Work status as on 08-11-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 15m3 completed,Column 10 nos completed(part 2) Sump tank base slab RCC completed, Sump tank wall upto 2.3m RCC completed, Retaining wall rear side 60% completed, sheet piling completed ,LGF2 FLOORSLAB AND RAMP- 130m3 ,Grade Slab work -130 m3 completed Tower1: Excavation-200cum,excavation- 200cum pcc-40 cum,pilecap-120 cum,plinth beam&grade slab-80cum,Basement columns-70 cum,LGF2 floor slab-125 cum,LGF2 Columns-100 cum,LGF1 floor slab-220 cum,STP WALL CONCRETE=40 CUM,LIFT PILE CAP& FOOTINGS=30 CUM,PCC= 6 CUM,ROCK BREAKING = 25 CUM,COLUMN CONCRETE =18cum
Tower 02 Excavation- 500cum,PCC-40 cum,Pilecap-170 cum,Plinth beam&grade slab-80cum,GRADE SLAB =50 CUM,PCC = 10 CUM,PILE CAP =30 CUM,PILE CHIPPING = 38 RM,COLUMN CONCRETE= 7 CUM
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2024.
- Sub Structural Works – L1 slab,L2 Slab and Column to be completed,STP wall casting, Part 2 lift wall casting,Part 4,1 lift area waterproofing
Work status as on 14-10-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 15m3 completed,Column 10 nos completed(part 2) Sump tank base slab RCC completed, Sump tank wall upto 2.3m RCC completed, Retaining wall rear side 60% completed, sheet piling completed ,LGF2 FLOORSLAB AND RAMP- 130m3 ,Grade Slab work -130 m3 completed Tower1: Excavation-200cum,excavation- 200cum pcc-40 cum,pilecap-120 cum,plinth beam&grade slab-80cum,Basement columns-70 cum,LGF2 floor slab-125 CUM,LGF2 Columns-100 cum, Tower 02 Excavation- 500cum,PCC-40 cum,Pilecap-170 cum,Plinth beam&grade slab-80cum
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2024.
- L1 slab,L2 Slab and Column to be completed,STP wall casting, Part 2 lift wall casting,Part 4,1 lift area waterproofing
Work status as on 12-09-2024, we have completed the following.
- Sub Structural Works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 15m3 completed,Column 10 nos completed(part 2) Sump tank base slab RCC completed, Sump tank wall upto 2.3m RCC completed, Retaining wall rear side 60% completed, sheet piling completed ,LGF2 FLOORSLAB AND RAMP- 130m3 ,Grade Slab work -130 m3 completed
Work status as on 13-08-2024, we have completed the following.
- Sub Structural Works – Pile concretingcompleted Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 129 m3 completed, Plinth beam RCC – 80m3 completed,Column 10 nos completed(part 2) sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
Work status as on 09-07-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 460 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 100m3 completed, Raft slab RCC – 30m3 completed, Plinth beam RCC – 5m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
Work status as on 11-06-2024, we have completed the following.
- Sub Structural Works – S Sub structural works – Pile concreting 459 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2024.
- Sub Structural Works- pile concreting 95% to be completed
Work status as on 09-05-2024, we have completed the following.
- Sub Structural Works – Sub structural works – Pile concreting 459 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed, Retaining wall rear side of house 60% completed, sheet piling completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2024.
-
- Sub Structural Works-pile concreting 95% to be completed
Work status as on 09-04-2024, we have completed the following.
-
-
- Sub Structural Works Sub structural works – Pile concreting 435 nos: completed out of 495 nos:, Pile chipping – 70 nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 85m3 completed, sump tank base slab RCC completed, sump tank wall upto 2.3m RCC completed
Work status as on 09-03-2024, we have completed the following.
-
-
- Sub Structural Works Sub structural works – Pile concreting 367 nos: completed out of 495 nos:, Pile chipping – 19nos: completed, excavation for pilecap (10 Nos:) completed, pile cap RCC – 30m3 completed, sump tank base slab RCC completed
Work status as on 10-02-2024, we have completed the following.
-
-
- Sub structural works – Pile concreting 300 nos: completed out of 495 nos:, Pile chipping started, excavation for pilecap (10 Nos:) completed
Work status as on 13-01-2024, we have completed the following.
-
-
- Sub Structural Works – Sub structural works – Pile concreting 221 nos: completed out of 495 nos:
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2024.
-
-
- Sub Structural Works – 70 more nos: of pile concreting to be completed, retaining wall 75% to be completed
Work status as on 08-12-2023, we have completed the following.
-
-
- Sub Structural Works – Sub structural works – Pile concreting 162 nos: completed out of 495 nos:
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
-
-
- Sub Structural Works – 75 more nos: of pile concreting to be completed, retaining wall 75% to be completed
We are pleased to inform you the current work progress at our site Artech “L’Attitude”, Sreekaryam, Few snaps of the work progress is attached for your reference.