Work status as on 12-04-2024, we have completed the following.
- Internal Finishes Main door – completed, Wall tiling – 3rd to 12th floor (toilets) – 90% completed, 13th floor – 60% completed, 14th,15th,18th floor – 40% completed, 17th floor – 60% completed, Flooring – 3rd,4th ,5th floor completed, 2nd floor – 80% completed, 6th floor – 95% , 7th – 12th floor – 80% completed, 15th floor- 40%, 13th floor – 80% completed, 14th – 60%, 16th – 60%, 17th floor – 40%, 18th floor – 20% completed, passage floor tiling – 1st to 14th floor – 100% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, painting 1st coat – 30% completed (25 flats), Water proofing – 3rd to 19th floor 98% completed, OHT- 80% completed, open terrace – 60% completed, Sump tank – 30% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed)
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 90% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 98% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed, switch fixing – 12 flats completed
- External Finishes Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th,6th,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2024.
- Internal Finishes wall tiling up to 14th floor 90% to be completed, Flooring – up to 17th floor 100% to be completed, passage floor tiling – 15th,16th, 17th,18th, GF floor 100% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – till 19th floor 100% to be completed, CP Sanitary – 5 flats to be completed, Electrical wire pulling – 10 flats to be completed, switch fixing – 10 more flats to be completed
- External Finishes Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 12-03-2024, we have completed the following.
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 12th floor (toilets) – 90% completed, 13th floor – 40% completed, 14th,15th,18th floor – 40% completed, 17th floor – 60% completed, Flooring – 3rd floor completed, 2nd floor – 70% completed, 4th – 12th floor – 80% completed,15th floor- 40%, 13th floor – 80% completed, 14th – 40%,16th – 60%, 17th floor – 30%,18th floor – 20% completed, passage floor tiling – 1st to 12th floor – 95% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 19th floor 98% completed, OHT- 80%completed, open terrace – 40% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed).
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 98% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed
- External Finishes Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2024.
- Internal Finishes Main door – 100% to be completed, wall tiling up to 14th floor 90% to be completed, Flooring – up to 15th floor 80% to be completed, passage floor tiling – up to 15th floor 95% to be completed, water proofing works – OHT – 100% to be completed, open terrace – 80% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – up to 15th floor – 90% to be completed
- External Finishes Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 10-02-2024, we have completed the following.
- Structural Works – Pile cap – completed, slab – 95% completed, retaining wall – 70% completed, compound wall – 80% completed (110m), GF, BF floor slab – 70% completed
- Civil Works Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 12th floor (toilets) – 90% completed, 13th floor – 40% completed, 14th,15th,18th floor – 20% completed, 17th floor – 40% completed, Flooring – 3rd floor completed, 4th – 12th floor – 80% completed,15th floor- 40%, 13th floor – 40% completed, 14th,16th,18th floor – 20% completed, passage floor tiling – 1st to 12th floor – 95% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 19th floor 98% completed, OHT- 80%completed, open terrace – 40% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed)
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 12th floor – 90% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2024.
- Structural Works – Ground floor slab – 80% to be completed, Raft slab – 80% to be completed, BF column 1 more No: to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling up to 14th floor 90% to be completed, Flooring – up to 15th floor 80% to be completed, passage floor tiling – up to 15th floor 95% to be completed, water proofing works – OHT – 100% to be completed, open terrace – 80% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – up to 15th floor – 90% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 13-01-2024, we have completed the following.
- Structural Works – Pile cap – completed, slab – 95% completed, retaining wall – 70% completed, compound wall – 80% completed (110m), GF, BF floor slab – 70% completed
- Civil Works Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 11th floor (toilets) – 90% completed, 13th floor – 40% completed, 14th,15th,18th floor – 20% completed, 17th floor – 40% completed, Flooring – 3rd floor completed, 4th – 11th floor – 80% completed,15th floor- 40%, 13th floor – 40% completed, 14th,16th,18th floor – 20% completed, passage floor tiling – 1st to 6th floor – 95% completed, lift cladding – p3 lift completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 19th floor 95% completed, OHT- 80%completed, open terrace – 30% completed, Door frame fixtures – completed, Handrails – 60% completed (firestair handrail completed, Main stair – completed, balcony handrail – 60% completed)
- Electrical, Plumbing & Firefighting works Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till GF -19th floor 90% completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 11th floor – 90% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, B,C,D,E -one coat paint completed, plumbing duct line – 2nd to 14th floor – 90% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2024.
- Structural Works – Ground floor slab – 80% to be completed, Raft slab – 80% to be completed, BF column 1 more No: to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling up to 14th floor 90% to be completed, Flooring – up to 15th floor 80% to be completed, passage floor tiling – up to 15th floor 95% to be completed, water proofing works – OHT – 100% to be completed, open terrace – 80% to be completed, Handrail – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – up to 15th floor – 90% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – up to 19th floor 100% to be completed
Work status as on 08-12-2023, we have completed the following.
- Structural Works Pile cap – completed, slab – 95% completed, retaining wall – 45% completed, compound wall – 60% completed (42m), GF, BF floor slab – 50% completed
- Civil Works Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – completed (till Terrace floor Completed), Internal plaster -completed (till Terrace floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 10th floor (toilets) – 90% completed, 13th floor – 20% completed, 14th,15th,18th floor – 20% completed, Flooring – 3rd floor completed, 4th floor – 80%, 5th floor – 80%, 6th floor – 80%, 7th floor – 80%, 8th floor – 80%, 9th floor – 80% completed, 10th floor – 80%, 11th floor – 80% completed 15th floor- 40%, 13th,14th,16th,18th floor – 20% completed, passage floor tiling – 2nd floor – 95% completed putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 95% 2 coat putty and primer completed, Water proofing – 3rd to 16th floor 98% completed, 17 to 19th floor – 70% completed, terrace water tank completed, Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 95% completed (till 15th floor completed, 16th, 17th,18th, 19th floor – 90% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 60% completed, Firefighting final fixtures – horizontal pipe line till 19th floor completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 90% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D,E,A outside area – 2 coat damp proof, 2 coat putty, one coat primer completed 90% completed, plumbing duct line – 2nd to 14th floor – 60% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2023.
- Structural Works – Ground floor slab – 50% more to be completed, Raft slab – 80% to be completed, BF column 12 Nos: to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling 11th,12th, 13th floor to be completed, Flooring – 12th,13th,14th floor to be completed,passage floor tiling – 1st,3rd,4th,5th floor 95% to be completed, water proofing works – balcony and toilets – 3rd to 19th floors 95% to be completed,
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – 10th,11th,12th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 70% to be completed, plumbing duct line – 2nd to 14th floor 90% to be completed
Work status as on 10-11-2023, we have completed the following.
- Structural Works – Pile cap – completed, slab – 95% completed, retaining wall – 45% completed, compound wall – 60% completed (42m)
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster -Ground floor – completed, 98% completed (till 19th floor completed)
- Internal Finishes – Main door – 84 nos: out of 92 nos:completed, Wall tiling – 3rd to 10th floor (toilets) – 90% completed, 13th floor – 20% completed, 14th,15th,18th floor – 20% completed, Flooring – 3rd floor completed, 4th floor – 80%, 5th floor – 80%, 6th floor – 80%, 7th floor – 80%, 8th floor – 80%, 9th floor – 80% completed, 10th floor – 70%, 15th floor- 40%, 13th,14th,16th,18th floor – 20% completed, putty works & Painting – putty 95% completed 1st to 19th floor 2 coat putty & 2 coat primer completed, GF – 70% one coat putty and primer completed, Water proofing – 3rd to 13th floor 98% completed, 14 to 17th floor – 70% completed, terrace water tank 98% completed, Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – 95% completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 15th floor completed, 16th, 17th,18th floor – 40% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 40% completed, Firefighting final fixtures – horizontal pipe line till 16th floor completed, 17th floor – 60% completed, vertical pipe line work – 90% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 70% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D outside area – 2 coat damp proof, 2 coat putty, one coat primer completed , E, A – 2 coat damp proof completed, 2 coat putty, one coat primer work – 80% completed, plumbing duct line – 2nd to 14th floor – 60% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2023.
- Inside plastering – 19th floor 100% to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling -up to 10th floor 100% to be completed, 11th ,12th – 80% to be completed, Flooring – 4th to 10th floor 100% to be completed, 11th ,12th – 50% to be completed, water proofing works – balcony and toilets – 3rd to 19th floors 100% to be completed, Handrails – balcony handrail 40% including glass portion to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Gas piping system- 50% to be completed, Firefighting final fixtures – 17th – 19th floor 100% to be completed, Electrical wire pulling – 4th to 9th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 50% to be completed, External Plastering – 100% to be completed, External painting – E,A – 2 coat putty and one coat primer 100% to be completed, plumbing duct line – 2nd to 14th floor 90% to be completed
Work status as on 10-10-2023, we have completed the following.
- Structural Works – Pile cap – completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall completed, ramp completed, retaining wall – 45% completed, compound wall – 60% completed (42m), LMR Base slab, roof completed, main and fire stair head room completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster -Ground floor – completed, 98% completed (till 19th floor completed)
- Internal Finishes – Main door -1st to 3rd floor completed, Wall tiling – 3rd to 8th floor (toilets) – 90% completed, 9th floor – 80% completed, 13th floor – 20% completed, 14th,15th,18th floor – 20% completed, Flooring – 3rd floor completed, 4th floor – 80%, 5th – 80%, 6th – 80%, 7th – 80%, 8th – 50%, 9th floor – 50% completed, 13th,14th,16th,18th floor – 20% completed, putty works & Painting – putty 50% completed 1st to 19th floor 2 coat putty & 2 coat primer 90% completed, Water proofing – 40% completed (till 16th floor bathrooms only, balcony – upto 16th floor 100% completed), Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – GF to 2nd floor, 1st to 19th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 15th floor completed,16th, 17th,18th floor – 40% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- 10% completed, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 80% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 40% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D outside area – 2 coat damp proof, 2 coat putty, one coat primer completed , E, A – 2 coat damp proof completed, 2 coat putty, one coat primer work – 50% completed, plumbing duct line – 40% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2023.
- Civil Works – Inside plastering – 19th floor 100% to be completed
- Internal Finishes – Main door – 100% to be completed, wall tiling -up to 10th floor 80% to be completed, Flooring – 4th to 10th floor 100% to be completed, Water proofing – 11th,12th – 50% to be completed, water proofing works – balcony and toilets – till 19th floors 100% to be completed, Handrails – balcony handrail 40% including glass portion to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Gas piping system- 50% to be completed, Firefighting final fixtures – 100% to be completed, Electrical wire pulling – 4th to 9th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 50% to be completed, External Plastering – 100% to be completed, External painting – E,A – 2 coat putty and one coat primer 100% to be completed, plumbing duct line – 80% to be completed
Work status as on 13-09-2023, we have completed the following.
- Structural Works – Pile cap – completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall completed, ramp completed, retaining wall – 40% completed, compound wall – 60% completed (42m), LMR Base slab, roof completed, main and fire stair head room completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – 70% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 8th floor (toilets) – 90% completed, Flooring – 3rd floor completed, 4th, 5th, 6th, 7th, 8th, 9th floor (45% completed), putty works & Painting – putty 50% completed (till 11th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 90% completed, 18th floor – 80% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, primer after two coat putty till 9th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 12th floor 100% completed), Door frame fixtures – completed, Handrails – 20% completed (firestair handrail completed, Main stair – GF to 2nd floor, 17th to 19th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 15th floor completed,16th, 17th,18th floor – 40% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 60% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 40% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed , 11th to 18th floor – 20% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – C,B,D outside area – 2 coat damp proof, 2 coat putty, one coat primer completed , E, A – 2 coat damp proof completed), plumbing duct line – 3rd to 9th floor floor completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2023.
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 19th floor 100% to be completed, GF to be completed
- Internal Finishes – Main door – 50% to be completed, wall tiling – 3rd to 13th floor 100% to be completed, Flooring – 4th to 10th floor 100% to be completed, Water proofing – 11th,12th – 50% to be completed, putty and painting – 10th to 16 th floor 2nd coat putty – 80% to be completed, primer after two coat putty till 14th floor to be completed, water proofing works – balcony and toilets – till 18th floors 100% to be completed, Handrails – Main stair 100% to be completed, balcony handrail 40% including glass portion to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 19th floor 100% to be completed, Firefighting final fixtures – 100% to be completed, Electrical wire pulling – 4th to 9th floor – 100% to be completed
- External Finishes – Windows & Sliding doors – 11th to 18th floor – 50% to be completed, External Plastering – 100% to be completed, External painting – E,A – 2 coat putty and one coat primer to be completed, plumbing duct line – till 19th floor to be completed
Work status as on 12-08-2023, we have completed the following.
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall completed, ramp completed, retaining wall – 40% completed, compound wall – 60% completed (42m), LMR Base slab completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – 70% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 8th floor (toilets) – 60% completed, Flooring – 3rd floor (A,B,C,D,E – 82% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (25% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 90% completed, 18th floor – 80% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 12th floor 100% completed), Door frame fixtures -completed, Handrails – 20% completed (firestair handrail GF to 14th floor completed, Main stair – GF to 2nd floor, 17th to 19th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed (till 12th floor, 13th floor – 60% completed , 14th,15th,16th floor – 20% completed, Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 50% completed, Electrical wire pulling – 3rd floor – 100% completed, 4th floor to 9th floor – 20% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 70% completed, one putty – 30% completed, 2nd coat – 15% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of AUGUST 2023.
- Structural Works – LMR roof to be completed, main and fire stair head room to be completed
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 19th floor 100% to be completed, GF to be completed
- Internal Finishes – Main door – 50% to be completed, wall tiling – 3rd to 13th floor 100% to be completed, Flooring – 3rd to 10th floor 100% to be completed, Water proofing – 11th,12th – 50% to be completed, putty and painting – 10th to 18 th floor 2nd coat putty – 80% to be completed, water proofing works – balcony and toilets – till 18th floors 100% to be completed, Haindrails – Main stair and Fire stair 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – till 17th floor – 100% to be completed, Firefighting final fixtures – 100% to be completed, Electrical wire pulling – 4th to 9th floor – 50% to be completed
- External Finishes – External Plastering – 100% to be completed, External painting – Damp proof – 90% to be completed, one putty – 50% to be completed, 2nd coat – 50% to be completed, plumbing duct line – 50% to be completed
Work status as on 12-07-2023, we have completed the following.
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 30% completed, compound wall – 40% completed (42m), LMR – 30% Completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 80% completed, Ground floor – 50% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 96% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 8th floor (toilets) – 15% completed, Flooring – 3rd floor (A,B,C,D,E – 82% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (25% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 90% completed, 18th floor – 80% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), 3rd,4th,5th floor 2nd coat putty completed, primer up to 18th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 10th floor 75% completed), Door frame fixtures – 97% completed (18th floor – completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed)
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 58% completed (till 12th floor, 13th floor – 25% completed), Corecutting – till 19th floor – 90% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 20% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 90% completed, 4th floor – 90% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2023.
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor 100% to be completed
- Internal Finishes – Water proofing – 11th,12th – 50% to be completed
Work status as on 06-06-2023, we have completed the following.
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 25% completed, compound wall – 40% completed (42m), LMR – 30% Completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Basement floor – 70% completed, Ground floor – 25% completed, Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 96% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 7th floor (toilets) – 15% completed, Flooring – 3rd floor (A,B,C,D,E – 82% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (23% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 80% completed, 18th floor – 50% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), 3rd,4th,5th floor 2nd coat putty completed, primer up to 18th floor completed, Water proofing – 39% completed (till 12th floor bathrooms only, balcony – upto 10th floor 75% completed), Door frame fixtures – 97% completed (18th floor – completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed))
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 58% completed (till 11th floor), Corecutting – till 18th floor completed, 19th floor – 50% completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 16th floor completed, vertical pipe line work – 15% completed
- External Finishes – Windows & Sliding doors – 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor,6th floor,7th floor – 75% completed, 8th, 9th, 10th – 30% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2023.
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – Ground floor to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor 100% to be completed
- Internal Finishes – Water proofing – 11th,12th – 50% to be completed
Work status as on 05-05-2023, we have completed the following.
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 25% completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 95% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 7th floor (toilets) – 15% completed, Flooring – 3rd floor (A,B,C,D,E – 80% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (20% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 80% completed, 18th floor – 50% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, Water proofing – 37% completed (till 12th floor bathrooms only, balcony – upto 8th floor 75% completed), Door frame fixtures – 95% completed (18th floor – completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed))
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 56% completed (till 10th floor), Corecutting – till 18th floor completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 15th floor completed, fire alarm work started
- External Finishes – Windows & Sliding doors – 3rd floor – 75% completed, 4th floor – 75% completed, 5th floor,6th floor,7th floor – 50% completed, 8th, 9th, 10th – 20% completed External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MAY 2023.
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – 19th floor 100% to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor to be completed
- Internal Finishes – Wall tiling – 8th, 9th floor 50% to be completed, Waterproofing – balcony 9th, 10th – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing work – 60% to be completed
- External Finishes – Windows & Sliding doors – up to 10th floor 80% to be completed
Work status as on 08-04-2023, we have completed the following.
- Structural Works – Pile cap – 82% completed, slab – 95% completed, swimming pool base slab completed, swimming pool wall – 60% completed, ramp completed, retaining wall – 25% completed
- Civil Works – Ceiling plastering – 100% completed (till 1st – 20th floor), Masonry – Block/ brick – 98% completed (till 19th floor Completed), Internal plaster – 1st floor – 90% completed, 94% completed (till 18th floor completed)
- Internal Finishes – Main door -sample flat only, Wall tiling – 3rd to 7th floor (toilets) – 14% completed, Flooring – 3rd floor (A,B,C,D,E – 80% completed), 4th, 5th, 6th, 7th, 8th, 9th floor (18% completed), putty works & Painting – putty 50% completed (till 9th floor 2 coat putty – completed, 10th to 16th floor one coat putty 90% completed, 17th floor – 80% completed, 18th floor – 50% completed, 1st Floor – 15% completed (2 coat primer, 2 coat putty), primer up to 18th floor completed, Water proofing – 37% completed (till 12th floor bathrooms only, balcony – upto 8th floor 75% completed), Door frame fixtures – 95% completed (18th floor – 80% completed), Handrails – 20% completed (firestair handrail GF to 14th floor completed, balcony handrail – frameonly – 70% completed))
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 56% completed (till 10th floor), Corecutting – till 16th floor completed, Centralised Gas piping system- mock up only, Firefighting final fixtures – horizontal pipe line till 15th floor completed, fire alarm work started
- External Finishes – Windows & Sliding doors – 3rd floor – 75% completed, 4th floor – 75% completed, External Plastering – 98% completed (B flat outside), A Flat outside – 92% completed, E Flat outside – 97% completed, C Flat outside – 99% completed, D flat outside – 90% completed, External Painting – primer – 60% completed, damp proof – 50% completed)
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application 100% completed, First coat painting 100% completed, Final coat painting 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2023.
- Structural Works – Amenities : Swimming pool wall – 80% to be completed, childrens play area, SHR, LMR to be completed
- Civil Works – Block work – 19th floor 100% to be completed, Inside plastering – 1st floor – 100% to be completed, 19th floor to be completed
- Internal Finishes – Wall tiling – 8th, 9th floor 50% to be completed, Waterproofing – balcony 9th, 10th – 80% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing work – 60% to be completed
- External Finishes – Windows & Sliding doors – up to 7th floor 80% to be completed
Click here to see the previous work progress updates.