Work status as on 08-11-2024, we have completed the following.
- Sub Structural Works – Pile concreting 111 nos. completed Pile integrity test – completed ,Pile chipping 101 nos: completed out of 111 Nos.Excavation of pile cap foundation – 1993 m3 completed out of 2660m3 PCC for pilecap – 105m3 completed out of 120 m3 RCC for pile cap – 250m3 completed out of 275m3 RCC for plinth beam and raft slab – 235m3 completed out of 260m3 ,RCC retaining wall 125 m3 completed out of 195m3 Column RCC – 143 m3 completed out of 800m3 Auger Pile RCC-11cum completed out of 11cum Ground Floor Slab:175cum out of 187cum completed First Floor Slab:160cum out of 160cum completed Second Floor Slab:172cum out of 172 cum completed
- BLOCK WORK 8″ Block Work: 12 m3 completed out of 1750m3
- PLASTERING WORKS – Wall Plastering; 164 sqm completed out of 35000sqm Ceiling plastering: 654sqm completed out of 9000sqm
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2024.
- Sub Structural Works – Column rcc 60cum, Beam and slab rcc 300 cum ,Staircase 10cum ,Shear wall 10cum, Sunshade drop 100 sqm to be completed
- BLOCK WORK 8″ Block Work: 30m3to be completed
- PLASTERING WORKS – Inside Plastering; 500sqm to be completed
Work status as on 14-10-2024, we have completed the following.
- Sub structural works – Pile concreting 111 nos. completed Pile integrity test – completed ,Pile chipping 101 nos: completed out of 111 Nos.Excavation of pile cap foundation – 1970m3 completed out of 2100m3 PCC for pilecap – 120m3 completed out of 155m3 RCC for pile cap – 250m3 completed out of 275m3 RCC for plinth beam and raft slab – 235m3 completed out of 260m3 ,RCC retaining wall 130m3 completed out of 200m3 Column RCC – 165m3 completed out of 800m3 Auger Pile RCC-11cum completed out of 11cum Ground Floor Slab:192cum out of 220cum completed First Floor Slab:187cum out of 187cum completed Second Floor Slab:172cum out of 172 cum completed
- BLOCK WORK- 8″ Block Work: 12m3 completed out of 1750m3
- PLASTERING WORKS- Wall Plastering; 88sqm completed out of 350000sqm Ceiling plastering: 80sqm completed out of 9000sqm
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2024.
- Sub Structural Works – Column rcc 60cum, Beam and slab rcc 300 cum ,Staircase 10cum ,Shear wall 10cum, Sunshade drop 100 sqm to be completed
- BLOCK WORK8″ Block Work: 30m3to be completed
- PLASTERING WORKS- Inside Plastering; 500sqm to be completed
Work status as on 12-09-2024, we have completed the following.
- Sub structural works – Pile concreting 111 nos. completed Pile integrity test – completed ,Pile chipping 101 nos: completed out of 111 Nos.Excavation of pile cap foundation – 1970m3 completed out of 2100m3 PCC for pilecap – 120m3 completed out of 155m3 ,RCC for pile cap – 250m3 completed out of 275m3 RCC for plinth beam and raft slab – 235m3 completed out of 260m3 ,RCC retaining wall 130m3 completed out of 200m3 Column RCC – 78m3 completed out of 800m3 Auger Pile RCC-11cum completed out of 11cum
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2024.
- Sub Structural Works – Pile chipping – 10 more nos: to be completed, Excavation of pile cap foundation – to be completed, Column and shear wall RCC 20m3 to be completed, Retaining wall RCC – 42m3 to be completed, Basement floor Roof slab RCC – 85m3 to be completed, GF roof slab 75m3 to be completed
Work status as on 13-08-2024, we have completed the following.
- Sub structural works – Pile concreting 111 nos. completed,Pile integrity test – completed,Pile chipping 101 nos: completed out of 111 Nos.Excavation of pile cap foundation – 1680m3 completed out of 1800m3 ,PCC for pilecap – 221m3 completed out of 255m3 ,RCC for pile cap – 305m3 completed out of 325m3,RCC for plinth beam and raft slab – 349m3 completed out of 381m3 ,RCC retaining wall 83m3 completed out of 125m3,Column RCC – 27m3 completed out of 800m3,Auger Pile RCC-11cum completed out of 11cum.
