors completed, 23rd floor completed.
- Tiling Works – 12 flats completed, Remaining in Progress
- Painting Works – 1st -18th putty and primer in progress, Ducts and Lift shafts Painting works in Progress
- Fire Fighting Works – Ground Floor – 13th Floor sprinkler line works completed. 14th – 17th in progress
- Elevator works – Service Lift works in Progress
As per the current work status from our site, we are targeted to complete the following works by the end of February 2026
- Civil Works – External plastering :West Side completion, East side 40% completion
- Plumbing Works – 24th floor completion
- Painting Works – Upto 20th floor completion. External primer works to be started.
Work status as on 08-01-2026, we have completed the following.
- Civil Works – Block work -Lower Basement Floor ,Upper Basement Floor ,Ground Floor in progress, 1st -24th floor completed 25th Floor in Completed ; Ceiling plastering Lower Basement Floor ,Upper Basement Floor in progress,Ground Floor -25th floor completed. Terrace Floor Completed.Plastering Inside : First to 24th floor completed. 25th in progress(25Type A&B pending)
- External plastering : North Side 40% completed.
- South Side – 80% completed, West Side – 90% Completed, Remaining in Progress
- Electrical works -WALL CHASING-First to 24th floor completed (25A&B pending) . 25th in progress
- Plumbing Works – 1st to 21st completed,22nd in progress
- Waterproofing Works – 1st-22nd floors completed, 23rd in progress.
- Tiling Works – 10 flats completed
- Painting Works – 1st -17th putty and primer in progress
- Fire Fighting Works – GF – 13th Floor sprinkler line works completed. 14th – 17th in progress
As per the current work status from our site, we are targeted to complete the following works by the end of January 2026
- Electrical works – WALL CHASING- 24th floor to be completed
- Plumbing Works – 22 to be completed
- Waterproofing Works- 23 to be completed
- Tiling Works – 20 flats to be completed
- Painting Works – Upto 20th floor completion. External primer works to be started.
Work status as on 08-12-2025, we have completed the following.
- Sub Structural Works – Boundary wall:- RCC pile cap – 36Nos. completed out of 45 Nos.RCC wall – 160 Rm completed out of 250RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works – Block work -LBF,UBF,GF in progress, 1st -24th floor completed 25th Floor in Progress ;Ceiling plastering Lower basement ,Upper Basement Floor in progress,Ground Floor-25th floor completed.Terrace Floor in ProgressPlastering Inside : First to 23rd floor completed.External plastering : South Side – 50% completed, West Side – 70% Completed, Remaining in Progress
- Electrical works – WALL CHASING-First to 23rd floor completed. 24th in progress
- Plumbing Works – 1st to 19th completed,20th in progress
- Waterproofing Works – 1st-21th floors completed, 22nd in progress.
- Tiling Works – 4A, 6A flat started
- Painting Works – Mock up and sample flat Completed ,1st -14th putty and primer in progress
- Fire Fighting Works – GF – 13th Floor sprinkler line works completed. 14th – 17th in progress
As per the current work status from our site, we are targeted to complete the following works by the end of December 2025
- Sub Structural Works – Parapet wall completion
- Civil Works – External plastering : West side 90% completion & North side – 50% Completion ;Brick work 25th floor to be completed; Plastering Inside-24th to be completed.
- Electrical works – WALL CHASING- 24th floor to be completed
- Plumbing Works – 20 to be completed
- Waterproofing Works – 22 to be completed
- Tiling Works – 4A,5A,6A,7A,8A completion
Work status as on 06-11-2025, we have completed the following.
- Sub Structural Works – Boundary wall:- PCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed, out of 45 Nos.RCC wall – 60 Rm completed
out of 250 RM ,Earth Filling Lower basement floor earth filling – 82% completed
Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works – Block work – Lower Basement Floor,Upper Basement Floor,
Ground Floor in progress, 1st -23rd floor completed 24th Floor in Progress;
Ceiling plastering Lower Basement Floor ,Upper Basement Floor in progress,
Ground Floor -24th floor completed. 25th Floor in Progress.
