Artech Sreya is the product of a vision conceived to bring together all the elements of luxury and comfort at an affordable price to the residents of Trivandrum. Located at the heart of the capital city, at Kaithamukku, the project has already caught the attention of savvy home seekers looking for an abode in the city. The elegant tower offers 2 and 3 BHK apartments which are spacious and lets in ample natural light and aeration. The sizes of each unit range from 1200 to 1625 sq ft. The complex offers value added leisure facilities like the Unisex gym, Banquet Hall, Landscaped Terrace, Party area, Children’s play area etc.

Quick Enquire

Take your first few steps towards finding the ultimate happiness of the Perfect Home.

Location

Artech Sreya, Kaithamukku - Location

Layout

Specification

Structure

Deep pile foundation complying with seismic 3 zone. RCC frame structure with brickwork and or concrete block partitions (All plumbing services passing through the walls are solid block). Concrete grade and Steel grade as per structural consultant’s advice.

Flooring & Tiling

Lift lobby and fascia wall & floor using composite marble /vitrified Tiles, as per the architect’s design.Staircases using vitrified tile flooring with hand railing using paint finished MS.Car park Area : Grano flooring with grooves or exterior grade paving tiles.Foyer / Living/ Dining/ Bed Rooms / Kitchen using 60cm X 60cm Vitrified tiles.Master Bed room using AC4 laminated wooden flooring
Toilets : Ceramic tile concepts 30cm X 30cm for floor and 30cm X 45cm for walls up to height of 8’ 0”.Servants Toilet : Ceramic tile 30cm X 30cm for floor and 30cm X 45cm for walls upto 8’0” height.Utility Room : 30cm X 30cm / 60 X 60 cm for floor and 30cm X 45cm for wallsupto 4’6” height and 2’ above the kitchen and work area counter
Balconies / Open Terraces / Decks : Rustic / antiskid / ceramic tiles 30cm X 30cm with MS railings.

Sanitary & Plumbing

Sanitary fittings: EWC wall-hung, concealed cisterns GEBRIT / GROHE make, counter washbasin. All sanitary fittings shall be of Roca / American Standard or equivalent.
Master Bed Room Faucets: Shall be single lever concealed diverters CP finish, heavy body metal fittings of Grohe / Roca or equivalent make. Provision for hot water connection shall be provided for overhead shower in each bathroom. Health faucet also shall be provided. Other Toilets : Shall be 3 in 1 mixer CP finish, Over head shower, health faucet by Jaquar / Roca / Grohe or equivalent. Plumbing: All water supply lines shall be in ISI marked CPVC pipes. Drainage lines and storm water drain pipes shall be in PVC.
Kitchen & Service area : Wall mounted Faucets / taps using JAQUAR or equivalent shall be provided. Stainless Steel Sink single bowl with drain board of make NIRALI or equivalent shall be provided for the kitchen and stainless steel sink without drain board shall be provided for the utility and service areas.Towel rods, towel ring, soap dish and health faucets shall be provided inside the toilets

Doors & Windows

Window shutters: Prefabricated colour anodised aluminum.
Door Frames: Main door frame and shutter shall be of seasoned teak wood. Inner and Outer face to be PU coated and finished.Door Shutters: All internal door frames shall be of seasoned hard wood with flush/ Masonite Skin door shutter. All internal and external faces shall be melaminefinish. Hardware: All hardware shall be in C.P Brass, tower bolts, doorstoppers, ball bearing hinges. Locks shall be mortise of Dorset /Yale make or equivalent.

Electrical

Concealed copper wiring using Finolex or equivalent make with modular plate switches, centralized cabling system for all electrical and communication requirements
Wiring shall be done for lighting, 5Amps, 15 Amps and AC points in the Apartment.
Switches: All switches shall be Honeywell / Legrand / Schneider or equivalent make.
Generator: Power backup will be provided for all common services and selected light and fan point in each living, bedrooms inside apartment and a refrigerator point except Air-conditioning and Geyser points.Light fixtures for the Common areas, external areas, apartment balconies and at entrance door of the individual apartments shall be provided
Adequate ELCB and MCB shall be provided in each apartments.Provision for the GEYSER points and fresh air fans shall be provided for all toilets.Provision for telephone and Internet shall be provided in the living room and master bed room.

Ceiling Treatment

Premium Emulsion paint shall be applied in the common areas, utility, service areas.Premium Emulsion paint shall be applied for the ceiling in apartments.

Wall treatment

Internal Walls: Acrylic / cement based Putty with Premium emulsion paint.Service area– Premium Emulsion.External Walls: Whether shield / Equivalent exterior grade emulsion / texture paint.

Elevator/s

Elevators: High Speed lift shall be provided as per the Govt. norms in each core with automatic doors & SS brush finish of KONE or reputed make.

Air Conditioning

Provision for Split ACs, shall be provided for the Master Bed.

Home Automation

Access control entry to the common entrance / foyers and gymnasium
Light sensors for common areas. Home security monitoring, gas leakage detectors, emergency panic intrusion alarm, visitor tracking. Multi level security system for common areas and lobbies.

Landscaping

Terrace gardens and well designed Landscape area. Interlock Pavers or Tiles to be laid in driveways and walkways.Water bodies and fountains shall be provided as per the architect’s design

Progress

Work status as on 5-7-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Door frame fixing work – completed
  • Electrical chasing work – completed
  • Wall Plastering work – upto Terrace floor – completed
  • Outside plastering work – completed
  • Flooring and skirting – progressing
  • Inside Putty & primer work – progressing
  • Plumbing work – progressing

Work status as on 9-6-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Door frame fixing work – completed
  • Electrical chasing work – completed
  • Wall plastering work – completed
  • Outside plastering work – completed
  • Inside Putty & primer work – on progress
  • Outside Putty & primer work – all floors – on progress
  • Plumbing work – on progress

Work status as on 9-5-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Electrical chasing work – completed
  • Outside plastering work – completed
  • Flooring and skirting – progressing
  • Outside Putty & primer work -progressing

Work status as on 8-3-2017, we have completed.

  • RCC for Structure – 100% completed
  • Block/Brick masonry – 100% completed
  • Door frame fixing work – 100% completed
  • Electrical chasing work – 100% completed
  • Wall Plastering work – 100% completed
  • Outside plastering work – 100% completed

Work status as on 8-2-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Door frame fixing work – completed
  • Electrical chasing work – completed
  • Wall Plastering work – upto Terrace floor – completed
  • Plumbing work – progressing
  • As per the current work progress from our site we are progressing with the same and will complete it by the end of February , 2017.
  • Slab shuttering and steel work – 6th floor – progressing
  • Ceiling plastering – 3rd floor – progressing
  • Block work – 1st floor – 90% completed and 2nd floor progressing

We are expected to complete the following works by the end of June 2015.

  • Slab RCC – 6th floor roof – 100% completion
  • Ceiling plastering – 3 rd floor – 100% completion
  • Block work – 1st& 2nd floor – 100% completion
  • Pile cap work – 23nos completed (out of 56)
  • Tie beam work – progressing
  • Plinth beam work – progressing
  • We are expected to complete the following works by the end of January 2015.
  • Pile cap work – 90% completion
  • Tie beam work – 100% completion
  • Plinth beam work – 60% completion
  • 1st floor column work – 50% completion
  • 1st floor Slab shuttering work – 50% completion

When buying a home, the location is a very important factor. A good location usually means easy accessibility of facilities, like schools, hospitals, shopping and basic infrastructure. There should be good roads to access your new home as well as being a little away from the heart of the city as no one really wants to face the constant honking and other humdrum disturbances.

This is all the more reason why you should consider buying apartments in Kaithamuku, an area that makes a great location for living. This primarily residential area is nestled between the Vanchiyoor and Pettah areas of Trivandrum. Though Trivandrum is the capital city of Kerala, it is far removed from the hustle and bustle usually associated with a capital city. Here, you will find lots of greenery, lower pollution levels, a booming IT industry and a great infrastructure that actually works!

Another factor to consider when going home-shopping is to look for big brand builders. This way, you can be sure of getting the best quality for your money. Artech Realtors have been in this industry for over two decades now and have premium apartment projects in key locations in the city. It’s no wonder then that savvy homebuyers have been taking greater interest in Artech apartments in Kaithamuku.

Furthermore, all Artech homes come with a bagful of amenities that will get your neighbours going green. Why not look at some of these flats in Kaithamuku while they are still available.