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2024.
- Sub Structural Works – Pile chipping – 10 more nos: to be completed,Excavation of pile cap foundation – 120 cum to be completed,Column and shear wall RCC 20m3 to be completed,Retaining wall RCC – 42m3 to be completed,Basement floor Roof slab RCC – 85m3 to be completed,GF roof slab 75m3 to be completed
Work status as on 09-07-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 89 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1665m3 completed out of 1800m3, PCC for pilecap – 221m3 completed out of 255m3, RCC for pile cap – 305m3 completed out of 325m3, RCC for plinth beam and raft slab – 349m3 completed out of 381m3, RCC retaining wall 83m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2024.
- Sub Structural Works – Earth back filling – 60m3 to be completed, pile chipping – 11 more nos: to be completed, pilecap RCC – 1m3 to be completed, Column and shear wall RCC 20m3 to be completed, retaining wall RCC – 20m3 to be completed, Basement floor Roof slab RCC – 85m3 to be completed, GF roof slab 75m3 to be completed
Work status as on 11-06-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 89 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1516m3 completed out of 1800m3, PCC for pilecap – 108m3 completed out of 255m3, RCC for pile cap – 183m3 completed out of 325m3, RCC for plinth beam and raft slab – 135m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
- Sub Structural Works – Earth work – 250m3 to be completed, pile chipping – 11 more nos: to be completed, PCC work – 35m3 to be completed, pilecap RCC – 25m3 to be completed, plinth beam and raft slab – 30m3 to be completed, Column RCC – 25m3 to be completed, retaining wall RCC – 5m3 to be completed, Roof slab RCC – 90m3 to be completed
Work status as on 09-05-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 76 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1386m3 completed out of 1800m3, PCC for pilecap – 105.4m3 completed out of 255m3, RCC for pile cap – 158.7m3 completed out of 325m3, RCC for plinth beam and raft slab – 135m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
- Sub Structural Works – Earth work – 245m3 to be completed, pile chipping – 14 more nos: to be completed, PCC work – 25m3 to be completed, pilecap RCC – 42m3 to be completed, plinth beam and raft slab – 70m3 to be completed, Column RCC – 10m3 to be completed, retaining wall RCC – 8m3 to be completed, Boundary wall RCC – 22m3 to be completed, Roof slab RCC – 95m3 to be completed
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – completed , Pile chipping 62 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 1041m3 completed out of 1300m3, PCC for pilecap – 88.6m3 completed out of 255m3, RCC for pile cap – 148.1m3 completed out of 325m3, RCC for plinth beam and raft slab – 131m3 completed out of 381m3, RCC retaining wall 33m3 completed out of 125m3, column RCC – 27m3 completed out of 800m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 58 nos: completed out of 111 Nos:, Excavation of pile cap foundation – 836m3 completed out of 1300m3, PCC for pilecap – 66.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 109m3 completed out of 381m3, RCC retaining wall 14m3 completed out of 125m3, column RCC – 7m3 completed out of 800m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 54 nos completed out of 111 Nos:, Excavation of pile cap foundation – 633m3 completed out of 1300m3, PCC for pilecap – 45.5m3 completed out of 255m3, RCC for pile cap – 128.5m3 completed out of 325m3, RCC for plinth beam and raft slab – 60m3 completed out of 381m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile integrity test – 36nos: completed out of 85nos: , Pile chipping 36 nos completed out of 111 Nos:, Excavation of pile cap foundation – 401m3 completed out of 1300m3, PCC for pilecap – 18.7m3 completed out of 255m3, RCC for pile cap – 62m3 completed out of 325m3, RCC for plinth beam and raft slab – 7m3 completed out of 381m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile chipping 22 nos completed out of 111 Nos:, Excavation of pile cap foundation – 335m3 completed out of 1300m3, PCC for pilecap – 6.8m3 completed out of 255m3, RCC for pile cap – 43.3m3 completed out of 325m3, RCC for plinth beam and raft slab – 2m3 completed out of 381m3
We are pleased to inform you the current work progress at our site Artech “Marvel”, Pattom, Few snaps of the work progress is attached for your reference.
- Sub Structural Works – Sub structural works – Pile concreting 111 Nos: completed, Pile cap 5 Nos completed out of 57 Nos:, pile chipping 11 nos completed out of 111 Nos: