ArtechArtech Palm Meadows

Project Description

A Sanctuary of bliss.. on every level!

Artech Palm Meadows is our 64th project, an integrated experience for living in harmony with the natural world. Where glimpses of landscaping are worked into the design of tower block to create pockets of recreational breathing spaces. Where spacious and well-appointed residences beckon you to live life to the fullest.

The 2 & 3 BHK homes are designed with careful thought. No wonder your personal living space is in harmony with personal style. Designed to let life flow, living large comes naturally. Take your pick from the multiple units plans on offer. Whichever home you choose – well-appointed interiors and the Artech stamp of quality assurance come standard!

Categories: ,

Quick Enquire

Take your first few steps towards finding the ultimate happiness of the Perfect Home.


Floor Plans

Amenities

  • Terrace Swimming pool with deck and seating
  • Full equipped Air – Conditioned Unisex Gym
  • Children’s Play Area
  • Rooftop party area
  • Plush Entrance lobby
  • Indoor Games Room
  • Multi purpose hall
  • Plush entrance lobby
  • Video door phone
  • Driver’s Dormitory
  • Furnished Guest Suite

Progress

 Work Schedule for the Month of July 2018

  • Pile chipping – 60nos to be completed (out of 148)
  • Pile cap work – 4nos to be completed (out of 14)
  • Column RCC work (Building) – 8 nos to be completed (out of 52)

Work status as on 05-06-2018, we have completed the following. 

  • Piling work – 100% completed
  • Pile chipping – 40 nos completed (out of 148)
  • Pile cap work – 1no completed (out of 14)
  • Column RCC work (Building) – 5 nos completed (out of 52)

 Work Schedule for the Month of June 2018

  • Piling work – 158 nos completed (out of 174)
  • Pile chipping – 9 nos completed (out of 148)
  • Pile cap work – 1no completed (out of 14)
  • Column RCC work (Building) – 5 nos completed (out of 52)

 As per the current work status from our site we are targeted to complete the following works by end of June 2018 

  • Piling work – 100% to be completed
  • Pile chipping – 18 nos to be completed (out of 148)
  • Column RCC work (Building) – 8 nos to be completed (out of 52)

As per the current work status from our site we are targeted to complete the following works by end of March 2018

  • Piling work -134 to be completed (out of 174)

Work status as on 1 3 -03 -2018, we have completed.

  • Piling work – 104 nos completed (out of 174)