Plastering Inside : 1st to 22nd floor completed, 23rd floor in progress
- Electrical works – WALL CHASING-First to 23rd floor completed.
- Plumbing Works – 1st to 19th completed,20th in progress.
- Waterproofing Works – 1st-21st floors completed, 22nd in progress.
- Tiling Works – Mock up and sample flat completed. 2B & 2C completed; Washroom Counter slab works – 3rd Floor in progress
- Painting Works – Mock up and sample flat Completed ,1st -14th putty and primer in progress
- Fire Fighting Works – GF – 13th Floor sprinkler line works completed.
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2025.
- Sub Structural Works – LMR, Head room, OHWT & Swimming pool works
- Civil Works – Ceiling plastering : 25th floor to be completed ;Block work 24th floor to be completed; Plastering Inside-23rd be completed.
- Electrical works – WALL CHASING- 24th floor to be completed
- Plumbing Works – 20 to be completed
- Waterproofing Works – 22 to be completed
- Tiling Works – Washroom Counter slab 3rd & 4th floor completion
Work status as on 07-10-2025, we have completed the following.
- Civil Works – Block work -LBF,UBF,GF in progress, 1st -23rd floor completed 24th Floor setoutting ; Ceiling plastering LBF ,UBF in progress,GF-24th floor completed Plastering Inside : First to 21st floor completed, 22nd floor in progress
- Electrical works : WALL CHASING-First to 22nd floor completed.
- Plumbing Works: 1st to 19th completed,20th in progress.
- Waterproofing Works: 1st-19th floors completed, 20th in progress.
- Tiling Works – Mock up and sample flat completed. 2B & 2C in Progress
- Painting Works – Mock up and sample flat Completed ,1st -14th putty and primer in progress
- Fire Fighting Works – GF – 9th Floor sprinkler line works completed, 10th Floor in progress.
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2025
- Sub Structural Works – LMR, Head room, OHWT & Swimming pool works
- Civil Works – Ceiling plastering : 24th floor to be completed ;Block work 23rd floor to be completed; Plastering Inside-21st to be completed.
- Electrical works – WALL CHASING- 21st floor to be completed
- Plumbing Works – 20 to be completed
- Waterproofing Works – 20 to be completed
- Tiling Works – 2B & 2C Flat completion
- Fire Fighting Works – 12th floor completion
Work status as on 09-09-2025, we have completed the following.
- Sub structural works – Piling works – 100% Completed , Pile chipping 83.87% completed (260 nos: completed out of 310 nos:), Pile load test completed, Pile integrity test completed
- Building Area : Pile cap – 100% completed , Plinth beam & Raft slab – 100% completed, LBF – GF Beam & Slab 95% completed, 1st to 25th floor slab and columns completed,Terrace Floor Slab Completed
- Podium Area:- Pile cap – 100% completed , Plinth beam & Raft slab – 100% completed, LBF – GF Beam & Slab 95% completed – completed, LBF – GF Columns 95% completed, RCC for STP- 100% Completed, RCC for Sump tank – 100% completed.
- Boundary wall:- PCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed out of 45 Nos.RCC wall – 60 Rm completed out of 250 RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works Block work -LBF,UBF,GF in progress, 1st -22nd floor completed 23 in progress ; Ceiling plastering LBF ,UBF in progress,GF-23rd floor completed,24 in progress Plastering Inside : First to 20th floor completed, 21st floor in progress
- Electrical works – WALL CHASING-First to 20th floor completed,21st in progress
- Plumbing Works – 1st to 18th completed,19th in progress
- Waterproofing Works – 1st-18th floors completed,19th in progress
- Tiling Works – Mock up and sample flat completed. 2B & 2C in Progress
- Painting Works – Mock up and sample flat Completed ,1st -13th putty and primer in progress
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2025.
- Sub Structural Works – LMR, Head room, OHWT & Swimming pool works
- Civil Works – Ceiling plastering : 24th floor to be completed ;Block work 23rd floor to be completed; Plastering Inside-21st to be completed.
- Electrical works – WALL CHASING- 21st floor to be completed
- Plumbing Works – 19 to be completed
- Waterproofing Works – 19 to be completed
- Tiling Works – 2B & 2C Flat completion
- Fire Fighting Works – 6th- 9th floor completion
Work status as on 06-08-2025, we have completed the following.
- Sub Structural Works- Sub structural works – Piling works – 100% Completed , Pile chipping 83.87% completed (260 nos: completed out of 310 nos:), Pile load test completed, Pile integrity test completed
- Building Area : Pile cap – 100% completed , Plinth beam & Raft slab – 100% completed, LBF – GF Beam & Slab 95% completed, 1st to 25th floor slab and columns completed,Terrace Floor Slab in progress
- Podium Area:- Pile cap – 100% completed , Plinth beam & Raft slab – 100% completed, LBF – GF Beam & Slab 95% completed – completed, LBF – GF Columns 95% completed, RCC for STP- 100% Completed, RCC for Sump tank – 100% completed.
- Boundary wall:- PCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed out of 45 Nos.RCC wall – 60 Rm completed out of 250 RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works Block work -LBF,UBF,GF in progress, 1st -21st floor completed 22 in progress ; Ceiling plastering LBF ,UBF in progress,GF-22nd floor completed,23 in progress Plastering Inside : First to 19th floor completed, 20th floor in progress
- Electrical works – WALL CHASING-First to 19th floor completed,20th in progress
- Plumbing Works – 1st to 17th completed,18th in progress
- Waterproofing Works – 1st-17th floors completed,18th in progress
- Tiling Works – Mock up and sample flat completed. 2B & 2C in Progress
- Painting Works – Mock up and sample flat Completed ,1st -12th putty and primer in progress
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2025.
- Sub Structural Works – RCC Slab – 25th floor to be completed,RCC Column – 24th to 25th floor to be completed
- Civil Works – Ceiling plastering :23rd floor to be completed ;Block work 22nd floor to be completed; Plastering Inside-20th to be completed
- Electrical works – WALL CHASING-20 and 21st floor to be completed
- Plumbing Works – 18 to be completed
- Waterproofing Works – 18 to be completed
- Tiling Works – 2B & 2C Flat completion
Work status as on 09-06-2025, we have completed the following
- Sub Structural Works – Sub structural works – Pile concreting completed , pile chipping 77.41% completed (240 nos: completed out of 310 nos:), pile load test completed, pile integrity test completed
- Building Area – PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – completed, Lower Basement column RCC completed, Lower basement floor slab and beam – 71% completed, Upper basement slab concrete – 54% completed, 1st to 22nd floor slab and columns completed,22nd-23rd columns completed,23rd floor slab-352 sqm completed,23rd-24th columns completed
- Podium Area – PCC pile cap – 34 Nos. completed out of 58 Nos:, RCC pile cap – 37 Nos: completed out of 58 Nos:, RCC pile cap (STP) – completed, Lower basement column RCC – 45 Nos. completed out of 72 Nos:, Upper basement column RCC – 10 Nos. completed out of 52 Nos:, STP slab concrete – 46m2 completed
- Boundary wall – PCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed out of 45 Nos.RCC wall – 60 Rm completed out of 250 RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works – Block work – LBF,UBF,GF in progress, 1st -18th floor completed ,19,20in progress Ceiling plastering LBF ,UBF in progress,GF-19th floor completed Plastering Inside : First to 16th floor completed, 17th floor in progress
- Electrical works – WALL CHASING-First to 17th floor completed,18th in progress
- Plumbing Works – Core Cutting & Sleeving fixing -First to 14th completed,15th in progress
- Waterproofing Works – 1-14 floors completed,15th in progress
- Tiling Works – Mock up and sample flat 95% completed
- Painting Works – Mock up and sample flat in progress,1st,3rd,4th ,5th ,6th putty and primer in progress
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2025.
- Sub Structural Works – RCC Slab – 23rd floor to be completed,RCC Column – 24th to 25th floor to be completed
- Civil Works Ceiling plastering :20th floor to be completed ;Block work 19,20th floor to be completed;Plastering Inside:17th,18th to be completed
- Electrical works – WALL CHASING-18 and 19th floor to be completed
- Plumbing Works – 15 to be completed
- Waterproofing Works- 15 to be completed
Work status as on 09-05-2025, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting completed , pile chipping 77.41% completed (240 nos: completed out of 310 nos:), pile load test completed, pile integrity test completed
- Building Area – PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – completed, Lower Basement column RCC completed, Lower basement floor slab and beam – 71% completed, Upper basement slab concrete – 54% completed, 1st to 22nd floor slab and columns completed,22nd-23rd columns completed,23rd floor slab-352sqm completed
- Podium Area – PCC pile cap – 34 Nos. completed out of 58 Nos:, RCC pile cap – 37 Nos: completed out of 58 Nos:, RCC pile cap (STP) – completed, Lower basement column RCC – 45 Nos. completed out of 72 Nos:, Upper basement column RCC – 10 Nos. completed out of 52 Nos:, STP slab concrete – 46m2 completed
- Boundary wall – RCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed out of 45 Nos.RCC wall – 60 Rm completed out of 250 RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works – Block work – LBF,UBF,GF in progress, 1st -16th floor completed ,17,18 in progress Ceiling plastering LBF ,UBF in progress,GF-19th floor completed Plastering Inside : First to 12th floor and 14th floor completed, 15th,16th floor in progress
- Electrical works – WALL CHASING-First to 16th floor completed
- Plumbing Works – Corecutting & Sleeving fixing -First to 12 th completed,13th in progress
- Waterproofing Works – 1-13 floors completed
- Tiling Works – Mock up and sample flat 95% completed
- Painting Works – Mock up and sample flat in progress,1st,3rd,4th ,5th ,6th putty and primer in progress
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2025.
- Sub Structural Works – RCC Slab – 23rd floor to be completed,RCC Column – 23rd to 24th floor to be completed
- Civil Works Ceiling plastering :20th floor to be completed ;Block work 18th floor to be completed;Plastering Inside:13th,15th,16th to be completed
- Electrical works – WALL CHASING-17 and 18th floor to be completed
- Plumbing Works – Corecutting & Sleeving fixing -13 to be completed
- Waterproofing Works- 14 to be completed
Work status as on 10-04-2025, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting completed , pile chipping 77.41% completed (240 nos: completed out of 310 nos:), pile load test completed, pile integrity test completed
- Building Area :- PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – completed, Lower Basement column RCC completed, Lower basement floor slab and beam – 71% completed, Upper basement slab concrete – 54% completed, 1st to 21st floor slab and columns completed,21st-22nd columns completed
- Boundary wall:- RCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed out of 45 Nos.RCC wall – 60 Rm completed out of 250 RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works Block work Block work -LBF,UBF,GF in progress, 1st -16th floor completed ,17,18 in progress Ceiling plastering LBF ,UBF in progress,GF-18th floor completed,19th in progress Plastering Inside : First to 12th floor ,14th floor completed,13th ,15th floor in progress
- Electrical works – WALL CHASING-First to 12th,14th floor completed,13, in progress
- Plumbing Works -Corecutting & Sleeving fixing -First to 10 th completed,11th in progress
- Waterproofing Works 1-11 floors completed
- Tiling Works – Mock up and sample flat in progress
- Painting Works – Mock up and sample flat in progress,1st,3rd,4th ,5th ,6th putty and primer in progress
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2025.
- Sub Structural Works – RCC Slab – 22nd floor to be completed,RCC Column – 23rd to 24th floor to be completed
- Civil Works Ceiling plastering :19th floor to be completed ;Block work 18th floor to be completed;Plastering Inside:13th and 15th to be completed
- Electrical works – WALL CHASING-13 and 15 floor to be completed
- Plumbing Works – Corecutting & Sleeving fixing -11,12 to be completed
- Waterproofing Works- 12 to be completed
Work status as on 10-03-2025, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting completed , pile chipping 77.41% completed (240 nos: completed out of 310 nos:), pile load test completed, pile integrity test completed
- Building Area :- PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – completed, Lower Basement column RCC completed, Lower basement floor slab and beam – 71% completed, Upper basement slab concrete – 54% completed, 1st to 20th floor slab and columns completed,20 th-21st columns completed
- Podium Area:- PCC pile cap – 34 Nos. completed out of 58 Nos:, RCC pile cap – 37 Nos: completed out of 58 Nos:, RCC pile cap (STP) – completed, Lower basement column RCC – 45 Nos. completed out of 72 Nos:, Upper basement column RCC – 10 Nos. completed out of 52 Nos:, STP slab concrete – 46m2 completed
- Boundary wall:- PCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed out of 45 Nos.RCC wall – 60 Rm completed out of 250RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works Block work -LBF,UBF,GF in progress, 1st -16th floor completed ,17,18 in progress Ceiling plastering LBF ,UBF in progress,GF-17th floor completed Plastering Inside : First to 12th floor completed,13th ,14th floor in progress
- Electrical works – WALL CHASING-First to 12th floor completed,13,14 in progress
- Plumbing Works – Corecutting & Sleeving fixing -First to 9th completed,10th and 11th in progress
- Waterproofing Works 1-10 floors completed
- Tiling Works – Mock up and sample flat in progress
- Painting Works – Mock up and sample flat in progress,1st,3rd,4th ,5th ,6th putty and primer in progress
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2025.
- Sub Structural Works – RCC Slab – 21st floor to be completed,RCC Column – 22nd to 23rd floor to be completed
- Civil Works Ceiling plastering :18th floor to be completed ;Block work 18th floor to be completed;Plastering Inside:13th and 14th to be completed
- Electrical works – WALL CHASING-13 and 14 floor to be completed
- Plumbing Works – Corecutting & Sleeving fixing -11,12 to be completed
Work status as on 13-02-2025, we have completed the following
- Sub Structural Works – Sub structural works – Pile concreting completed , pile chipping 77.41% completed (240 nos: completed out of 310 nos:), pile load test completed, pile integrity test completed
- Building Area :- PCC for pile cap – completed , RCC for pile cap – completed , RCC pedestal column – completed , Plinth beam & Raft slab – 90% completed, Lower Basement column RCC completed, Lower basement floor slab and beam – 71% completed, Upper basement slab concrete – 54% completed, 1st to 20th floor slab and columns completed,20 th-21st columns completed
- Podium Area:- PCC pile cap – 34 Nos. completed out of 58 Nos:, RCC pile cap – 37 Nos: completed out of 58 Nos:, RCC pile cap (STP) – completed, Lower basement column RCC – 45 Nos. completed out of 72 Nos:, Upper basement column RCC – 10 Nos. completed out of 52 Nos:, STP slab concrete – 46m2 completed
- Boundary wall:- PCC pile cap – 6 Nos. completed out of 45 Nos.RCC pile cap – 6Nos. completed out of 45 Nos.RCC wall – 60 Rm completed out of 250RM ,Earth Filling Lower basement floor earth filling – 82% completed ,Ramp :Ramp concrete – 53 Rm Completed out of 107Rm
- Civil Works Block work -LBF,UBF,GF in progress, 1st -17th floor completed Ceiling plastering LBF ,UBF in progress,GF-17th floor completed Plastering Inside : First to 9th floor completed,10th ,11th floor in progress
- Electrical works – WALL CHASING-First to 11th floor completed,12th in progress
- Plumbing Works – Corecutting & Sleeving fixing -First to 7th completed,8th and 9th in progress
- Waterproofing Works 1st,2nd,3rd,4th,5th floor- completed, 6th,7th comppleted ,8th,9th in progress
- Tiling Works – Mock up and sample flat in progress
- Painting Works – Mock up and sample flat in progress,1st,3rd,4th ,5th primer in progress
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2025.
- Sub Structural Works – RCC Slab – 21st floor to be completed,RCC Column – 22nd to 23rd floor to be completed
- Civil Works Ceiling plastering :18th floor to be completed ;Block work 18th floor to be completed;Plastering Inside:10th and 11th to be completed
- Electrical works – WALL CHASING-12 th and 13th floor to be completed
- Plumbing Works – Corecutting & Sleeving fixing -Fourth floor to be completed